City of Maud
Anti-Data Center Policies
Maud does not specifically list data centers, so zoning depends on use classification and district; commercial or industrial construction requires permits and site-plan review.
current law · City of MaudRequires data centers to follow Maud’s general zoning and permitting rules; it sets no data-center-specific requirements.Maud Code of Ordinances, Chapter 155: Zoning Code
What this means
Data centers are not specifically listed, so whether they are allowed may depend on how the city classifies the use and which zoning district applies; land and buildings must follow district regulations. New commercial or industrial construction also requires permits and site-plan review (site plan approval). These rules add meaningful uncertainty, paperwork, and potential delay, but the text does not expressly ban data centers.
People behind it
- City Council
The chapter assigns it responsibility for administering and enforcing the zoning regulations.
- City Secretary
The chapter assigns the City Secretary roles in enforcement, notices, and issuing permits.
- Zoning Board
The chapter assigns it roles in zoning appeals, exceptions, variances, temporary-use permits, and amendment review.
Restrictions & requirementsHide restrictions & requirements8
Development must comply with the zoning rules for its district. Data centers are not expressly named in the listed permitted uses, so the code does not itself establish which district, if any, allows them. District use regulations and the requirement to conform to district rules
Building permits are required to erect, move, add to, or structurally alter a building or structure. Applications must include scaled plans and specified site and building information; a permit generally cannot issue unless the project conforms to the zoning code or the Zoning Board has issued a written order. If permitted work has not begun within 90 days, the permit expires. Permit requirements and 90-day deadline
New construction and additions for commercial or industrial uses require a site plan approved by the Building Official before a building permit may issue. The plan must show building locations, setbacks, screening, parking and access; the reviewing body may require revisions or additional screening, setbacks or rights-of-way. Site-plan requirements
District-specific limits apply to lot area and width, setbacks, building height, lot coverage and floor area. Parking is also required at the listed district ratios—for example, the M District requires one space per 1,000 square feet of general floor area and one per 400 square feet of office and sales space. Lot and building limits
Listed building-permit fees include $0.20 per square foot for new commercial or institutional construction, with a $50 minimum; plan review costs $125, and engineering review is charged at cost plus 10%. Permit fees double for projects started without a permit. The applicable fee category depends on the project. Permit fee schedule
Land annexed into the city is initially zoned R-1. Applications for other uses in newly annexed areas may be referred to the City Council, which may impose additional requirements and conditions; final authorization is required before a building permit issues. Rules for newly annexed land
A zoning-map or other zoning amendment follows a public-hearing process, including notice to nearby property owners. If the Zoning Board recommends denial, or a qualifying written protest is filed against an approval, adoption requires a three-fourths City Council vote. Amendment and voting requirements
Existing nonconforming uses of land lose the right to continue if discontinued for more than 30 days; nonconforming uses of structures lose that status after six consecutive months of discontinuance or 18 months during any three-year period. A nonconforming structure destroyed beyond 50% of its replacement cost generally cannot be rebuilt except in compliance with the code. Nonconformity limits
Benefits & exceptionsHide benefits & exceptions1
A data center that was a lawful use before a zoning change made it nonconforming may generally continue operating, but it cannot expand onto additional land; a land use loses this protection after more than 30 days of cessation, while a building use loses it after six consecutive months or 18 months within a three-year period. A nonconforming structure also cannot be altered to increase its nonconformity, and if more than 50% destroyed by replacement cost, it generally cannot be rebuilt unless it conforms to the code. These protections apply only if the data center was lawful before the relevant change. Nonconformities may continue subject to restrictions