City of Grandview

Neutral Data Center Policies

Johnson County’s enacted resolution urges Texas officials to study and consider future data-center rules, especially safeguards against water-intensive cooling, but imposes no enforceable project requirements.

Rating and summary from Johnson County as there are no scored current or future laws outside temporary restrictions for City of Grandview.

current law · City of Grandview
Sets general M-2 industrial-district rules that would apply to data centers there, including requirements for enclosed operations and limits on noise, emissions, and storage.Grandview zoning ordinance—M-2 Heavy Manufacturing/Industrial District (Code §56-445)
Restrictions & requirementsHide restrictions & requirements7
  • If a data center is a permitted M-2 use, business, servicing, and processing activities generally must take place inside completely enclosed buildings, subject to exceptions for parking, loading, merchandise display, and drive-in establishments. Enclosed-building requirement

  • Storage within 100 feet of a residential district—except operable motor vehicles—must be indoors or screened by a barrier 6 to 8 feet high. Storage within 50 feet of the screening cannot exceed its height. Storage and screening limits

  • M-2 operations must meet applicable state and federal standards for smoke, particulate matter, and radiation. Dust, odor, gas, fumes, glare, or vibration cannot reach a concentration at or beyond the property line that harms public health, safety, or welfare or damages property. Operating performance standards

  • Noise must not be objectionable because of intermittence, beat frequency, or shrillness; sound at the property line may not exceed 75 dB(A) for more than 15 minutes in any one hour. Noise limits

  • Manufacturing or processing may not emit water pollution. If potential hazards exist, safeguards acceptable to the relevant state and national health and environmental agencies must be installed before a certificate of occupancy is issued, and the applicant must establish that they are acceptable. Water-pollution safeguards

  • A use listed as a specific use in the referenced use schedule is permitted in M-2 only when granted in accordance with section 56-765. The excerpt does not establish whether data centers fall in that category. Specific-use approval

  • Other manufacturing or industrial uses that do not meet the general definition for manufacturing processes may be permitted by the city council only after a public hearing and review of their operational characteristics and other relevant community-welfare information. The excerpt does not establish whether this applies to data centers. Council review and public hearing

Sources