City of Hutchins

Anti-Data Center Policies

Hutchins’s enacted zoning ordinance does not name data centers, so they may need a use classification or zoning change; other project requirements may add costs and delays.

current law · City of Hutchins
Treats data centers as unlisted uses, requiring the city to classify them through its zoning process before they can be allowed.City of Hutchins 2026 Zoning Ordinance (data center provisions)

What this means

The draft does not name data centers, and says unlisted uses are not allowed, which could mean a classification process or zoning amendment before development. Nonresidential and industrial projects also face site-plan, parking, landscaping, and building-design requirements, creating real costs and delay, though the draft does not outright prohibit data centers. The Council agenda proposes replacing the zoning ordinance.

People behind it

  • Worked on revising the zoning ordinance and presented the draft to the Planning and Zoning Commission.

  • Organization Stephen Cook worked with on revising the zoning ordinance.

Restrictions & requirementsHide restrictions & requirements6
  • A use not listed in the zoning use charts is not allowed. The draft does not list data centers, so a proposed data center would need a use classification and, if necessary, a zoning amendment before it could proceed. The classification process involves a Planning and Zoning Commission recommendation and City Council decision; zoning amendments require public hearings, and if the Commission recommends denial, approval requires at least a four-fifths Council vote. A use not listed is not allowed.

  • Nonresidential development requires site-plan review. Building permits cannot issue until the site plan and required engineering or construction plans are approved, and a certificate of occupancy cannot issue until construction conforms to the approved plans. Staff may also require additional studies or information for a particular site plan. An approved site plan expires if development has not commenced within one year. Site plan review and approval shall be required.

  • Site-plan and zoning applications carry fees, and applications may be blocked by delinquent property-related taxes, assessments, impact fees, or other debts to the City until paid or covered by an arrangement acceptable to the City. accompanied by payment of the appropriate fee.

  • In the Light Industrial and Heavy Industrial districts, minimum lot area is 20,000 square feet, minimum lot width is 100 feet, minimum lot depth is 200 feet, and the front setback is 50 feet. Occupied buildings are generally limited to three stories or 45 feet; near residentially zoned property, lower height limits and larger setbacks apply. These districts also require at least 80% masonry exterior construction. Minimum Lot Area: Twenty thousand.

  • New nonresidential construction is subject to landscaping requirements, including an approved landscape plan, landscaping of at least 15% of the total site area, and landscaping of at least 10% of gross parking area. In nonresidential or multifamily development, removing trees six inches or larger in caliper requires a tree-removal permit; industrial property abutting residential property must have a screening wall at least 14 feet high. a minimum of 15 percent of the total site area.

  • All uses must meet performance standards for noise and other impacts, including smoke and particulate matter, odors, hazardous materials, vibration, and glare. Nonresidential lighting must use full-cutoff, downcast fixtures; new nonresidential developments must use LED fixtures, and light on an adjacent residentially zoned area may not exceed 0.25 footcandles. All uses, including those which may be allowed by PD or SUP.

Benefits & exceptionsHide benefits & exceptions2
  • The ordinance provides a process for considering uses not listed in its use tables: an applicant may submit information about a new or unlisted use, the Planning and Zoning Commission recommends a classification, and the City Council decides whether to approve an ordinance amendment. A data center is not specifically listed or automatically allowed; it would require this classification process and, if approved, a zoning amendment.

  • The Planned Development district allows planned combinations of uses and “new or innovative concepts in land utilization” that other districts may not permit, with development requirements tailored in the approving ordinance. A data center would need to be specifically identified in the application and approved; the process requires at least one acre, public hearings, and approval of a plan.