Hunt County bars data centers from receiving county tax abatements; separate enacted measures support a possible unincorporated-area pause and request a state pause, but do not themselves impose one.
Rating and summary from Hunt County as there are no scored current or future laws outside temporary restrictions for City of Lone Oak.
failed · City of Lone OakRequires city review to assign a zoning district to a data center as an unlisted use; the ordinance contains no data-center-specific rules.Lone Oak data-center-specific regulation search
What this means
The ordinance does not ban data centers or offer them special incentives, but an unlisted use must go through zoning classification, and buildings need permits. That could add some uncertainty and delay, though the sources do not say how a data center would be classified or what requirements would apply to a specific site. Unlisted uses are referred for zoning classification; building permits are required.
People behind it
- City Council
Adopted the ordinance and may initiate amendments; it also designates the official who administers and enforces the zoning rules. The ordinance was adopted by the City Council.
- Building official
Designated as the administrative official to supervise administration and enforcement of the ordinance. The building official is designated to supervise administration and enforcement.
Restrictions & requirementsHide restrictions & requirements7
A data center is not specifically listed in the ordinance. For a new or unlisted land use, the zoning official refers the question to the Planning and Zoning Commission, which holds a public hearing and recommends a district; the City Council makes the classification decision. New or unlisted uses
The use must comply with the regulations for its zoning district. If the site is also in the floodplain overlay, that overlay takes precedence, and buildings or structures are barred there except for those listed as permitted. District regulations apply and floodplain building restrictions
If the data center requires a conditional use permit, the City Council may approve it only after a public hearing, notice, and a Planning and Zoning Commission recommendation, and after finding that specified public-welfare, compatibility, infrastructure, access, and yard standards are met. The Council may impose conditions; after a denial, the application cannot be resubmitted for six months. Conditional-use requirements
Building permits are required for applicable construction, moving, additions, enclosure, or structural alterations; a certificate of occupancy is required before a new or altered building or changed use is occupied. The permit and occupancy certificate must conform to the zoning ordinance. Permit requirement and occupancy certificate requirement
A building permit expires if the permitted work has not begun within six calendar months of issuance; further work then requires a new permit. Six-month permit expiration
The City Council sets fees and charges for ordinance administration, permits, occupancy certificates, zoning-change requests, and Board of Adjustment appeals. No action may be taken on an application or appeal until applicable fees and charges are paid in full. Fees and payment requirement
If rezoning is needed, the process requires Planning and Zoning Commission review and a public hearing, followed by a City Council public hearing and ordinance adoption. A denied rezoning request for the same classification and property cannot be considered again for six months; a qualifying protest by owners of at least 20% of specified land requires a three-fourths favorable Council vote. Rezoning procedure, six-month waiting period, and protest vote threshold
Benefits & exceptionsHide benefits & exceptions2
The I1 Light Industrial District permits storage and warehousing establishments and other similar wholesale, light-manufacturing, construction, or service uses. The ordinance does not name data centers or specify that they qualify, so their eligibility would depend on zoning classification. Storage and warehousing establishments; similar wholesale, light-manufacturing, construction, or service uses.
A lawful existing use that becomes nonconforming may generally continue, which could protect an existing data-center use after a zoning change if it qualifies. It may not be extended, and if discontinued for six consecutive months it cannot be resumed as a nonconforming use. Lawful existing uses may be continued.