Loading map…

City of Spring Valley Village

Mixed Data Center Policies

Texas offers substantial tax breaks on equipment and electricity to large projects meeting investment and job requirements, while large grid connections face studies, fees, and possible emergency power cuts; some requirements apply only to very large loads.

Rating and summary from Texas statewide as there are no scored current or future laws outside temporary restrictions for City of Spring Valley Village.

failed · City of Spring Valley Village
Restricts data centers in Office Building District B to uses that qualify as office buildings or their accessory uses; it does not specifically regulate data centers.No data-center-specific law or ban identified in Spring Valley Village, Texas

What this means

The district allows office buildings and accessory HVAC and power facilities, which may accommodate some data center projects, but it does not expressly name data centers as a permitted use. The limits on lot coverage and building area and required traffic review add meaningful constraints and planning burden.

People behind it

  • The City administers and enforces its codes, including the zoning regulations.

Restrictions & requirementsHide restrictions & requirements10
  • In Office Building District “B,” an 80-foot setback applies between the district boundary with Dwelling District “A” and the nearest building or structure; the adjoining 50 feet must remain in its natural state, with no construction except a fence and no parking or storage. The 80-foot building setback

  • Building height is capped at 54 feet. On lots abutting Dwelling District “A,” height is limited to 40 feet at the 80-foot building line and may increase by one foot for each two feet farther away, up to 54 feet and four stories above finished grade. No building shall exceed fifty-four (54) feet

  • Roof appurtenances such as antennas, cooling towers, and mechanical-equipment enclosures are generally limited to 10 feet above the roof and must be at least 10 feet from the building’s exterior wall; elevator equipment may receive additional height. Mechanical equipment may cover no more than 20% of the roof, and architectural screens must reach the equipment’s top height. Mechanical equipment shall not cover more than twenty (20) percent

  • Buildings generally must be set back at least 30 feet from tract, lot, property, and street lines; the minimum is 40 feet from a Major Thoroughfare and 50 feet from I-10 or its adjacent public access road. at least thirty (30) feet

  • Construction, including buildings, parking lots, parking garages, and streets, may not exceed 75% of the lot area. shall not exceed seventy-five (75) percent

  • An office building’s gross building area may not exceed 0.64 square feet per square foot of lot area. sixty-four hundredths (.64)

  • Outdoor lighting must be located, screened, or shielded so adjacent residential lots or structures are not directly illuminated. A parking garage less than 160 feet from an occupied Dwelling District must be screened on the side facing that district. not directly illuminated

  • Before development approval, the applicant must submit a traffic impact analysis to the Planning and Zoning Commission and City Council. It must address projected traffic, roadway capacity and impacts, needed public improvements, and their costs; the analysis is not determinative of whether a building permit is issued. no development shall be approved

  • A free-standing wood or masonry fence or wall at least 8 feet high must run along the entire property line bordering Dwelling District “A.” Commercial construction or expansion adjoining that district cannot proceed until the fence or wall is erected. Plans must be submitted for a building permit, inspection fees apply, and owners must maintain the barrier; after certified notice of needed maintenance, they have 60 days to repair, rebuild, or replace it. not less than eight (8) feet in height

  • The district prohibits storage, handling, processing, or manufacturing of materials dangerous because of explosive, inflammable, radioactive, or other dangerous qualities. It also prohibits manufacturing, commercial, or industrial activity harmful to adjoining residents or property through odors, dust, fumes, gas, smoke, noise, or airborne particles. dangerous by reason of explosive

Benefits & exceptionsHide benefits & exceptions2
  • Office buildings for business and professional use are permitted, including for scientific, research and development, and similar purposes. The section does not specifically name data centers, so whether a data center qualifies would depend on its classification under this permitted use. Office buildings for business and professional use

  • HVAC equipment and auxiliary power facilities are permitted as accessory uses to the primary office uses, provided they are immediately and exclusively accessory to those uses on the site. Accessory uses include HVAC equipment and auxiliary power facilities

Sources

Cookie preferences · Report missing data