Sharon Township
This restriction takes precedence while in effect. The rating below excludes temporary restrictions.
Neutral Data Center Policies
Sharon Township has enacted a temporary pause on data-center applications, permits, and site plans, delaying new construction and expansion for up to 12 months or until sufficient rules are adopted.
Rating from Washtenaw County as there are no scored current or future laws outside temporary restrictions for Sharon Township.
current law · Sharon TownshipPauses acceptance and processing of permits and site plans for data centers in Sharon Township until February 5, 2027, or until the township adopts sufficient regulations, whichever comes first.Sharon Township Resolution No. 2026-02-05-01 (2026)
What this means
The measure would pause acceptance and processing of data-center applications, permits, and site plans for up to 12 months, or until the township adopts sufficient rules. That would significantly delay new construction and expansion, though it is temporary rather than a permanent ban.
People behind it
- Trustee Cooper
Moved the resolution for adoption.
- Treasurer Brickley
Seconded the motion to adopt the resolution.
- Sharon Township Board of Trustees
Adopted the resolution.
Show 1 more peopleShow fewer people
- Michelle Mrocko
Sharon Township Clerk who certified the board’s adoption.
Restrictions & requirementsHide restrictions & requirements2
Twelve-month moratorium on acceptance and processing of data center applications, permits and site plans.
Prevails over conflicting ordinances.
Benefits & exceptionsHide benefits & exceptions1
Moratorium may end early upon Board determination of sufficient regulations; conditional relief, not an affirmative approval right.
Sources
Data provided by Regbase · Cookie preferences · Report missing data