City of Bryson
Neutral Data Center Policies
Bryson’s building rules apply to unsafe or code-violating buildings, not data centers specifically; a violating facility could face repair or demolition, but the effect on development is limited.
current law · City of BrysonRequires owners to repair or demolish unsafe buildings, including data centers, but sets no data-center-specific requirements.TITLE XV: LAND USAGE, Chapter 151–155
What this means
The measure does not single out data centers or limit construction generally; it addresses buildings that are unsafe or violate applicable codes (building standards). A data center found in violation could face repair or demolition costs, but this conditional safety process is unlikely to meaningfully affect data center development overall (repair or demolition orders).
People behind it
- City Council of the City of Bryson
Enacted and adopted the ordinance establishing the City’s Code of Ordinances.
- City Secretary
Was directed to file a copy of the adopted Code of Ordinances.
Restrictions & requirementsHide restrictions & requirements8
If a data-center building is suspected of violating the chapter, the Building Inspector or designee may inspect it. Inspections are required for suspected violations.
A building may be ordered repaired, removed, or demolished if it meets the chapter’s substandard-building criteria, including structural instability, specified deterioration thresholds, code violations, or inadequate safety or sanitation conditions. The standards for determining whether action is required.
A reported violation requires a City Council hearing, with notice to specified parties; the hearing must be at least 10 days after notice. If a violation is found, repair, removal, or demolition is generally required within 30 days. More than 30 days may be allowed if the work cannot reasonably be completed in that time, but more than 90 days requires a detailed plan and schedule and proof that the work’s scope and complexity require it. Hearing and work deadlines.
If repairs are estimated to cost 50% or more of the building’s appraised value, the building must be demolished or removed; demolition or removal is also required if repairs cannot bring it into compliance. The 50% repair-cost threshold.
An owner, lienholder, or mortgagee may appeal the hearing decision to district court, but must file within 30 calendar days after the order is mailed. The 30-day appeal deadline.
If ordered work is not completed on time, the City may perform or arrange repair, removal, or demolition and charge the expenses to the responsible parties or assess them against the property. City work and expense recovery.
The City may record a lien for its repair, removal, or demolition expenses, except against property protected as a homestead; the lien is extinguished if the expenses are reimbursed. Lien for City expenses.
A property owner may be fined up to $1,000 per day for a violation, or up to $10 per day if the property is the owner’s lawful homestead, provided the owner was notified and then violated the chapter or failed to comply. Daily penalty limits and conditions.