City of Angus
Anti-Data Center Policies
Angus requires permits and council approval for building projects, while zoning limits allowed uses. A data center’s classification may need council review, adding an approval step and possible delay.
current law · City of AngusRequires the city council to assign unlisted uses, potentially including data centers, to an appropriate zoning district; it contains no data-center-specific rules.Ordinances | City of Angus
What this means
The code does not specifically ban data centers or offer them incentives, but building projects need permits and council approval, and zoning controls which uses are allowed. An unlisted use may need a council decision on its zoning classification, adding approval steps and potential delay (building permits require city council approval; classification of new and unlisted uses).
Restrictions & requirementsHide restrictions & requirements11
Data centers are not expressly listed as a use. A new or unlisted use must be referred to the city council, which determines the appropriate zoning district by resolution; land uses must conform to the district’s rules. The council determines the zoning classification.
If zoning approval requires a change in classification, specific-use permit, or variance requiring legal notice, the application carries a nonrefundable $250 fee. Zoning changes require a public hearing, advance notice, and council action; written objections meeting the stated threshold can require a three-fourths council vote. A $250 administration fee.
Where the zoning schedule marks a use for a specific-use permit, council approval follows notice and a public hearing. The application must include a scaled site plan and may be subject to conditions that must be met before occupancy. After proper notice and a public hearing.
A building permit is required before erecting, constructing, or locating a building or structure; each permit must be approved by the city council, and the application must include plans and a description of the structure and its intended use. The council or inspector may refuse a permit for specified hazards or other good cause. Each permit must be approved by the city council.
Building-permit costs include a fee based on building type, size, or value; inspection fees are additional and are set by the designated building inspector. Inspection fees are set by the designated building inspector.
A building or land use may not be occupied or changed to a different use before the required certificate of occupancy. For new or altered buildings, the code calls for foundation, plumbing, electrical, and framing inspections before the certificate is issued; permanent utilities also require a certificate of occupancy. No permanent structure may be occupied.
Electrical installations and alterations require a city permit, currently stated as $15 per permit; deviations from the permitted work need written city approval. Electrical contractors must present a master electrician’s license, and aluminum wire is prohibited. No aluminum wire shall be used.
If classified in an industrial district, operations face district-specific requirements. In I-1, most business, service, or processing activity must be enclosed, certain storage near residential districts must be enclosed or screened, and uses must meet nuisance and noise limits. I-2 uses must meet listed environmental performance standards, including a property-line noise limit of 75 decibels for no more than 15 minutes in any hour. Sound levels of noise at the property line.
Subdivision development requires city-council plat approval. Building, plumbing, and electrical permits may not be issued for a lot until the final plat is approved and recorded and subdivision standards are met; plat applications also carry filing fees. No building, plumbing, or electrical permit shall be issued.
Construction, demolition, alteration, or repair in a residential or business district is restricted to 7:00 a.m.–9:00 p.m., except for urgent public-safety necessity with a mayor-issued permit. Other than between the hours of 7:00 a.m. and 9:00 p.m..
Where city sewer service is deemed available, owners of buildings and residences must apply to connect and pay the applicable fees; the code states a $250 sewer-tap fee plus actual connection materials and labor costs. A sanitary sewer connection fee of $250.00.
Benefits & exceptionsHide benefits & exceptions2
Unlisted-use zoning review: The building inspector may refer a new or unlisted use to the city council, which determines the appropriate zoning district based on the use’s characteristics and compatibility. This provides a route for review of a data center, but does not guarantee approval. classification of any new or unlisted form of land use
Planned development zoning: A PD district can combine uses allowed in different districts and allow flexibility in land and building design. It requires at least three acres, city council approval, and plans and standards specified in the granting ordinance. permit flexibility in the use and design of land and buildings