Uinta County

Neutral Data Center Policies

Uinta County approved a specific data center project, with construction required within five years and annual inspections, public water-use reporting, road upkeep, and noise and lighting limits.

current law · County project: Prometheus Wyoming I LLC data center project in Section 13, T15N, R119W
Uinta County approved Prometheus Wyoming I LLC's data-center conditional-use permit on June 16, 2026, subject to 15 conditions.Wyoming Uinta County Prometheus Wyoming I LLC Conditional Use Permit CUP 26-01 (2026)

What this means

The measure enables a specific data center by approving its conditional use permit and industrial subdivision, but it also adds project requirements. These include a five-year construction deadline, annual county inspections, public water-use reporting, road upkeep, and noise and lighting limits (permit conditions). Overall, it modestly supports development while adding meaningful responsibilities for this project.

People behind it

  • Applicant for the Conditional Use Permit for the construction and operation of a Data Center.

  • Approves the permit with all 15 conditions.

Restrictions & requirementsHide restrictions & requirements8
  • Requires compliance with both the Wyoming Industrial Siting Act and Uinta County’s Land Use Plan.

  • Requires dust abatement in accordance with Wyoming Air Quality Standards and Regulations.

  • Requires reporting of annual onsite water consumption.

  • Makes the developer responsible for upkeep, maintenance and repair of two county roads.

  • Requires compliance with DarkSky International Standards to avoid light pollution.

  • Caps operational noise at the boundary at no greater than 60 dBAs.

  • Requires reimbursement for applicable emergency services rendered.

  • The permit may be revoked, suspended, or enforced by the County for a material violation.

Benefits & exceptionsHide benefits & exceptions2
  • Authorizes the site-specific data center: commissioners voted to approve the CUP with all 15 conditions.

  • Allows time for development: construction must begin within five years.