Washtenaw County
Neutral Data Center Policies
Washtenaw County enacted a resolution directing staff to prepare data-center guidance, but it does not require anyone to follow it; the suggestions could add costs or delays if municipalities adopt them.
current law · County measureDirects county staff to prepare data-center guidance for local governments and urges them to require environmental and noise studies, public hearings, clean-energy and water-use measures, and protections for residents and infrastructure.Washtenaw County Resolution No. 26-054 (2026)
What this means
The resolution directs county staff to prepare guidance, but it does not itself require data centers or local governments to follow the suggested rules. Those suggestions could add costs or delays if municipalities adopt them, but the sources do not show that they have been made mandatory.
People behind it
- Washtenaw County Board of Commissioners
Adopted the data center resolution and directed county staff to develop outreach materials and an implementation plan.
- Jason Maciejewski
Proposed an amendment to the Washtenaw County data center resolution.
- Washtenaw County staff
Directed by the Board of Commissioners to develop informational materials and an outreach plan for local municipalities.
Show 3 more peopleShow fewer people
- Washtenaw County Environmental Council
Assigned to review and provide input on the county’s data center outreach materials.
- Washtenaw County Resiliency Office
Produced the preliminary municipal data center planning toolkit and led collaboration with local governments.
- Jimmy Wilson Jr.
Sponsored the state bill endorsed by the county that would rescind $100 million in funding for the University of Michigan–Los Alamos project.
Restrictions & requirementsHide restrictions & requirements13
Require applicants to submit water-use and water-source data, energy-use and energy-source data, an environmental impact statement, and a noise and low-frequency-vibration study before approval
Require at least two accessible, well-publicized public hearings before approval, with the required studies and data released beforehand
Require operators to publish Water Use Effectiveness measurements at least quarterly
Require operators to source 100% of their energy from wind, solar, battery, or geothermal sources
Prohibit water-wasteful evaporative cooling technology
Require developers and operators to pay their fair share of energy consumption exceeding their own energy sources
Require developers and operators to pay for grid infrastructure, including new or additional electrical substations
Require union agreements and local hiring targets
Require setbacks for data-center buildings, associated substations, and backup generators, along with noise- and low-frequency-vibration protections
Require developers and operators to fund extra first-responder services and initial and ongoing infrastructure costs
Ypsilanti imposed a 60-day emergency moratorium and a separate 365-day moratorium on data centers
The county encouraged local municipalities to enact data-center moratoriums
Saline Township's consent judgment allowed a specific data-center project to proceed only subject to conditions concerning water and sewer service, road improvements, setbacks, noise standards, decommissioning, tax-abatement cooperation, and financial contributions for farmland preservation, community projects, and fire departments.
Benefits & exceptionsHide benefits & exceptions3
Planned unit developments (PUDs) may allow data centers to be evaluated and approved through a negotiated process instead of strict compliance with base-zoning requirements, with customized standards for issues such as water, energy, noise, setbacks, decommissioning, and workforce development.
Saline Township's October 2025 consent judgment allows the Related Digital data-center project to move forward, subject to conditions concerning water and sewer service, road improvements, setbacks, noise, decommissioning, tax-abatement cooperation, and financial contributions.
Augusta Township approved rezoning 522.2 acres for a proposed data center, while the remainder of the more-than-800-acre site was already zoned general industrial.