City of Pineland
Neutral Data Center Policies
Pineland’s M-2 industrial areas allow most uses and set no height or lot limits, but data centers are not specifically addressed, and sites near homes need a 100-foot buffer.
current law · City of PinelandEstablishes general zoning-use rules for residential, commercial, and industrial districts, but does not specifically regulate data centers.Pineland zoning district regulations (Article 11)
What this means
The rules could make data centers easier to build in M-2 industrial areas, which allow almost any use not specifically excluded and set no height or lot limits. But they do not mention data centers or provide incentives, and M-2 sites near residential districts must include a 100-foot buffer.
People behind it
- Bill Whittington
Made the motion to adopt the ordinance.
- Ross Parker
Seconded the motion to adopt the ordinance.
- John O. Booker, Jr.
Approved the ordinance as Mayor.
Show 1 more peopleShow fewer people
- Paula Smith
Attested to the ordinance as City Secretary.
Restrictions & requirementsHide restrictions & requirements3
The ordinance does not specifically mention data centers, but requires new buildings and uses, changes of use, and structural alterations or enlargements to comply with the regulations for their zoning district (district regulations apply to buildings and uses).
In the M-1 district, nonresidential uses are limited to listed uses and similar uses, and may operate only if they are not noxious or offensive because of odors, smoke, dust, noise, vibration, fumes, or glare (M-1 use restrictions).
An M-2 industrial use that abuts or faces an R-1, R-2, or R-3 district must provide a buffer at least 100 feet wide; the 50 feet nearest the residential-district boundary is limited to landscaping and specified recreation and access uses, while the remaining 50 feet may be used for industry-related parking (M-2 buffer requirements).
Benefits & exceptionsHide benefits & exceptions2
In the M-2 district, uses are allowed except for specified exclusions, including residential and C-1/C-2 commercial uses; the ordinance also sets no height or lot requirements there. If a data center qualifies as a permitted M-2 use, these rules can facilitate its construction or expansion. M-2 uses abutting or facing an R-1, R-2, or R-3 district must provide a 100-foot buffer, with limits on how parts of that buffer may be used. M-2 uses and requirements
Industrial uses in the M-1 district have no height limit. This applies only to industrial uses allowed under the district’s use rules, which require that uses not be noxious or offensive because of odors, smoke, dust, noise, vibration, fumes, or glare. M-1 height rule