Brenham’s enacted zoning amendments allow data centers in industrial districts only with specific-use permits and strict conditions, including no water-based evaporative cooling, power reporting, and a 300-foot setback from nearby homes or public institutions.
current law · City of BrenhamRequires data centers in Brenham’s industrial district to get a special-use permit and meet rules on water cooling, electricity reporting, equipment screening, parking, and distance from homes and public institutions (additional requirements and restrictions).Brenham zoning-code amendments for data centers (May 2026)
What this means
The measure would allow data centers in industrial districts, but only with specific-use-permit approval and strict conditions. The ban on water-based evaporative cooling, along with power-reporting requirements and a 300-foot setback from nearby homes or public institutions, could make projects significantly harder to build and operate.
Restrictions & requirementsHide restrictions & requirements6
Data centers in Industrial Districts require prior approval through a specific use permit process. Specific use permit approval
Water-based evaporative or consumptive cooling is prohibited, including systems that use water evaporation or consumption directly or indirectly to cool the data center. Water-based cooling methods are prohibited
For specific-use-permit review, applicants must submit an electric-demand report covering projected minimum and maximum loads, needed infrastructure, peak-demand management, and on-site backup generation. If the property is outside the city’s electric service territory, the applicant must also provide the serving utility’s written certification of available capacity and its ability and intent to serve the projected load. Electric-demand report and utility certification
All ground-mounted equipment must be screened on every side by a wooden or masonry wall at least six feet tall and at least one foot taller than the equipment, whichever height is greater. Screening height requirements
Required off-street parking is one space per 300 square feet of floor area used for office, meeting, training, or security personnel. Parking-space ratio
Where an industrial use is adjacent to a residential or public institutional use, a data center building and its ancillary equipment must be at least 300 feet from that use’s property line. 300-foot separation requirement
Benefits & exceptionsHide benefits & exceptions1
Data centers are eligible for approval as a specific use in Industrial Districts, subject to the specific-use-permit process and the ordinance’s requirements. Allowed as a specific use in Industrial Districts