City of Temple
Pro-Data Center Policies
Temple allows large data centers in light and heavy industrial zones and small ones in those zones and commercial areas, with parking requirements that may add manageable obligations.
current law · City of TempleDefines small and large data centers, specifies which Temple zoning districts allow them by right or require a conditional use permit, and sets their parking requirements.Ordinance No. 2021-0065-O (FY-21-5-AMND), amending Temple Unified Development Code—large and small data center definitions, zoning, conditional-use permissions, and parking
What this means
The measure would make data centers easier to site in industrial districts: large centers would be allowed by right in light and heavy industrial zones, and small centers also in commercial zones (district rules). It also adds parking requirements, but these appear manageable, so the overall effect is a meaningful, though not major, benefit.
People behind it
- City Staff
Proposed the amendments (“City Staff has proposed amendments”).
Restrictions & requirementsHide restrictions & requirements5
Large data centers require a conditional use permit in Commercial (C) districts; they are permitted by right in Light Industrial (LI) and Heavy Industrial (HI) districts. The ordinance’s large-data-center zoning rules
Small data centers require a conditional use permit in General Retail (GR) districts; they are permitted by right in C, LI, and HI districts. The ordinance’s small-data-center zoning rules
Data centers must provide parking based on area or staffing: office/administrative space requires one space per 600 square feet of gross floor area or one per two employees, whichever is greater; equipment area requires one per 25,000 square feet; and storage or warehousing requires one per 5,000 square feet or one per two employees, whichever is greater. The data-center parking ratios
Parking areas must be paved with asphalt or concrete and maintained; alternative paving materials require approval by the Director in consultation with the City Engineer. A driveway connecting the parking area to a street or alley is also required. The parking-area paving and driveway requirements
Off-street parking for nonresidential uses must allow drivers to exit without backing into a public street, right-of-way, or alley, except in the Central Area (CA) district; the Director may grant an exception when the request demonstrates consistency with public-safety best practices and the Comprehensive Plan. The parking-exit rule and exception
Benefits & exceptionsHide benefits & exceptions2
Data centers may be permitted by right in several commercial and industrial districts: large data centers in Light Industrial and Heavy Industrial districts, and small data centers in Commercial, Light Industrial, and Heavy Industrial districts. Large data centers require a conditional use permit in Commercial districts; small data centers require one in General Retail districts. Large data-center zoning rules Small data-center zoning rules
The measure establishes data-center parking ratios: one space per 600 square feet of office/administrative area or per two employees, whichever requires more spaces; one per 25,000 square feet of equipment area; and, if applicable, one per 5,000 square feet of storage/warehousing or per two employees, whichever requires more spaces. Data-center parking ratios
Sources
pending · City of TempleRestricts principal data centers to industrial zones and requires permits, a 200-foot setback from single-family homes, noise and traffic controls, water-efficient cooling, and utility service agreements.Ordinance No. 2026-0050-O, amending Temple Code of Ordinances Chapter 38 to require utility service agreements
What this means
The proposed rules would add meaningful steps and costs: data centers need a conditional use permit, must meet a 200-foot setback, and face noise and traffic studies and possible required road improvements. They do not ban projects, and city staff said some requirements were already included in development agreements, which limits the added burden (permit and development standards).
Restrictions & requirementsHide restrictions & requirements9
Principal data centers are limited to light-industrial and heavy-industrial zoning districts. The new rules limit where principal data centers may be located
Principal data centers must obtain a conditional use permit, through which the city may impose additional project- and location-specific requirements. Principal data centers must obtain a conditional use permit
Projects must meet development standards addressing residential compatibility, noise, traffic, lighting, landscaping, screening, and water-efficient cooling. The standards cover these development impacts
A data center must be set back at least 200 feet from single-family residential property. The regulations include a minimum 200-foot setback
Loading areas, generators, cooling equipment, substations, transformers, and service areas must be positioned to maximize separation and buffering from residential areas. Equipment and service areas must maximize separation
Before building permits are issued, a project must submit a noise-mitigation plan prepared by an acoustical engineer; acoustical testing is required after construction and before each phase can be occupied. Noise plans and testing are required
Principal data centers must start with a preliminary traffic study covering construction and operating traffic, deliveries, emergency and site access, and nearby intersections and roads. A preliminary traffic study is required
City-required transportation improvements must be built, funded, or financially guaranteed before a certificate of occupancy is issued. Transportation improvements must be secured before occupancy
Utility service agreements are required for certain industrial developments and special utility projects. The agreements may set water-use limits, require remote monitoring, and require developers to fund needed utility improvements. Agreements may impose water and infrastructure obligations
Benefits & exceptionsHide benefits & exceptions1
The code creates a route for principal data centers to be built in light- or heavy-industrial districts, subject to a conditional use permit. The permit is not automatic, and projects must meet requirements including a 200-foot residential setback and noise and traffic standards. limited to light industrial and heavy industrial zoning districts
Sources
pending · City of TempleRequires future data center projects in Temple to obtain a Conditional Use Permit, allowing public review and project-specific conditions before approval.Ordinance No. 2026-0051-O (FY-26-11-AMND), amending the Temple Unified Development Code—Data Center and Data Center-Accessory Use standards
What this means
Requiring a conditional use permit even where data centers are otherwise allowed adds public review and may require extra studies and project-specific conditions, creating meaningful costs or delays (permit requirement). The proposed noise, water-efficiency, parking, and accessory-use rules add safeguards and constraints, but the measure does not ban data centers (proposed code updates).
People behind it
- City of Temple
Proposed the Unified Development Code amendments establishing updated data-center review and permitting rules.
Restrictions & requirementsHide restrictions & requirements3
Future data center projects would need a Conditional Use Permit, even in zoning districts where data centers are otherwise permitted, adding public review before proceeding. The permit requirement
The City could impose project-specific conditions and require technical studies and supporting documentation before a project moves forward. Project-specific conditions and studies
Developments in industrial zones and special utility projects would be required to enter utility service agreements. The utility-agreement requirement
Benefits & exceptionsHide benefits & exceptions2
Rowan tax-abatement agreements provide a financial incentive. The supplied material does not state the abatement amount, duration, or detailed conditions. Rowan Temple Tax Abatement Agreement
Utility service agreements create a way to arrange utility services for covered industrial developments and special utility projects, with negotiation authority delegated to the City Manager. The requirement applies only to specified developments and zoning districts; it does not guarantee service. Utility service agreements for certain developments