City of Cibolo

Strongly Pro-Data Center Policies

Guadalupe County grants the project a conditional tax break, with 90% abatements for five years and smaller abatements through year ten, in exchange for commitments and safety, road, insurance, and reporting requirements.

Rating and summary from Guadalupe County as there are no scored current or future laws outside temporary restrictions for City of Cibolo.

pending · City of Cibolo
Initiates development of data-center zoning rules, including proposed permits and operating standards; no data-center-specific rules have been adopted yet.Cibolo Council Direction to Develop Data Center Regulations

What this means

If enacted, the proposal would add meaningful costs and review steps: even limited-use centers could face noise studies, sound testing, and other operating requirements (draft standards). Larger or certain specialized centers would need a special-use permit (SUP required), but the proposal does not ban data centers, and the packet describes these rules as drafts for future consideration.

People behind it

  • Initiated the regulatory development process and is scheduled to deliberate and direct development of proposed data-center regulations; the packet identifies the agenda item as discussion and direction to develop regulations.

  • Named in the proposed motion as the official to be directed to have the Planning and Economic Development Department initiate the UDC amendment process; the motion says direct the City Manager.

  • Named in the proposed motion as the department to initiate the procedure to amend the 2024 Unified Development Code; the motion specifies have the Planning and Economic Development Department initiate the procedure.

Restrictions & requirementsHide restrictions & requirements15
  • Draft proposal: A specific use permit (SUP) would be required for hyperscale data centers of 75 MW or more, AI-focused facilities, facilities using evaporative cooling, and closed-loop fan-cooled facilities over 75 MW. SUP required for these data-center types

  • Draft proposal: The limited-use category is restricted to data centers of 75 MW or less using closed-loop cooling; the draft defines facilities outside those criteria as “Data Center, All Other.” 75 megawatts or less

  • Draft proposal: Applicants would disclose electrical demand, pay interconnection and transmission study costs, and undergo review of transmission upgrades needed to reliably serve the project. interconnection and transmission study costs

  • Draft proposal: Nighttime noise would be limited to 65 dBA at property lines, or to levels equivalent to the noise existing when construction begins, verified by a pre-development noise study. 65 dBA nighttime at property lines

  • Draft proposal: Applicants would provide an acoustical study by a qualified consultant modeling full buildout, peak summer cooling, equipment operating simultaneously, generators, transformers, rooftop equipment, tonal and low-frequency sound, and site topography and reflective surfaces. study prepared by a qualified acoustical consultant

  • Draft proposal: Post-construction sound testing would be required before final occupancy and after substantiated complaints. before final occupancy

  • Draft proposal: Emergency generators would need a noise-management plan, and routine generator testing would be limited to weekdays from 8:00 a.m. to 5:00 p.m., except during emergencies. Emergency-operation exemptions would apply only for the duration of a genuine outage, emergency, or legally required reliability event. 8:00 a.m. and 5:00 p.m. on weekdays

  • Draft proposal: Noise-related equipment and site conditions would include low-noise fans, nighttime fan management, landscape berms, acoustically enclosed all-weather generators, and generator stacks oriented to discharge vertically upward. Low noise fans required

  • Draft proposal: Generator and transformer areas would need spill containment; cooling-water chemicals would need secondary containment; refrigerant systems would need leak detection and automatic isolation where appropriate; and low-impact development would be required where soils and site conditions permit. spill containment

  • Draft proposal: Operators would provide proof of applicable TCEQ generator and air-quality authorizations; the attachment also identifies EPA Tier 4 engine-emission standards as a pollution standard. Proof of all TCEQ generator and air-quality authorizations

  • Draft proposal: Material expansions involving electrical load, cooling, generators, or water use would trigger amended review. material expansion of load

  • Draft proposal: Data centers with domestic wastewater treatment facilities would need TCEQ permits to construct and operate, including operator licensing and effluent-quality and discharge monitoring; facilities classified as significant industrial users would also have to comply with applicable pretreatment rules and requirements. TCEQ Permits to construct and operate domestic wastewater treatment facilities

  • Draft proposal: The listed standards include compliance with adopted fire and building codes and submission of emergency-response and water-containment or runoff-management plans. Emergency response plans

  • Draft proposal: The off-street parking table would require one space per facility, plus one additional space per two employees. one (1) per facility

  • The proposed ordinance amendments would go through statutory zoning procedures, including referral to the Planning and Zoning Commission for a public hearing and recommendation, required public notices, public hearings before the commission and City Council, and final Council consideration. public hearings before the Planning and Zoning Commission and City Council

Benefits & exceptionsHide benefits & exceptions2
  • The draft creates a Limited Use category for data centers with electrical capacity of 75 MW or less that use closed-loop water cooling, while reserving Specific Use Permits for specified categories such as AI-focused centers and evaporative-cooled facilities. This provides the qualifying facilities a less discretionary approval path, subject to the proposed standards and applicable zoning. Limited-Use Permitted Data Centers

  • The draft sets a minimum parking requirement of one space per facility, plus one additional space per two employees. This may reduce required parking compared with a larger per-employee standard. one additional space per two employees