City of Lowry Crossing

Mixed Data Center Policies

Lowry Crossing’s zoning ordinance does not specifically address data centers, so the city must classify them and decide where they may operate. In industrial districts, paved parking, masonry walls, and landscaping requirements may constrain design and add costs.

Rating from Texas statewide as there are no scored current or future laws outside temporary restrictions for City of Lowry Crossing.

current law · City of Lowry Crossing
Requires city officials to classify data centers as unlisted uses under the zoning ordinance; it contains no data-center-specific regulations.Exhibit 14A: Zoning Ordinance - City of Lowry Crossing, TX

What this means

The ordinance does not name data centers, so the city would first need to classify an unlisted use and decide where it may operate (unlisted uses are reviewed by the Planning and Zoning Commission). In industrial districts, requirements such as paved parking, masonry exterior walls, and landscaping could add costs and design constraints (parking must be paved; industrial landscaping standards).

Timing

Ends
When the property is classified by zoning change as a district other than TR1.

The temporary restriction applies to TR1-classified property: construction, alterations, and new uses are barred until reclassification (until such territory has been classified). For annexed territory, lawful uses already in existence may continue, but no new use is permitted until permanent zoning is granted (no new use other than the lawful use).

People behind it

  • Recommended adoption of the new zoning ordinance, as stated in the ordinance’s recital of the Commission’s recommendation.

  • Enacted the ordinance, which states it was ordained by the City Council of Lowry Crossing, as shown in the enacting clause.

Restrictions & requirementsHide restrictions & requirements9
  • A data center is not specifically listed as a use in the ordinance. A new or unlisted use must be referred to the Planning and Zoning Commission, which recommends a district, and the City Council makes the classification decision; standards for the use may be interpreted from a similar use. New or unlisted uses

  • Land and buildings must conform to the regulations for their zoning district. If a zoning change is needed, the process includes public hearings before the Planning and Zoning Commission and City Council, with advance notice to nearby property owners and newspaper publication. Conformance with the zoning regulations, public hearings

  • A zoning-change application requires a filing fee set by the City Council to cover City costs, including publication, mailing notices, and outside engineering; an additional fee may be charged if the applicant causes a hearing to be rescheduled. Zoning-change filing fees

  • A proposed zoning change requires a three-fourths City Council vote if the Planning and Zoning Commission denied it or a qualifying written protest was filed by owners of at least 20% of the specified affected area. Three-fourths vote

  • In the Highway Commercial district, no use is permitted unless authorized through a Special Use Permit or Planned Development. The district also requires site-plan review before building permits or certificates of occupancy. These requirements apply if the site and use are placed in that district. HC use authorization, site plan review

  • A zoning ordinance may require site-plan review before a building permit or certificate of occupancy. When required, both the Planning and Zoning Commission and City Council must conclude the review by motion before the permit or certificate may issue. Site-plan review prerequisite

  • If classified in the Light Industrial district, operations must not send dust, fumes, gas, noxious odors, smoke, or glare beyond the property; noise at the boundary cannot exceed the average street-traffic noise there, and the use must not create fire hazards on surrounding property. Light Industrial operating limits

  • Existing nonconforming uses or structures may not be expanded beyond the lot or tract they occupied on the ordinance’s effective date, except for off-street loading or parking approved by the Board of Adjustment. Structural alterations or extensions are also restricted unless required by law or the building is made conforming. Limits on nonconforming uses

  • Nonresidential and surface-parking-lot development is subject to landscaping requirements. Minimum landscaped site area is 10% in the Retail, Highway Commercial, Commercial, Light Industrial, and Heavy Industrial districts, and 15% in the Office district. Minimum landscaping area

Benefits & exceptionsHide benefits & exceptions7
  • The Heavy Industrial district allows premises to be used for any purpose unless another ordinance or law prohibits it, but bars new residential buildings. A data center would still need to be located in property zoned HI, and special traffic, drainage, or similar requirements may lead to a special-use-permit requirement. “used for any purpose”

  • The Light Industrial district permits commercial and light-manufacturing uses, including indoor manufacturing and industrial plants, subject to limits on off-site emissions, noise, and fire hazards. The ordinance does not specifically name data centers, so their classification or eligibility would need to be determined. “commercial and light manufacturing uses”

  • For a new or unlisted type of land use, the Planning and Zoning Commission determines the appropriate district and sends a recommendation to the City Council, which makes the classification decision. This provides a process for considering a data center even though it is not named in the listed uses. “new or unlisted use”

  • A Planned Development district can combine uses that are not allowed in other districts and set project-specific development standards. The granting ordinance must specify the permitted uses and standards, and the district generally remains subject to other city ordinances unless that ordinance provides otherwise. “combination and mixing of land uses”

  • Where site-plan review is required, the review is intended to check compliance with existing city requirements and may not impose new conditions. Completion of the review is a prerequisite to a building permit or certificate of occupancy, but it does not authorize noncompliance with the ordinance. “shall not impose any new condition”

  • A special-use-permit classification runs with the land, so a new owner may continue the approved use. A new zoning change is required if the approved plan is deviated from or the use is conducted differently. “runs with the land”

  • Lawfully operating nonconforming uses and structures may retain nonconforming status, and ordinary repairs and maintenance are allowed. The use generally cannot expand beyond the existing lot or tract; it may be deemed abandoned after one year of discontinuance for a permanent structure, or six months for a use without one. “Repairs and normal maintenance”