Town of Salisbury
Anti-Data Center Policies
Salisbury’s zoning rules do not specifically allow data centers, so approval may be difficult or require a zoning change; ordinary site, access, and environmental requirements also apply.
current law · Town of SalisburyDoes not specifically regulate data centers; any proposal would be subject to the town’s general zoning rules.Salisbury Zoning Regulations (effective March 2, 2026)
What this means
The regulations do not specifically list data centers as an allowed use, and uses not allowed in a zone are prohibited; the Commission decides how to interpret uncertain uses (unlisted uses are prohibited). This could make approval difficult or require a zoning change, while ordinary site, access, and environmental requirements add further hurdles; the document provides no special incentives for data centers.
People behind it
- Planning and Zoning Commission
Adopted the zoning regulations and is responsible for administering them.
Restrictions & requirementsHide restrictions & requirements7
Use must be authorized in the zone: uses not allowed as a permitted or Special Permit use are prohibited. Data centers are not expressly named in the use tables, so whether one is allowed depends on how the Commission classifies the proposed use. Uses not allowed are prohibited.
A zoning permit is required before a building or structure is erected, added to, or changed in exterior dimensions, or a regulated use is established or changed. Required approvals from other agencies must be obtained before the zoning permit is issued. No building or structure shall be erected.
If the proposed use requires Site Plan or Special Permit approval under the use tables, the project must undergo that review; a Special Permit requires a public hearing and review against the regulation’s standards. The applicable permit depends on the Commission’s classification of the use. The Commission shall hold a public hearing.
Development must meet the dimensional requirements for its zone, including applicable minimum lot area, setbacks, building coverage, and height limits; overlay districts can impose additional, more restrictive requirements. Overlay requirements are in addition.
A Sedimentation and Erosion Control Plan is generally required when cumulative disturbed area exceeds one-half acre, and may be required for smaller disturbances. In C20, CG20, and LI zones, a Site Plan also requires a Stormwater Management Plan if lot impervious surface exceeds 20% or the proposal disturbs more than one-half acre. Excavation, filling, or grading generally requires a Special Permit, subject to stated exceptions, including qualifying construction excavation with no more than 250 cubic yards removed. more than one-half (1/2) acre.
A new or substantially improved parking lot with 30 or more spaces must include EV-charging infrastructure in at least 10% of its spaces; substantial improvement means paving, repaving, or reconfiguring 50% or more of an existing lot. thirty or more parking spaces.
Work under an approved Site Plan must generally be completed within five years. The Commission may grant extensions, but the total completion period cannot exceed ten years from approval. completed within five (5) years.