Town of Norfolk

This restriction takes precedence for the map color while in effect.

Pro-Data Center Policies

Norfolk allows data centers only in its Commercial/Industrial zone, with a special permit, site-plan review, and a public hearing, limiting where they can be built and adding time and cost.

Rating from Connecticut statewide as there are no scored current or future laws outside temporary restrictions for Town of Norfolk.

current law · Town of Norfolk
Restricts data processing centers to the Commercial/Industrial zone, where they require a special permit; they are not allowed in the other business zones.Norfolk Zoning Regulations (Effective January 1, 2024)

What this means

Data centers are allowed only in the Commercial/Industrial zone and require a special permit, so they cannot be built in the other business zones. The permit process includes site-plan review and a public hearing, creating significant limits and added time and cost.

Timing

The amendment history lists a moratorium on medical marijuana production and dispensing, but does not state when or how it expires.

People behind it

  • Adopted the zoning regulations and is responsible for administering and enforcing them.

  • The Commission’s authorized agent for administering and enforcing the regulations.

Restrictions & requirementsHide restrictions & requirements9
  • Data processing centers are not allowed in the Village Business or Retail/Business zones; they require a Special Permit in the Commercial/Industrial zone. Principal uses not expressly allowed in a district are prohibited, so a data processing center is also prohibited as a principal use in residential zones. Data processing centers not expressly allowed

  • A Special Permit application generally must include a Site Plan and a written description of the proposed use, and the Commission must hold a public hearing. The Site Plan exception applies if the ZEO finds there are no physical changes and a Site Plan is unnecessary; interior renovations in previously approved space may also avoid a Special Permit if the use is allowed, there are no exterior changes, and no additional parking is required. Site Plan application public hearing

  • The applicant must show that the applicable Special Permit criteria are satisfied, including neighborhood compatibility, traffic and access, utilities, nuisance avoidance, and consistency with the Plan of Conservation and Development. The Commission may impose reasonable conditions; the permit authorizes only the approved use, its conditions bind the property, and noncompliance can lead to revocation. Special Permit criteria burden of demonstrating

  • In the Commercial/Industrial zone, the dimensional standards require at least 2 acres and 200 feet of street frontage; setbacks are 75 feet from the front property line, 40 feet from other property lines, and 100 feet from a residential-zone boundary. Maximum ground coverage is 20%, and maximum building height is 3 stories or 45 feet. Commercial/Industrial standards

  • Parking and loading must be adequate and provided on the same lot, except in the Village Business area. For uses not listed in the parking table, the Commission determines the required parking in proportion to expected use. Uses not listed

  • Special Permit proceedings have statutory processing deadlines: the hearing must begin within 65 days of receipt, conclude within 35 days after it begins, and the decision is due within 65 days after the hearing concludes. The applicant may consent to extensions totaling up to 65 days. within sixty-five (65) days

  • The Commission may retain outside technical consultants at the applicant’s expense if the proposal may significantly affect Norfolk and staff cannot complete a timely review or the proposal requires expertise unavailable from staff. The applicant must pay the estimated review costs, and permits cannot issue until processing fees are paid. at the applicant’s expense

  • Exterior lighting for business and industrial uses must use specified cut-off or shielded fixtures, with no direct light source visible at the property line. Unless modified by the Commission, parking, display, aesthetic, and sign lighting must be off outside operating hours and the one-hour transition period; security lighting must be triggered and shut off after five minutes. full cut-off type fixtures

  • The Commission may not approve a Special Permit for a property with an existing zoning violation unless the application will remedy that violation. existing zoning violation

Benefits & exceptionsHide benefits & exceptions1
  • Data processing centers may be approved by Special Permit in the Commercial/Industrial zone; they are not listed as allowed in the Village Business or Retail/Business zones. Data processing centers