City of Dallas

Mixed Data Center Policies

Texas offers substantial tax breaks on equipment and electricity to large projects meeting investment and job requirements, while large grid connections face studies, fees, and possible emergency power cuts; some requirements apply only to very large loads.

Rating and summary from Texas statewide as there are no scored current or future laws outside temporary restrictions for City of Dallas.

pending · City of Dallas
Proposes a public hearing on temporarily pausing construction permits and initial occupancy certificates for hyperscale data centers in Dallas.September 23, 2026 council request to consider a hyperscale data-center moratorium

What this means

The proposal would authorize a public hearing about a possible moratorium; it would not itself stop data-center construction, expansion, or operation. The memo describes the requested action as authorizing a public hearing, so its direct effect is limited to considering a future restriction.

Timing

Ends
90 days after adoption

The memo requests a public hearing on implementing a moratorium; it does not itself impose one or specify its duration. If adopted under the cited statute, the moratorium expires after 90 days unless extended. An extension requires a public hearing and written findings, and the total duration may not exceed 180 days. The statute sets the 90-day expiration and extension requirements.

People behind it

  • Dallas City Councilmember who proposed the item by requesting a public hearing on a moratorium for certain hyperscale data-center development.

Restrictions & requirementsHide restrictions & requirements6
  • The memo proposes a moratorium on permits for construction or development of local utilities when limited to communications exchange facilities operating as hyperscale data centers, and on certificates of occupancy for their initial occupancy. It is a request to consider a moratorium, not evidence that one has been adopted. Proposed moratorium scope.

  • To justify a commercial-development moratorium, the city would need written findings based on reasonably available information, including evidence of the need for new or amended rules and the harm to public health, safety, or welfare without a moratorium; the affected geographic boundaries; the commercial property types covered; and the goals for the moratorium period. Required findings.

  • Before imposing the moratorium, the city must give hearing notice at least 30 days in advance, hold two public hearings at least 30 days apart, and begin the final ordinance process within 12 days after the second hearing. The ordinance requires at least two readings at least 28 days apart and approval by at least three-fourths of all governing-body members on final reading. Notice, hearings, and vote requirements.

  • A moratorium initially expires after 90 days. An extension requires a public hearing and written findings, and the total duration cannot exceed 180 days. A new moratorium addressing the same harm, property type, or geographic area cannot be adopted until two years after the prior moratorium expires. Duration and extension limits.

  • A moratorium must allow an applicant to seek a waiver by claiming a right under a development agreement or by providing the public facilities covered by the moratorium at the landowner’s cost; the governing body must vote on a written waiver request within 10 days. Waiver procedure.

  • The moratorium cannot affect a project in progress under Chapter 245, prohibit filing or processing such an application, or prohibit or delay processing a zoning application filed before the moratorium takes effect. Project-in-progress and zoning protections.

Benefits & exceptionsHide benefits & exceptions4
  • Dallas classifies data centers as communications exchange facilities, a utility and public-service use allowed by right in most nonresidential zoning districts, according to the memo’s description of the City Development Code.

  • For a commercial-development moratorium not based on a shortage of essential public facilities, the City must make written findings showing that existing regulations are inadequate to prevent harm to public health, safety, or welfare. The findings must identify the harm, the area and types of property covered, and the goals of the moratorium—requirements that constrain when and how such a moratorium may be imposed. Existing ordinances must be inadequate

  • Moratoria are time-limited: one expires after 90 days unless extended with required findings, extensions cannot exceed 180 days in total, and a new moratorium addressing the same harm, property type, or area is barred for two years after the prior one expires. The statute also protects projects in progress under Chapter 245 and zoning applications filed before the moratorium takes effect. A moratorium adopted under this subchapter expires Projects in progress

  • A permit applicant may seek a moratorium waiver by asserting rights under a development agreement or offering to provide the facilities covered by the moratorium at the applicant’s expense; the governing body must vote on the request within 10 days. apply for a waiver

Sources

pending · City of Dallas
Proposes reviewing Dallas’s development code to create specific land-use rules for data centers or update rules for communications exchange facilities; no change has been enacted.August 11, 2026 council request to consider data-center zoning-code amendment

What this means

This memo only requests a public hearing to consider possible code changes; it does not itself add rules or benefits for data centers. It says the request is to authorize the hearing, not make an amendment, so it has no meaningful direct effect on building, expanding, or operating them (“not the amendment to the development code at this time”).

People behind it

  • Councilmember who proposed the request for a hearing and code amendment.

  • Councilmember who signed in support of the request.

  • Councilmember who signed in support of the request.

Show 3 more peopleShow fewer people
  • Councilmember who signed in support of the request.

  • Councilmember who signed in support of the request.

  • Mayor who referred the request to the Committee on Economic Development.