City of Edna
Pro-Data Center Policies
Edna allows data centers in industrial districts, while commercial locations need a special-use permit and may face added review or conditions. Projects must still follow the city’s usual land-use rules.
current law · City of EdnaDefines data centers broadly and allows them in industrial districts only with a specific-use permit, while permitting them in planned-development districts.Land Use Management Ordinance, City of Edna (including Ord. No. 2026-05 amendment)
What this means
The measure makes data centers permitted in industrial districts, while commercial districts require a special-use permit, which can add review and conditions. This is a modest net benefit, not a major incentive, and projects still must meet the city’s usual land-use rules.
People behind it
- City of Edna City Council
Approved the first reading of the proposed ordinance updating the Comprehensive Plan and zoning requirements.
Restrictions & requirementsHide restrictions & requirements2
In the Commercial (C) District, data centers require a specific use permit; they are permitted in the Industrial (I) District. Data Center
A specific use permit requires a public hearing, proper notice, and a Planning Commission recommendation before City Council action. The Council may require plans and operating information and impose operating, location, construction, or other safeguards. public hearing and proper notice
Benefits & exceptionsHide benefits & exceptions5
The use schedule lists data centers as permitted in the Industrial District, allowing them there without a specific use permit. Data Center
The schedule also lists data centers as eligible for a specific use permit in the Commercial District. The City Council may approve such permits after a public hearing and may impose operating, location, construction, and protective conditions. Specific use permits
The ordinance defines data centers broadly to include facilities for server farms, data storage, bitcoin mining, crypto processing, artificial-intelligence processing, cloud computing, and related services, bringing those uses within the data-center classification. Data center definition
In the Industrial District, electrical substations are permitted, and electrical transmission lines are permitted in all listed districts; these land-use allowances can accommodate infrastructure serving a data-center site. Utility and service uses
A data center that was lawfully operating before a zoning change, or was in regular and continuous use when the area was annexed, may qualify as a nonconforming use and continue operating, subject to city regulations. If its structure is destroyed, rebuilding is generally barred unless destruction was partial and no more than 75% of its value; permitted reconstruction cannot expand the use. Nonconforming uses