Neutral Data Center Policies
Carrizo Springs requires ordinary building permits, fees, and electrical inspections, adding some cost and delay. It prohibits certain communication towers, but that rule does not ban data centers.
current law · City of Carrizo SpringsDoes not establish any data-center-specific regulations; it sets generally applicable building and electrical requirements.Telecommunication towers prohibited, Carrizo Springs Code of Ordinances § 8-3 (Ordinance No. 628)
What this means
Data centers would face ordinary building-code, permit-fee, and electrical inspection requirements, which add some cost and delay (permits and fees; electrical work inspection). The city also prohibits certain communication towers, but the measure does not ban data centers or provide them special benefits, so the overall effect appears minor (telecommunication towers prohibited).
People behind it
- Chief building official
Enforces the dangerous and unsafe structures provisions of Chapter 8, as specified in the enforcement-official provision.
Restrictions & requirementsHide restrictions & requirements4
Building and zoning permits and fees apply to residential and commercial construction; the city collects fees under a schedule established by the council. The permits and fee schedule is set by the council.
The city adopts the 2024 International Building Code, including its provisions on building standards, permits, and fees. The 2024 edition is adopted as the building code.
Electrical work requires a city permit before construction, installation, or alteration begins. Permits may be issued only to master electricians or to a person doing the work on their own existing legal homestead, subject to submitting plans and satisfying the inspector; a temporary service not attached to a building is excepted. The permit requirement and exceptions are set out in the code.
Electrical permit fees must be paid before the permit is issued and work begins; permitted work is inspected, and approval is required before a utility may energize the line. Fees are due before work begins, and the utility may not energize the line until inspector approval.
Benefits & exceptionsHide benefits & exceptions1
Temporary electrical service is allowed without a permit or inspection if it is not attached to a building and uses approved SE cable. This is a limited exception for temporary service, not a general exemption for a data center’s permanent electrical work. Temporary service without inspection or permit