City of Coupland

Mixed Data Center Policies

Texas offers substantial tax breaks on equipment and electricity to large projects meeting investment and job requirements, while large grid connections face studies, fees, and possible emergency power cuts; some requirements apply only to very large loads.

Rating and summary from Texas statewide as there are no scored current or future laws outside temporary restrictions for City of Coupland.

failed · City of Coupland
Subjects data centers to general zoning rules and case-by-case review as an unlisted use; it does not establish data-center-specific requirements.No identified Coupland data-center-specific measure

What this means

The ordinance does not specifically ban data centers, but it says a new or unlisted use must be classified by the city, adding some uncertainty and approval steps. It also requires permits and occupancy approval for permanent structures, so the overall effect is a minor hurdle rather than a major barrier.

People behind it

  • Adopted and enacted the zoning ordinance.

Restrictions & requirementsHide restrictions & requirements11
  • Data centers are not expressly listed. A new or unlisted use must be referred to the Planning and Zoning Committee for a zoning-classification recommendation, and the City Council determines the classification by resolution; land use must conform to the zoning rules for its district. Unlisted uses

  • When applicable, permanent construction requires City Council approval and a building permit; occupancy requires a certificate of occupancy after inspection. A change to a different use classification also requires a certificate of occupancy. Building permits and occupancy

  • Where applicable, a building site must meet one of the ordinance’s lot-creation conditions, such as being part of an approved recorded plat, qualifying as a separately owned parcel fronting a dedicated street, or being part of an approved site plan. Access must be by public street or drive. Creation of building site

  • If the applicable zoning district allows a data center only by specific use permit, the application requires a scaled site plan and public hearing; the City Council may impose conditions that must be met before occupancy. Specific use permits

  • A zoning change involves public hearings and notice: affected owners within 200 feet must receive written notice at least 10 days beforehand, and notice must be published at least 15 days beforehand. A request denied with prejudice cannot be resubmitted for 180 days; a zoning protest meeting the ordinance’s 20-percent threshold requires a three-fourths Council vote. Zoning amendments and notice

  • If a planned development district is used, it must cover at least 3 acres and requires conceptual and development plans approved by the Planning and Zoning Committee and City Council. The initial development plan is due within 6 months of conceptual-plan approval; if the project is not completed within 2 years, the original concept plan may be reviewed. Planned development requirements

  • In a flood-plain district, a building or structure cannot be erected until City Council approval following engineering studies establishing that it will not be subject to flood damage or create a flood hazard. Permitted uses in the flood-plain portion of a district are limited. Flood-plain restrictions

  • District-specific limits can constrain a facility’s height, lot size, coverage, and setbacks. For example, the ordinance sets a 35-foot height limit in the B-1, B-2, and I-1 districts; minimum lot areas of 1 acre in B-1 and 2 acres in B-2 and I-1; and maximum building coverage of 40% in B-1 and 50% in B-2 and I-1. These standards apply if the project is located in those districts. Business and industrial district standards

  • Off-street parking is required under the ordinance’s use-based schedule. For uses not listed, the City Council determines the most similar listed use; the schedule includes one space per 1,000 square feet of gross floor area or one per two employees, whichever is greater, for warehouse, wholesale, manufacturing, and other industrial-type uses. Retail, commercial, and industrial structures of at least 3,000 square feet also require loading space at a ratio of one per 20,000 square feet. Parking and loading requirements

  • A lawful nonconforming use or structure may not be expanded beyond the tract it occupied when the ordinance took effect. If the nonconforming use is discontinued for 6 months, it is treated as abandoned; if a nonconforming structure is destroyed, it may be rebuilt but the use’s size and function cannot be expanded. Nonconforming uses and structures

  • A violation of the ordinance can result in a fine of $500 per day, with each day treated as a separate offense. Violation penalty