City of Bastrop

Mixed Data Center Policies

Bastrop allows data centers in industrial areas, requires special approval in general commercial areas, and bars them in some other districts. Standard development reviews may add cost and delay, but no special operating restrictions are described.

Rating from Texas statewide as there are no scored current or future laws outside temporary restrictions for City of Bastrop.

current law · City of Bastrop
Limits data centers to industrial areas, allows them in general commercial areas only with special approval, and prohibits them in other zoning districts.Bastrop Development Code, Chapter 14, Sections 14.02.008 and 14.04.007 (data center use classification)

What this means

Data centers would be allowed in industrial areas, but need special approval in general commercial areas and are barred from some other districts. Standard site-plan and development reviews add some cost and delay, but there are no special operating restrictions.

Timing

Ends
At least 60 calendar days after the filing of a complete demolition application

This is a limited demolition stay for designated historic landmarks and contributing structures in a Historic District, not a general development moratorium. A demolition permit cannot issue until the stay has expired and a Certificate of Appropriateness has been approved or deemed approved (the 60-day stay).

People behind it

  • Directed staff to amend the Development Code and adopted the ordinance repealing the B3 Code and adopting the Bastrop Development Code.

  • City Manager who submitted agenda items and was asked to carry out the recommended Development Code actions.

  • City Secretary directed to implement and codify the ordinance.

Show 3 more peopleShow fewer people
  • City Attorney directed to implement and codify the ordinance.

  • Directed to implement and codify the ordinance.

  • Administers zoning enforcement and administrative development decisions under Chapter 14.

Restrictions & requirementsHide restrictions & requirements10
  • Data centers are permitted by right in the Industrial (IND) district, require a Conditional Use Permit in General Commercial (GC), and are not permitted in the other listed districts. IND standards include a minimum lot size of 2.5 acres and a 60-foot building-height limit.

  • A data center in GC requires a Conditional Use Permit, public hearings before the Planning and Zoning Commission and City Council, and required public notice. City Council decides the application and may impose conditions to address impacts, including operational limits.

  • New nonresidential buildings require an approved Site Plan before a building permit. Site Plan review may also be triggered by specified exterior additions or intensifications and requires plans and documentation such as site layout, parking and access, landscaping, trees, drainage, utilities, and lighting where applicable.

  • A Traffic Impact Analysis is required for projects generating at least 100 new peak-hour trips or 1,000 new average daily trips, and may also be required for safety or operational concerns. Applicants may have to fund or construct proportionate transportation improvements or dedicate right-of-way.

  • New construction generally must provide sidewalks along street frontages before receiving a Certificate of Occupancy. A fee-in-lieu or deferral is available only with Director approval under stated conditions.

  • Landscaping rules require landscaped area of at least 10% of net lot area for industrial/employment development and 20% for commercial development, generally installed before occupancy. Industrial development abutting residential or mixed-use property must provide a 30-foot landscape buffer; protected-tree impacts or removal can require a permit and mitigation.

  • Nonresidential outdoor lighting is limited to 100,000 lumens per net acre in a contiguous illuminated area and must meet shielding requirements. Lighting left on more than 30 minutes after closing or completion of activities must be reduced to 25% or less of the allowed output, and building-permit applications must include an outdoor-lighting plan.

  • Because the parking schedule does not specify a data-center ratio, the Planning Director determines the most similar listed use or may require a parking-demand study.

  • Applicants must pay applicable City fees and may be charged actual costs for specialized third-party review.

  • A data storage building accessory to a primary commercial use is not permitted in P/OS, SF, or MU districts, requires conditional approval in RR, and is permitted in GC, PI, and IND.

Benefits & exceptionsHide benefits & exceptions4
  • Data center/research and development lab use is permitted by right in the Industrial (IND) district, requires a Conditional Use Permit in General Commercial (GC), and is not permitted in the other listed districts. IND sites must meet a 2.5-acre minimum lot size, a 60-foot maximum building height, and 65% maximum impervious coverage; increased setbacks apply where a site abuts residential zoning. Use table IND standards

  • Data storage buildings accessory to a primary commercial use are permitted in General Commercial (GC), Public Institutional (PI), and Industrial (IND) districts; they may be approved conditionally in Rural Residential (RR) and are not permitted in the listed SF or MU districts. Data Storage Buildings

  • A new nonresidential building requires a site plan, but the Director decides it administratively without a public hearing. Approval authorizes submission of construction drawings and building-permit applications and runs with the land, but expires after two years if no building permit is issued and construction is not active; one extension of up to six months is possible. Administrative site-plan decision Approval and construction submissions

  • A data center could seek a Planned Development District (PDD) for site-specific standards and a master plan that can address infrastructure phasing. The PDD and master plan remain in effect unless amended, superseded, or repealed by ordinance. Approval requires consistency with the Comprehensive Plan, adequate public facilities, clear and enforceable standards, and equal or superior outcomes to base zoning in at least three specified areas. The usual minimum site size is five acres, with a one-acre exception for qualifying infill or constrained sites. PDD standards and development matrix Master plan duration