City of Oak Leaf

Anti-Data Center Policies

Oak Leaf’s zoning ordinance does not specifically address data centers, so the City Council may need to interpret how they fit existing use categories or consider a zoning change, creating possible uncertainty and delay.

current law · City of Oak Leaf
Requires the City Council to classify unlisted uses, potentially through a zoning-text amendment, but sets no data-center-specific rules.Oak Leaf Zoning Ordinance, Chapter 15A

What this means

The ordinance does not specifically address data centers. If the city cannot fit one into an existing use category, the City Council must interpret it and may start a zoning text amendment process, which can add uncertainty and delay (unlisted uses). The sources provide no data-center-specific benefits or protections.

People behind it

  • May initiate zoning amendments on its own motion and has authority to amend the ordinance after a public hearing and a Planning and Zoning Commission recommendation.

  • May request a zoning district boundary amendment.

  • Administers specified application and review procedures, including maintaining zoning application requirements and administering landscape plan review.

Restrictions & requirementsHide restrictions & requirements6
  • Land and buildings may be used only for uses listed for their zoning district. If the building inspector cannot classify an unlisted use, the City Council must interpret it and initiate a zoning text amendment; this could apply to a data center not otherwise listed. The use of land or buildings shall be in accordance with those listed.

  • A zoning amendment requires a complete application and payment of the City’s fee, a public hearing, a Planning and Zoning Commission recommendation, and an affirmative vote of three-fourths of all City Council members. A documented protest also requires a three-fourths vote; it must be filed at least seven calendar days before the hearing and meet the ordinance’s land-area thresholds. All amendments shall require an affirmative vote by three fourths.

  • Newly annexed land is initially zoned District U. Until the City assigns permanent zoning, the City may issue only permits for buildings or land uses permitted in District U, subject to the stated exception for qualifying existing or previously planned uses. All land or territory annexed by the City shall be initially zoned as District U.

  • Before a building permit is issued, a building site must be created through an approved recorded plat, a qualifying separately owned pre-annexation parcel facing a dedicated street (for one main building), or an approved site plan. The ordinance also states that a plat of record must be created before permit issuance. No permit for construction of a building or buildings.

  • An application for a permit found incomplete expires on the 45th calendar day after filing if the applicant has not supplied the requested information; a new application and fee may then be required. shall expire on the forty-fifth (45th) calendar day.

  • For applications filed on or after October 13, 2020, a permit or permit application expires after two years without progress toward completion. A project commenced by filing a permit application expires on the fifth anniversary of the first approved permit application if there has been no progress; new applications are then subject to current regulations. shall expire two (2) years from the date the application.

Benefits & exceptionsHide benefits & exceptions4
  • A planned development (PD) can set modified development requirements, allowing an applicant to request standards that differ from the ordinance’s normal requirements. The application must identify and justify the requested deviations, and the minimum area is 15 net acres unless the City Council makes a specified finding for a smaller district. PD applications may request differing standards

  • A property owner or authorized representative may request a zoning-district boundary amendment, which can provide a route to seek zoning appropriate for a data center. Approval is not automatic: it requires a public hearing, a Planning and Zoning Commission recommendation, and a three-fourths affirmative City Council vote. The owner of the real property

  • If the building inspector cannot classify a proposed use under an existing listed use, the City Council is to interpret the use and initiate a zoning-text amendment. This provides a process for addressing a data-center use not listed in the ordinance, but does not itself authorize that use. unable to classify the use

  • The Zoning Board of Adjustment may grant variances for specified standards, including height, yards, lot area, exterior structure, and off-street parking. A variance requires findings on public interest, ordinance intent, consistency with the Comprehensive Plan, and unnecessary hardship, among other criteria; it cannot authorize a change of use not permitted in the district. variance from the terms