City of Weslaco

Mixed Data Center Policies

Texas offers substantial tax breaks on equipment and electricity to large projects meeting investment and job requirements, while large grid connections face studies, fees, and possible emergency power cuts; some requirements apply only to very large loads.

Rating and summary from Texas statewide as there are no scored current or future laws outside temporary restrictions for City of Weslaco.

failed · City of Weslaco
Requires a proposed data center, if treated as an unlisted use, to undergo city review for zoning classification; the ordinance contains no data-center-specific rules.No data-center-specific Weslaco regulation identified

What this means

The rules do not specifically ban data centers, and industrial-zoned land can host a broad range of uses. But because data centers are not listed, the city may need to classify them as a new use, and some industrial activities require City Commission approval, adding uncertainty and potential delay (new or unlisted uses; industrial-use approvals).

People behind it

  • Adopts zoning amendments and changes by ordinance, after the required review and hearing process (“amend, supplement, or change by ordinance”).

  • Reviews proposed zoning amendments and makes recommendations and reports to the City Commission (“submit the same to the city planning commission for its recommendation and report”).

  • Has administrative duties under the ordinance, including referring new or unlisted land uses for zoning classification review (“shall refer the question concerning any new or unlisted use”).

Show 1 more peopleShow fewer people
  • Is responsible for enforcing the zoning ordinance and refusing permits for violations (“duty of the building inspector to enforce the provisions”).

Restrictions & requirementsHide restrictions & requirements6
  • A data center must be allowed in the property's zoning district; buildings and land may not be used for purposes not permitted in that district. If the proposed data-center use is unlisted, the planning director refers it to the Planning and Zoning Commission, which recommends a classification to the City Commission for determination by ordinance. District-permitted uses Unlisted uses

  • In the industrial district, certain uses require City Commission approval following a Planning and Zoning Commission recommendation before a building or occupancy permit may issue. The listed uses include manufacturing or processing, unscreened outside storage, laboratories, public utilities, and warehousing and storage; this requirement applies if a data-center proposal is classified as one of those uses. Industrial-district approval

  • Building permits for land improvements or building construction, alteration, or enlargement require a scaled plat showing the lot and building dimensions and location, a written statement of the intended use, and any other information the building inspector requires. Permits expire if unclaimed for six months after approval, and issued permits expire after one year, subject to the stated renewal provision. Permit application requirements Permit expiration

  • A certificate of occupancy and compliance is required before a building or premises may be used or occupied, including after new construction or structural alteration. Certificate required before use

  • District-specific height, yard, lot-area, lot-coverage, and parking rules apply to development; construction must conform to the requirements for the property's zoning district. Area and parking conformity

  • Property in the airport hazard zoning district requires an airport hazard zoning district development permit to establish compliance. A variance may require an FAA determination and review by the Airport Advisory Board. Some structures under 75 feet are exempt from a height permit in specified horizontal, conical, and approach-zone circumstances, but not from applicable height limits or other requirements. Airport hazard permit Variance requirements Height-permit exceptions