City of Harlingen
Neutral Data Center Policies
Harlingen requires commission approval for large projects outside city limits to connect to a city-owned stormwater drain, which may delay those connections. The rule does not govern general construction or operation, and the developer said other drainage options were available.
current law · City of Harlingen’s extraterritorial jurisdiction: stormwater drainage connections to city-owned drains from properties larger than one acreRequires projects over one acre, including data centers, that seek to connect to Harlingen-owned drainage outside city limits to obtain City Commission approval at a public meeting.Harlingen resolution requiring commission approval for external stormwater connections
What this means
The measure adds a public vote and possible delay for large projects outside city limits that want to connect to a city-owned stormwater drain (connections would need commission approval). It does not ban data centers or control their general construction or operation, and the developer said it had other drainage options, so the added burden appears minor.
People behind it
- Daniel Lopez
Moved to approve the resolution requiring City Commission approval for qualifying stormwater connections from outside city limits to city drains. Motion by Lopez
- Commissioner Perez
Seconded the motion to approve the resolution. Second by Perez
Restrictions & requirementsHide restrictions & requirements2
Projects larger than one acre seeking to connect to a city-owned drainage ditch outside Harlingen must obtain City Commission approval through an agreement, rather than receive administrative approval; the request must be publicly noticed. The city described this as applying to any industry or development, not just data centers. Projects over one acre must go to the commission
FluidStack’s pending drainage agreement was tabled subject to the company holding a town hall before the next commission meeting, after 6 p.m., and giving the community advance notice. The agreement could not return to the agenda unless that condition was met. Tabled subject to a town hall
Sources
expired · City of HarlingenPauses data center development in Harlingen for 120 days while the city studies potential impacts and prepares regulations.Harlingen 120-day data center moratorium
What this means
The 120-day moratorium would temporarily prevent or delay data-center development while the city studies infrastructure impacts and updates its rules; a short-term moratorium is a substantial hurdle during that period. The article says there are currently no proposed projects in the city, and the longer-term rules are not yet known. 120-day moratorium
Timing
- Ends
- 120 days
People behind it
- Harlingen City Commission
Approved the 120-day moratorium. The commission approved moving forward with the process.
Restrictions & requirementsHide restrictions & requirements1
A temporary 120-day moratorium related to data centers within Harlingen city limits, while the city researches potential impacts and considers updating its ordinances. The source does not specify which activities the moratorium pauses. 120-day moratorium to conduct research