City of Bridgeport
Neutral Data Center Policies
Bridgeport’s zoning rules require projects to follow district use and building requirements and generally obtain a building permit; industrial uses are exempt from listed off-street parking requirements, and there are no data-center-specific incentives.
current law · City of BridgeportRegulates land uses generally but does not specifically mention or impose data-center-specific requirements.EXHIBIT 14A: Zoning Ordinance - City of Bridgeport, TX
What this means
The ordinance does not specifically address data centers, but it requires development to follow district use and building rules and generally requires a building permit, adding some location and approval steps (district use rules, building permit requirement). Industrial uses are exempt from the listed off-street parking requirements, which may ease one burden, but the measure offers no data-center-specific incentives.
People behind it
- City Council of the City of Bridgeport
Enacted the zoning ordinance: “BE IT ORDAINED BY THE CITY COUNCIL”.
- Building Inspector
Named as the official responsible for administering and enforcing the ordinance.
Restrictions & requirementsHide restrictions & requirements6
The ordinance bars using land or erecting, reconstructing, or structurally altering a building for a purpose not permitted in its zoning district. Data centers are not expressly listed, so whether this limits a particular project depends on its zoning and use classification. No building shall be erected
Construction, alteration, repair, moving, or demolition of a building or structure requires a building permit; land or a building generally cannot be occupied or used until a certificate of occupancy and compliance is issued. Permanent water, sewer, electrical, or gas connections also require that certificate. without first applying for and obtaining a building permit
A zoning change may be needed if a proposed data-center use is not permitted in the site’s district. The process includes public hearings and notice; an application fee applies, and the applicant may have to reimburse agreed legal or engineering review costs. If the Planning and Zoning Commission recommends against the change, or qualifying owners file a protest, approval requires a four-fifths City Council vote. four-fifths (4/5) of all the City Council
A nonconforming building or structure cannot be added to or enlarged unless the addition or enlargement meets the district’s requirements; a nonconforming use generally cannot be expanded or extended. These limits may restrict expansion of an existing data center that is nonconforming. shall not be added to or enlarged
The ordinance sets district-specific limits on building height, yards, lot area, and other development dimensions. For example, R-1 and R-2 buildings are limited to 2½ stories or 35 feet and have front- and side-yard requirements; the applicable requirements depend on the site’s district. shall not exceed two and one-half (2-1/2) stories or thirty-five (35) feet
Violations may result in a fine of up to $2,000, with each day a violation continues treated as a separate offense. Each day such violation is committed
Benefits & exceptionsHide benefits & exceptions5
If a data center is classified as an industrial use, the Industrial District allows any manufacturing or industrial process not prohibited by other law. The ordinance requires City Council approval for specified uses, but data centers are not among the listed examples. Any manufacturing or Industrial process
In the Industrial District, multiple buildings may be located on one lot if they are under common ownership, which could accommodate a multi-building campus. More than one building may be permitted
For industrial-zoned uses, the parking rules specify no minimum parking requirement; the ordinance also exempts industrial-zoned land uses and structures from the nonresidential parking provisions. Industrial: None
The Industrial District requires no front or rear yard. No side yard is required unless one is provided, and a side yard of at least five feet is required where the lot abuts a dwelling-zoned lot. No rear yard required
Industrial buildings may be up to twice the width of the widest street they are on, capped at 10 stories or 120 feet unless the City Council grants a special permit for greater height. in no case shall the height be greater than ten (10) stories