Chesterfield County limits new data centers to two employment districts and requires case-by-case conditional-use approval. Previously approved projects may proceed, but new development or expansion needing zoning approval faces significant barriers.
current law · County measureChesterfield County's ZOMod ordinance was adopted September 17, 2025, effective January 1, 2026.Virginia ZO-2025-001 (2025)
What this means
New data centers would be limited to two employment districts and require conditional-use approval, so projects face a narrower choice of sites and case-by-case review. Previously approved projects can proceed, but the change creates a significant barrier for new development and expansion requiring new zoning approval.
People behind it
- Chesterfield County Board of Supervisors
Voted unanimously to approve the ordinance update.
- Chesterfield County Planning Commission
Recommended approval in July.
Restrictions & requirementsHide restrictions & requirements3
Eliminates development by-right of new data center projects.
Limits approval to EC and EG under the Data Center use matrix.
The legacy-zoning grace period is not provided to data center projects.
Benefits & exceptionsHide benefits & exceptions2
Recognizes Data Center as a defined use, including supporting infrastructure.
Retains a conditional-use approval path in EC and EG: allowed only in those districts as a conditional use.