City of Howardwick
Neutral Data Center Policies
Howardwick does not specifically restrict data centers, but new construction generally requires a building permit and must follow zoning and building rules. The sources identify no data-center-specific benefits or operating restrictions.
current law · City of HowardwickSets general zoning, utility, and permitting rules that may apply to data centers, but creates no data-center-specific requirements.City of Howardwick Code of Ordinances
What this means
The code does not specifically ban or discourage data centers, but new construction generally needs a building permit and must follow zoning and building rules. These are modest hurdles, and the sources do not identify data-center-specific benefits or operating restrictions.
Restrictions & requirementsHide restrictions & requirements7
Permits are required before construction of facilities above or below ground. The permit fee is set by the city council. Building permits ... ahead of commencement of construction.
Permits are required before placing a new or permanent structure on a lot and before utility service or septic-system construction begins. Permits last six months and may be extended once for six more months; required inspections must be completed before occupancy or service. A TCEQ septic-system permit is required before the city issues a building permit when applicable. Building permits shall be required.
Buildings must meet setbacks of 20 feet from the front property line, five feet from side and rear lines on non-corner lots, and 10 feet from the side street on corner lots. The city council may grant a special permit for an exception. 20 feet from the front property line.
Properties are assigned to specified zoning districts. If a project requires a zoning change, the city council reviews the request for compatibility and potential impacts, and an approved application requires a fee set by the council. A denied request generally cannot be reconsidered for six months, unless the next regular meeting after the city’s general election occurs sooner. reviewed by the city council for compatibility.
Buildings and property must comply with the adopted 2009 International Property Maintenance Code and 2009 International Wildland-Urban Interface Code. International Property Maintenance Code, 2009 edition.
Utility construction, installation, and maintenance within the city must comply with applicable state and federal requirements and the city’s adopted plumbing and building-code standards. must comply with the rules and regulations set forth by the state.
Sound discernible beyond the property may not exceed 85 dB(A) during daytime hours or 70 dB(A) during nighttime hours; other loud or disturbing noise may also be prohibited. 85 dB(A) during daytime hours and 70 dB(A) during nighttime hours.