City of Jasper
Mixed Data Center Policies
Texas offers substantial tax breaks on equipment and electricity to large projects meeting investment and job requirements, while large grid connections face studies, fees, and possible emergency power cuts; some requirements apply only to very large loads.
Rating and summary from Texas statewide as there are no scored current or future laws outside temporary restrictions for City of Jasper.
pending · City of JasperClassifies data centers under general zoning rules, with the Building Official deciding which comparable use standards apply; it sets no data-center-specific requirements.Jasper, Texas zoning ordinance (public hearing draft, October 21, 2026)
What this means
The draft does not ban data centers, and industrial districts allow offices and some light-industrial uses, so a data center may be allowed depending on how the city classifies it. But projects would still face zoning and permit requirements, and some related utility facilities require special approval, creating a modest risk of extra delay or cost (industrial uses and approvals).
People behind it
- Greg Kelley
City Manager authorized to finalize the zoning ordinance in coordination with Kendig Keast Collaborative.
- Kendig Keast Collaborative
Consultant coordinating with the City Manager on finalizing the zoning ordinance.
- Jasper City Council
Identified in the draft as the body that adopts the ordinance; it also authorized the finalization process.
Restrictions & requirementsHide restrictions & requirements6
A data center is not expressly listed as a use. The Building Official may authorize an unlisted use only if it is a subcategory of, or functionally similar to, a permitted, limited, or special use; otherwise it is prohibited. Unlisted uses may be authorized (Sec. 3.800).
If classified as an Office use, a data center would be prohibited in GR, require a Special Use Permit in MF, be a limited use in DT, and be permitted in MU, CM, and IL. All Offices (Secs. 3.100 and 3.200(C)(13)).
New nonresidential development generally requires an approved Site Development Plan before development, a Building Permit before construction, and a Certificate of Occupancy before occupancy or use. A Construction Permit is also required before beginning construction where applicable. A site plan shall be approved and it is unlawful to occupy (Secs. 7.400(A), (C)–(E)).
Development applications require a fee. If an application is incomplete, the applicant has up to 10 calendar days to supply missing items; otherwise it is rejected, and applying again requires a new application and fee. A new application and fee shall be required (Sec. 7.100(B)).
If classified as an Office use, the parking standard is one space per 300 square feet of gross floor area. All Offices 1 per 300 sf GFA (Sec. 4.300(C)).
If located in IL, development must meet that district’s dimensional limits, including a one-acre minimum lot area, 30-foot front and street-side setbacks, 20-foot interior-side setback, 30-foot rear setback, and 50-foot maximum height. Industrial (IL) (Sec. 2.400).
Benefits & exceptionsHide benefits & exceptions6
Data processing is listed among Office uses. If the Building Official classifies a data center within that category, offices are permitted in MU, CM, and IL districts; limited in DT; and require a Special Use Permit in MF. data processing
A data center not specifically listed may still be authorized if the Building Official determines it is a subcategory of, or functionally similar to, a permitted, limited, or special use. It receives the comparable use’s standards; if it does not qualify, it is prohibited. functionally similar
The use table permits Minor Utilities in every district and allows Major Utilities in every district with a Special Use Permit. This could apply to qualifying utility facilities serving a data center, but does not itself establish that a data center qualifies as a utility. Major Utility
For a complete development application, the applicable ordinances and technical regulations are those in effect when it is submitted. A valid prior development approval may also be carried out within its approved scope, subject to its validity and expiration. ordinances in effect at the time
An inactive application can remain subject to newer regulations while an extension period is available; if the extension deadline lapses, the application becomes subject to the new regulations. subject to the new regulations
Site-plan review may account for infrastructure that is already available or planned, including utilities, roads, drainage, and public services; approval requires the Building Official to find the applicable criteria are met. existing and planned infrastructure