Borough of Waymart

Anti-Data Center Policies

Waymart Borough does not specifically ban data centers, but an unlisted use requires Borough Council review, creating uncertainty and possible delay; conditional-use review may also consider effects on neighbors, traffic, and public services.

current law · Borough of Waymart
Regulates data centers under general zoning rules, but does not specifically mention or set data center-specific requirements.N/A — No data center-specific laws, ordinances, or bans identified for Waymart Borough

What this means

The rules do not specifically ban data centers, but an unlisted use must be reviewed by the Borough Council, which adds uncertainty and potential delay (unlisted uses). If treated as a conditional use, it also faces review of its effects on neighbors, traffic, and public services (conditional-use criteria).

People behind it

  • Adopted the zoning ordinance.

  • Listed as the Zoning/Building Permit Officer; the ordinance assigns the Zoning Officer responsibility for enforcing its provisions.

Restrictions & requirementsHide restrictions & requirements11
  • A zoning permit is required before construction, additions or alterations, or a change in land or building use. Applications must include a plot sketch and the permit depends on compliance with applicable regulations; a permit expires after 24 months. A zoning permit shall be required and become void twenty-four (24) months

  • If a data center is classified as a conditional use, it requires review by the Borough planning agency and approval by Borough Council. Approval depends on standards addressing neighborhood effects, traffic, public services and utilities; the Borough may impose additional conditions. approval by the Waymart Borough Council and impose such conditions

  • If a new use or addition generates more than 250 vehicle trip ends per day, it is a major traffic impact development and a conditional use. It generally must have direct access to U.S. Route 6 or State Route 296 and 500 feet of clear sight distance in both directions. An exception allows access from a non-collector street if the developer agrees to improve or finance improvements to collector-road standards. more than 250 trip ends per day and direct access to U.S. Route 6

  • For a major traffic impact development generating at least 750 vehicles per day, an applicant must submit a transportation impact report before conditional-use approval or preliminary subdivision approval. If the study projects road or intersection capacity deficiencies, the development cannot be permitted unless the applicant addresses the needed improvements or provides a financial guarantee. ADT of 750 vehicles or more and provides a financial guarantee

  • Major traffic impact developments must provide 100-foot setbacks for wooded yards or 150-foot setbacks for unwooded yards, applying to front, side and rear yards. a setback of 100 feet and 150 feet if the yard is not wooded

  • For a conditional commercial, manufacturing or other nonresidential use, specified operating standards include a 65-decibel day-night average sound-level limit at the property line, no vibration detectable there without instruments, and restrictions on glare, smoke and harmful or excessive air pollution. Where the use adjoins a residence or specified residential district, side and rear yards must be at least 50 feet with a six-foot solid-fence or dense-evergreen buffer. shall not exceed 65 decibels and minimum side and rear yards shall be increased to 50 feet

  • A major traffic impact development also requires a report assessing noise, glare and security. A public hearing is mandatory for these developments. a public hearing shall be mandatory and report assessing the impact

  • In a floodplain overlay, development is prohibited unless it fully complies with the Borough Floodplain Ordinance. no development shall be permitted

  • A certificate of use must be issued before vacant land or a newly built, structurally altered or change-of-use structure is occupied or used. shall be occupied or used until a certificate of use

  • Applicable zoning-permit, special-permit, conditional-use or variance fees must be paid in full before the permit, conditional use or variance is issued; the ordinance does not specify the fee amounts. fees, charges and expenses and fees have been paid in full

  • Where applicable, nonresidential parking and loading areas and their circulation or service lanes must be set back at least 20 feet from the edge of a public thoroughfare and adjoining property lines. Commercial, office, manufacturing, wholesale, hospital or similar buildings must also provide loading space at least 60 feet deep, 12 feet wide and 14 feet high. buffer zone at least 20 feet and 60 feet in depth, 12 feet in width

Benefits & exceptionsHide benefits & exceptions5
  • Principal permitted and accessory uses receive permits as a matter of right if they meet the ordinance’s standards. The ordinance does not identify data centers specifically, so this benefit depends on a data center being classified as a permitted use in the applicable district. permits ... shall be issued as a matter of right

  • If a proposed use is neither expressly permitted nor denied, the Borough Council determines whether it is allowed by comparing it to uses named in the ordinance, and may classify it as permitted, conditional, or accessory. This provides a route for consideration, not an automatic approval. Whenever any proposed use is neither specifically permitted nor denied

  • A legally established nonconforming use may continue normal maintenance and repair, including interior renovations that do not structurally alter the property, increase its use, or change the nature of the use. Normal maintenance and repair activities

  • Changes, additions, or expansions of a qualifying nonconforming use may be approved as conditional uses, subject to limits including no further violation of yard or height rules, no increase in certain outdoor storage, and compliance with parking and traffic requirements. Expansion onto another property is limited to an immediately adjacent property of record, and some expansions may be prohibited. All changes and additions to nonconforming uses

  • A nonconforming use may be re-established within 18 months after discontinuance or vacancy; the ordinance allows an extension where proven necessary. within a period of 18 months

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data