Town of Annetta South
Neutral Data Center Policies
Parker County opposes county tax breaks and other incentives for data centers, which could make projects less attractive, but does not ban construction or operation. Other provisions ask state officials to consider safeguards rather than require them.
Rating and summary from Parker County as there are no scored current or future laws outside temporary restrictions for Town of Annetta South.
failed · City of Annetta SouthProhibits data centers unless the city approves them as a permitted similar use, since the zoning ordinance does not specifically list data centers.No data center-specific laws or bans identified in Annetta South
What this means
Data centers are not listed as permitted uses, and the ordinance says unlisted uses are prohibited unless the Planning Commission finds them similar to an allowed use (unlisted uses are prohibited). A project could seek zoning approval, but it would also face public review and site-plan requirements, creating significant barriers rather than an outright ban.
People behind it
- Annetta South Planning and Zoning Commission
Held a public hearing and recommended the zoning ordinance to the City Council. The ordinance was submitted with the Commission’s recommendation.
- Zoning Administrator
Responsible for administering and enforcing the ordinance; the role is assigned to the City Secretary unless the Mayor designates another official. The ordinance specifies this responsibility.
Restrictions & requirementsHide restrictions & requirements6
Land or structures may be used only for uses permitted in their zoning district. Uses not specifically listed are prohibited, although the Planning and Zoning Commission may permit a new use it finds similar to uses listed for that district; an authorized new use is then sent to the City Council for a text amendment. Unlisted uses are prohibited.
A zoning change requires public hearings and approval, including a Planning and Zoning Commission recommendation and final City Council action. The process includes public notice, written notice to owners within 200 feet, and a sign on the property; the change must be consistent with the Comprehensive Plan, and zoning cannot be finalized until the property is annexed. Applications also require a fee. Notice to each property owner within 200 feet.
A site plan and its approval are required before a building permit may be issued. The City Council considers approval after review by the Zoning Administrator and recommendations from the Planning and Zoning Commission; approval requires applicable ordinance compliance and adequate capacity for water, sewer, and access. The required plan materials include, among other things, utilities and drainage, site topography, landscaping, building elevations, and lighting. Site plan approval shall be required prior to the issuance of a building permit.
New development must provide a landscape plan and meet landscaping standards, including landscaping at least 20% of the property, preserving 10% of existing trees over six inches, and providing a 20-foot landscaped strip along each public street. A minimum of twenty (20) percent of the property shall be landscaped.
A newly erected or structurally altered building cannot be used, occupied, or changed to a new use until the City issues a certificate of occupancy confirming compliance with the ordinance and applicable building codes. No building hereafter erected or structurally altered shall be used.
An approved site plan expires after two years unless the development has received a certificate of occupancy. effective for a period of two (2) years.
Benefits & exceptionsHide benefits & exceptions4
A data-center project already under construction, or covered by an unexpired building permit issued under the prior ordinance, may proceed under that ordinance; the completed use or structure may be nonconforming under the new ordinance. Construction in progress
A zoning-change application filed before the ordinance took effect is processed under the requirements in force when it was filed. Pending applications for zoning changes
If a project had submitted a site plan, building-permit application, and construction plans before the effective date, showing development under the prior ordinance, the Building Official must grant a permit under the prior ordinance’s requirements. Site Plan, building permit application and construction plans
A lawful data-center use that becomes nonconforming may generally continue; it may change to another nonconforming use of the same or more restricted classification, subject to limits. The right is lost if the use is discontinued for more than 90 days; total destruction of the building ends the right, and rebuilding after partial destruction depends on the extent of damage and, in some cases, Council approval. A non-conforming use of a property is discontinued