City of Mesquite
Anti-Data Center Policies
Mesquite allows data centers only in industrial areas, generally with City Council approval. Applicants must meet strict siting, noise, water-use, study, cooling, and cleanup requirements, creating significant barriers without banning development.
current law · City of MesquiteRequires most new data centers in Mesquite to get City Council approval in industrial areas and follow rules on noise, water use, generators, setbacks, screening, and decommissioning.Ordinance No. 5259 (Zoning Text Amendment No. 2026-01, Data Centers)
What this means
The measure would allow data centers, but only in industrial areas and generally with City Council approval of a conditional use permit (approval required). Applicants would also face substantial siting, noise, water-use, study, and long-term cleanup requirements, including closed-loop or recycled cooling, creating significant barriers even though development is not banned.
People behind it
- City of Mesquite Planning & Development Services staff
Developed the proposed standards for the zoning text amendment.
Restrictions & requirementsHide restrictions & requirements16
A principal-use data center requires City Council approval of a Conditional Use Permit (CUP) and is allowed only in the Industrial district or qualifying Planned Development districts; it is prohibited in residential, office, commercial, agricultural, and mixed-use districts. A CUP is not needed where a PD ordinance specifically permits the use by right. Permitted zoning districts and CUP.
A data center must be on a lot of at least five acres. Minimum lot area.
Accessory data centers are allowed where the principal use is allowed, but generally remain subject to the data-center standards. A fully contained accessory facility no larger than 25% of the principal use’s floor area is exempt from the CUP and data-center setback requirements; its ground-mounted equipment must still meet the standards. Accessory Data Center exception.
The standards apply to new data centers and expansions that increase gross floor area or ground-mounted equipment area by more than 10%. Applicability threshold.
CUP applications must include specified site, landscape, and building plans; technical studies on noise, lighting, utilities, water and wastewater, traffic when required, vibration, and electromagnetic fields; and operational, emergency, and decommissioning information. The City may also require additional studies or information. CUP application requirements.
The City may require review by an independent technical consultant when staff expertise is insufficient or submitted studies need verification; the applicant must pay the actual and reasonable review costs. Consultant review costs.
Setbacks require principal buildings to be at least 300 feet from residential district boundaries and specified protected uses, and ground-mounted equipment to be at least 500 feet away. Buildings must also be 100 feet from nonresidential property lines; pavement must generally be 50 feet from street rights-of-way. Data-center setbacks.
Data-center buildings are limited to 75 feet in height, and accessory structures located between the principal building and a property line are limited to 30 feet. Building height limits.
Sites must provide a 50-foot landscaped buffer along public rights-of-way and residentially zoned districts, screen ground-mounted and rooftop equipment, and meet specified fencing and residential-adjacency landscaping requirements. Screening and buffering.
Lighting is subject to full-cutoff, fixture-height, and color-temperature limits; no exterior fixture may cause illumination above 0.0 footcandles at a property line, and a photometric plan is required. Lighting limits.
Operational noise is limited to 65 dBA during the day and 60 dBA at night, with a 55 dBA nighttime limit at shared lines with residential property, residential districts, or specified protected uses. Low-frequency limits also apply. Applicants must submit acoustic modeling, and post-construction studies are due within 60 days of each phase’s certificate of occupancy and whenever requested; exceedances require immediate corrective measures. Noise limits and post-construction study.
Diesel generators must meet EPA Tier 4 Final emissions standards and use Level 3 or equivalent sound-attenuating enclosures. Routine full-load testing is restricted to weekdays (excluding federal holidays), 9 a.m.–4 p.m., no more than four hours per event and no more than once per generator per quarter; monthly no- or light-load exercises are limited to 30 minutes. Emergency operation must be reported to the Director within 72 hours. Generator standards and testing limits.
Only closed-loop or recycled-water cooling is allowed. Using municipal potable water for open evaporative or once-through cooling that discharges to waste is prohibited; applicants must disclose projected water use and document available utility capacity. Cooling and water requirements.
Battery storage at data centers must meet applicable fire and building codes and the BESS fire and life-safety requirements; the data-center standards govern its setbacks and screening. BESS at data centers.
Commercial cryptocurrency mining is prohibited as a principal or accessory use in every zoning district and may not be combined with a data-center use. Cryptocurrency mining prohibition.
A data center that ceases operations for 36 continuous months is considered inactive and must proceed under its approved decommissioning plan. Work must generally begin within 180 days after that period and be substantially completed within 12 months after commencement; the Director may grant extensions for good cause. Decommissioning time limits.
Benefits & exceptionsHide benefits & exceptions8
Data centers may be approved as a principal use in the Industrial district and qualifying Planned Development districts, subject to City Council approval of a Conditional Use Permit (CUP). A CUP is not required in a Planned Development whose ordinance specifically permits a data center by right.
Accessory data centers are allowed in any district that allows the principal use. If fully inside the principal-use building and no more than 25% of its gross floor area, they are exempt from the data-center CUP and setback requirements; noise, screening, and utility standards still apply.
The data-center standards apply to expansions only when they increase gross floor area or ground-mounted equipment area by more than 10%. Smaller expansions are therefore outside this section’s applicability threshold.
The Director may modify parking requirements based on an operational-needs analysis submitted with the CUP application.
Building design standards allow flexibility where mandatory standards are infeasible because of a data center’s functional requirements, if the overall design intent is achieved. Several facade and entrance provisions are stated as standards the building “should strive” to meet.
Battery energy storage systems are permitted as an accessory use, subject to applicable fire, building, BESS, and data-center screening requirements.
Lawfully established or vested data centers are classified as legal nonconforming uses, subject to the ordinance’s nonconforming-use provisions. Expansion, enlargement, or a material operational change requires compliance with the applicable standards.
Specified noise limits do not apply to emergency generator use caused by sudden, reasonably unforeseen events beyond the operator’s control, or to routine generator testing that follows the prescribed schedule. The exemption does not remove other applicable requirements.