Mixed Data Center Policies

Texas offers substantial tax breaks on equipment and electricity to large projects meeting investment and job requirements, while large grid connections face studies, fees, and possible emergency power cuts; some requirements apply only to very large loads.

Rating and summary from Texas statewide as there are no scored current or future laws outside temporary restrictions for City of Hurst.

failed · City of Hurst
Requires data centers to fit a use allowed in their zoning district or obtain applicable zoning approval; Hurst’s zoning chapter does not specifically regulate data centers.Hurst Texas data center law review—no specific measure identified

What this means

The rules do not specifically address data centers, and uses not named in a district are prohibited. A project would need to fit a permitted use and meet applicable zoning, permit, and site requirements, creating meaningful approval hurdles but not an outright ban.

Timing

Ends
The earliest of: the effective date of an ordinance approving the proposed zoning change; the day after the city council’s final decision denying it; the 90th day after filing a written hardship-relief request; or the day after approval or conditional approval of a certificate of site plan approval.

While the Historic Landmark zoning procedure is pending, the city may not accept certain permit applications for the property. The restriction ends on the earliest listed event; no extension condition is stated. No application may be accepted for a permit.

Restrictions & requirementsHide restrictions & requirements8
  • Only uses specifically allowed by a zoning district may operate; a use not named in any district is prohibited citywide. This chapter does not expressly name data centers, so their zoning classification would need to be established before approval. Any use not named in any district is prohibited.

  • If a zoning change is needed, it requires Planning and Zoning Commission and City Council public hearings, notice to nearby property owners, and council action. A written protest from owners of at least 20% of specified affected land requires a three-fourths favorable council vote. After denial of a rezoning request, another application for the same classification on the same property cannot be considered for six months. No application for rezoning shall be considered within six (6) months.

  • A Planned Development (PD) requires at least five acres; a site smaller than five acres may use the Special Planned Use District (SPUD) process, which remains subject to PD requirements. A City Council-approved site plan is required before building permits or certificates of occupancy, and the proposed use must be found compatible with the immediate area. A site plan approved by the city council shall be a prerequisite.

  • Construction, enlargement, alteration, and other listed building work require a building permit; buildings cannot be occupied and a change in occupancy or land use cannot occur until a certificate of occupancy is issued. No person shall erect or construct.

  • For uses counted under the parking table's “any other use” category, at least one off-street parking space is required per 200 square feet of floor area; fractional space calculations require a whole space. Required parking areas and access drives generally must be paved to specified standards. Any other use.

  • Applicable new construction must meet landscaping requirements, including landscaping at least 15% of the lot and a 15-foot landscaped setback along public street rights-of-way; a landscape plan is required when the landscaping rules apply. An area not less than fifteen (15) percent.

  • On property regulated by the tree-preservation rules, removing or damaging a designated tree generally requires a tree-removal permit. Permitted removals of trees at least three inches in size require replacement trees; the stated penalty for removal or damage is $100 per diameter inch. No person directly or indirectly shall cut down.

  • Citywide environmental controls prohibit noise above ambient levels that is discernible beyond the property line, as well as specified emissions, off-site vibration, and discernible glare. Noise above the ambient noise level is discernible beyond the property line.

Benefits & exceptionsHide benefits & exceptions4
  • In the Texas Highway 10 Multiuse District, electrical power substations are listed as planned-development uses. Other uses may also be considered if they meet the district’s purpose; approval is subject to the planned-development application, site plan, and adopting ordinance. Electrical power substations

  • The planned-development framework allows approved site plans or ordinances to modify specified development standards, including lot size, building height, parking, landscaping, and screening. A PD generally requires at least five acres; smaller sites may use the SPUD classification. These are discretionary approvals, not automatic exemptions. Specific general conditions may be modified

  • For land at least five acres in size, Interim Zoning can authorize temporary uses not otherwise allowed or temporary exemptions from development restrictions. The proposed use is limited to a maximum of five years, and the ordinance must set an expiration date. Temporarily utilized for uses not otherwise allowed

  • A lawfully established use may generally continue if later zoning makes it nonconforming, providing some protection against future restrictions. The use may not expand its land or floor area, and abandonment—including vacancy or nonuse for six continuous months—generally ends the right to continue it. The lawful use ... may be continued