City of Ypsilanti

This restriction takes precedence while in effect. The rating below excludes temporary restrictions.

Neutral Data Center Policies

Ypsilanti enacted a temporary pause on data-center development for up to 365 days; meeting minutes also describe a 60-day hold on new zoning permits, not a permanent ban.

Rating from Washtenaw County as there are no scored current or future laws outside temporary restrictions for City of Ypsilanti.

current law · City of Ypsilanti
Temporarily prohibits new zoning permits for data centers in Ypsilanti for 60 days; the council also approved a separate resolution imposing a 365-day moratorium.City of Ypsilanti Resolution No. 2026-046A and Ordinances Nos. 1457, 1461 and 1472 (2026)

What this means

The council approved a temporary 365-day moratorium on data centers, which would pause data center development for a year. The minutes also describe a 60-day hold on new data-center zoning permits, so the measure would create a substantial delay rather than a permanent ban.

Timing

Ends
60 days after adoption; alternatively, 365 days under Resolution No. 2026-046A

The meeting minutes record approval of Ordinance No. 1457 imposing a 60-day moratorium on new data-center zoning permits and also approval of an alternate 365-day moratorium resolution. The sources do not clarify which measure controls.

People behind it

  • Moved to approve Ordinance No. 1457 imposing a 60-day data-center zoning moratorium and proposed the alternate 365-day moratorium resolution.

  • Seconded the motion to approve Ordinance No. 1457 imposing a 60-day data-center zoning moratorium.

  • Seconded the motion to add the alternate data-center resolution and co-sponsored its consideration.

Show 1 more peopleShow fewer people
  • Seconded the motion to approve Resolution No. 2026-046A imposing a temporary 365-day moratorium on data centers.

Restrictions & requirementsHide restrictions & requirements2
  • An emergency 60-day moratorium prohibits issuing new zoning permits for data centers. (emergency moratorium ... for 60 days)

  • A separate temporary 365-day moratorium was approved for data centers. (temporary 365-Day moratorium on data centers)