Moody’s rules require zoning compliance and a building permit, but do not specifically address or ban data centers; because they are not listed uses, the City Council would decide where they may be allowed, potentially causing uncertainty or delay.
current law · City of MoodyRequires the City Council to decide which zoning districts may allow data centers, since they are not specifically listed as a permitted use.No data-center-specific local measure found in Moody, Texas
What this means
A data center is not specifically listed, so the City Council would decide which zoning districts may allow it, creating uncertainty and possible delay (unlisted uses). Building also requires zoning compliance and a permit, but the rules do not expressly ban data centers or impose data-center-specific limits (permit and zoning requirements).
People behind it
- City Council
Makes zoning decisions under the ordinance, including approving zoning for newly annexed areas and classifying new or unlisted uses.
- Administrative official
Administers building permits and certificates of occupancy and refers questions about new or unlisted uses to the City Council.
- City secretary
Maintains the official zoning map and the record copy of certificates of occupancy.
Restrictions & requirementsHide restrictions & requirements5
A data center is not expressly listed as a permitted use in the use table. Uses not expressly authorized are prohibited, and new or unlisted uses must be referred to the City Council, which decides the appropriate zoning district and may amend the ordinance. Unlisted uses are prohibited unless authorized and the Council determines their zoning classification.
Buildings and land uses must conform to the regulations for their zoning district. A building permit is required for construction, moving, additions, or structural alterations, and it cannot issue unless the site is a properly approved and recorded platted lot. District conformance is required and permits require a properly platted building site.
A certificate of occupancy is required before a building or premises may be used or occupied after creation, erection, conversion, or a change or alteration in use or structure. A temporary certificate may last no more than six months. Occupancy requires a certificate and temporary certificates are limited to six months.
A building permit expires if the permitted work has not begun within six calendar months of issuance; work may not proceed until a new permit is obtained. The six-month permit expiration rule.
Newly annexed territory is automatically classified as agricultural, and construction permits there are limited to buildings permitted in the R1 single-family district unless the City establishes alternative zoning. Annexed territory defaults to agricultural zoning and construction permits are limited to R1 uses.
Benefits & exceptionsHide benefits & exceptions3
A data-center use that was in existence before December 1, 2009 is deemed a legal nonconforming use, subject to the ordinance’s rules for nonconforming uses. Pre-existing uses
A qualifying pre-existing structure is exempt from district area and height requirements and may be expanded, repaired, or remodeled without meeting area requirements. The height exemption does not cover new construction that exceeds the applicable district height limit. Pre-existing structures
A lot or parcel that existed before December 1, 2009 but fails current zoning requirements is treated as a legal nonconforming lot and exempt from district area requirements. If it had structures on it before that date, those structures are also exempt from front, rear, and side yard setbacks. Pre-existing lots