City of Hale Center

Anti-Data Center Policies

Hale Center’s zoning ordinance may require City Council approval for data centers classified as unlisted industrial uses, while M-1 projects need site plans and must meet lot and setback rules.

current law · City of Hale Center
Requires City Council approval for an unlisted industrial use, but contains no data-center-specific zoning rules.Hale Center zoning ordinance (Exhibit 9A)

What this means

The ordinance does not name data centers, but a data center treated as an unlisted industrial use may need City Council approval, and M-1 projects require a site plan and must meet lot, coverage, and setback rules (unlisted industrial processes; M-1 site plan and lot rules). These requirements could add cost or delay, but the text does not ban data centers or clearly say how they would be classified.

People behind it

  • Adopted Ordinance No. 394 and is identified as the governing body that may amend the ordinance.

  • Charged with administering and enforcing the zoning ordinance.

Restrictions & requirementsHide restrictions & requirements12
  • Data centers are not expressly listed as a permitted use. Land use is limited by zoning district; in M-1, an industrial process not specifically enumerated requires City Council approval of its location before a zoning permit may issue. Permitted M-1 uses

  • A building permit is required to erect, move, add to, or structurally alter a building or structure, and it must conform to the ordinance unless the Board of Adjustment issues a written order. Building permits required

  • A zoning permit is generally required before land or a structure in an R, C, or M district is newly created, erected, changed, converted, or enlarged. The ordinance exempts continued existing uses and principally single-family dwellings; a home occupation in a residential district still requires a permit. Zoning permits required

  • A required zoning permit must match the approved use, arrangement, and construction; land and buildings may be used only for the use for which the permit was issued. Use limited to the permit

  • In M-1, a site plan must be submitted to and approved by the Building Official before a zoning permit is issued. In C-1, the same requirement applies to commercial or multiple-family uses or structures. M-1 site plan requirement

  • M-1 development must meet minimum lot and dimensional standards: 10,000 square feet of lot area, 100 feet of lot width, 75% maximum lot coverage, a 15-foot front yard, and side and rear yards that increase when adjoining residential districts. M-1 lot and setback rules

  • M-1 buildings are limited to 150 feet unless they are set back an additional foot for each four feet of height above 150 feet. M-1 height limit

  • In M-1, total building floor area may not exceed one and one-half times the lot’s square footage. M-1 floor-area limit

  • Off-street parking is required when a building or structure is erected or enlarged or its capacity increased, and parking spaces must be on private property, measure 9 by 20 feet excluding aisles, and have adequate ingress and egress. Parking requirements

  • Permit fees and other charges are set by the City Council, and a permit may not issue until applicable fees and expenses are paid in full. Fees payable before issuance

  • A building permit expires if work does not begin within 90 days; it also expires if work is not substantially completed within two years, after which further work requires a new permit. Building permit deadlines

  • A zoning permit becomes null and void if it is not used within six months after it is granted. Zoning permit expiration