City of Glenn Heights
Pro-Data Center Policies
Glenn Heights zoning allows a data center and electrical substation on about 141 acres, but construction still requires site-plan review and traffic, noise, and lighting studies.
current law · City of Glenn Heights; the planned development at 1118 Uhl Road (140.984-acre tract)Rezones about 141 acres from residential to planned industrial development for a data center and electrical substation, with construction still subject to site-plan review.Ordinance O-15-24 / Planned Development District PD-30
What this means
The zoning change enables a data center and electrical substation on about 141 acres, a meaningful benefit. But it does not authorize construction by itself: the project still needs site-plan review and traffic, noise, and lighting studies, which add requirements. The zoning change allows the data center and substation, while future development still requires review.
Restrictions & requirementsHide restrictions & requirements2
Future development must go through the city’s site plan review process before construction. site plan process
Before building, developers must submit traffic, noise, and lighting studies. traffic, noise and lighting studies
Benefits & exceptionsHide benefits & exceptions2
The zoning change allows data center and electrical substation uses on about 140 acres previously zoned residential. It establishes a development framework, but does not itself authorize construction; future development must go through site-plan review, and developers must submit traffic, noise, and lighting studies. The zoning change and review requirements
The approved zoning allows supporting infrastructure, including generator yards, storage facilities, and private utility improvements. Supporting infrastructure allowed by the regulations