Burnett County

Anti-Data Center Policies

Burnett County’s ordinance is labeled enacted, though its description uses future wording; it requires rezoning for projects of at least 40 acres and permits and conditions for facilities over 1 megawatt, creating a barrier, not a ban.

current law · County measure: Areas subject to county zoning; excludes incorporated villages and the towns of Blaine, LaFollette, Sand Lake, and Wood River, except that the I-2 rules apply in shoreland-zoning areas
The Burnett County Sentinel reports that the County Board unanimously approved a new I-2 floating zoning district.Burnett County I-2 Tech-Energy Industrial District Ordinance (2026)

What this means

The rules would make large data centers harder to site and operate: projects need at least 40 acres rezoned, and facilities over 1 megawatt need a conditional-use permit and must meet requirements such as noise limits, monitoring, water planning, and solar panels on 75% of roofs and parking areas (approval steps and project conditions). Smaller facilities are treated more lightly, so this is a significant barrier rather than a ban.

People behind it

  • Developed and reviewed the proposed I-2 zoning district and recommended it to the County Board.

  • Burnett County Land Services Department director who worked on the draft ordinance and compiled its proposed solar-panel requirement.

Restrictions & requirementsHide restrictions & requirements9
  • A project must first obtain rezoning of at least 40 acres into the floating I-2 district. Rezoning requires a full County Board vote and, where applicable, town approval; outside shoreland areas, the affected town can veto it. (rezone at least 40 acres)

  • Facilities larger than 1 megawatt need a conditional use permit and a public hearing, in addition to the I-2 rezoning. Facilities of 1 megawatt or less may be permitted in the district without that separate hearing. (larger ones would also need a conditional use permit)

  • Buildings must be at least 300 feet from property lines. (at least 300 feet from property lines)

  • Noise is limited to 55 decibels during the day and 45 decibels at night, measured at the property line. (55 decibels by day and 45 at night)

  • Noise, vibration and groundwater must be tested before construction and at least twice yearly afterward; testing must be done by a county-approved independent third party. (testing be done by a county-approved independent third party)

  • Operators must have a metered water-use plan. (a metered water-use plan)

  • Projects must have community benefit and development agreements, which can require contributions such as support for emergency response or road maintenance. (community benefit and development agreements)

  • Solar panels are required on 75% of data center roofs and parking areas. (Solar panels on 75% of data center roofs and parking areas)

  • A decommissioning plan is required. (A decommissioning plan)

Benefits & exceptionsHide benefits & exceptions1
  • In the I-2 district, data centers of 1 megawatt or less may be approved by the zoning office without a separate hearing, once the property has been rezoned into the district. The smaller-scale uses provision

Sources