City of Round Rock

Pro-Data Center Policies

Round Rock’s enacted ordinance allows a data center and its related substation on separate parcels at a specific 57-acre site and removes minimum parking requirements, while retaining design, security-wall, and landscaping conditions.

current law · City of Round Rock; the 57.15-acre property governed by PUD No. 155
Allows a data center on a designated 57-acre Round Rock site, with a supporting electric substation, and sets site-specific rules for its design, security, and landscaping.Chisholm Planned Unit Development (PUD) — data center zoning ordinance

What this means

The measure would expressly allow data centers on one parcel and a related electric substation on another, creating a clear path to develop the 57.15-acre site. It also removes minimum parking for data centers, though building design, security-wall and landscaping rules add conditions; overall, this is a meaningful but site-specific benefit.

People behind it

  • Approved the ordinance rezoning the property as PUD No. 155. The ordinance was approved.

  • As mayor, was authorized and directed to enter into the PUD No. 155 Development Plan. The Mayor is hereby authorized and directed.

Restrictions & requirementsHide restrictions & requirements6
  • Data centers are permitted only in Parcel Area 1. Parcel Area 2 may have a primary electric substation only in conjunction with a data center in Parcel Area 1; Parcel Area 3 does not list data centers as a permitted use. Uses not specifically covered by the plan are subject to C-1a zoning, rather than the former C-1 district. The permitted uses are assigned by parcel area.

  • Data center buildings facing IH-35 must incorporate at least three listed design features, change wall planes and exterior finish at intervals no greater than 80 feet, and have no overhead doors facing IH-35. No overhead doors shall face IH-35.

  • Data center structures must be enclosed within a perimeter wall or fence. Walls must meet specified finish, material, and sight-line requirements and be 8 to 20 feet high; decorative view fencing is allowed only under stated conditions, including screening mechanical yards and substations with qualifying walls. Structures shall be entirely contained within a perimeter wall or fence.

  • When Parcel Areas 1 or 2 are developed for data center or substation use, landscaped buffers at least 8 feet wide must be installed where shown on the concept plan, with planting quantities and, for some buffer types, evergreen-species requirements. Buffers that measure at least eight (8) feet wide.

  • If Parcel Area 2 is developed as an electric substation, Monarch Tree #960 may be removed without a separate Council request only with required mitigation and preservation of trees #963 and #964. The special removal permission does not apply if Parcel Area 2 is developed for C-1a uses. Tree # 960 may be removed.

  • Plan changes beyond the limited minor-change authority must follow the original PUD application procedure. Minor changes may be approved administratively up to 10% of a numerical standard, but changes in land use, density, building height, or site coverage—and certain other listed changes—cannot use that route. All changes not permitted above shall be resubmitted.

Benefits & exceptionsHide benefits & exceptions7
  • Parcel Area 1 expressly allows a data center, alongside uses permitted in the C-1a district. “Data Center”

  • Parcel Area 2 allows a primary electric substation when established in conjunction with a data center on Parcel Area 1; C-1a uses are also allowed there. “in conjunction with a Data Center Use”

  • For zoning and subdivision, the property is governed by the PUD, and its terms control where they conflict with the City Code; matters not specifically covered default to C-1a rules. “this Plan shall supersede”

  • No minimum parking is required for data center use or for a primary electric substation. “no minimum parking shall be required”

  • For data center and/or electric-substation development on Parcel Areas 1 and 2, the PUD waives interior parking-lot landscaping, parking-lot landscape buffers, and foundation treatment. “shall not be required”

  • If Parcel Area 2 is developed as an electric substation, Monarch Tree #960 may be removed without a separate City Council request, provided required mitigation is supplied and trees #963 and #964 are preserved. This allowance does not apply if Parcel Area 2 is developed for C-1a uses. “may be removed without separate City Council request”

  • The Planning and Development Services Director may administratively approve minor plan changes, including adjustments to site layout, building configuration, driveways, and project phasing, up to 10% of a numerical standard. This route excludes, among other things, changes in land use and increases in density, building height, or site coverage; other changes must follow the original PUD procedure. “administratively approve a minor change”