City of Angleton
Neutral Data Center Policies
Brazoria County’s enacted resolution asks state leaders to consider giving local governments more authority over data-center impacts, including noise, light, water, assessments, setbacks, and fees. It creates no binding requirements for data-center projects itself.
Rating and summary from Brazoria County as there are no scored current or future laws outside temporary restrictions for City of Angleton.
pending · City of AngletonRequires data centers with at least 20 MW of capacity to obtain City Council approval and meet rules on location, water and power capacity, noise, security, and cleanup when operations end.Draft Angleton data-center zoning amendment, proposed Code §§ 28-63 and 28-64
What this means
The proposal would make data centers of 20 MW or more significantly harder to build, expand, or operate: they would need city approval, stay at least 500 feet from residential property, and provide extensive plans and studies (permit and application requirements). It would also require measures such as closed-loop cooling, 24/7 on-site security, and financial assurance, creating substantial costs and ongoing duties (minimum requirements).
People behind it
- City Council of the City of Angleton
Approved the proposed amendments and is identified as the body enacting the ordinance.
- Planning Development Services Department
Receives applications for specific use permits for data centers.
Restrictions & requirementsHide restrictions & requirements18
A City Council-approved specific use permit is required before a data center can be erected, operated, expanded, or modified. Data centers are listed as permitted by specific use permit only in the LI district.
The data-center rules apply to facilities with an aggregate critical IT load or capacity of 20 MW or greater.
An application is not considered complete until it includes the specified materials, including site plans, noise and emissions assessments, hazardous-materials and emergency plans, traffic and grid-coordination analyses, a decommissioning plan, and a community-engagement plan. The City may request additional information.
Applicants must provide financial assurance, such as a bond or letter of credit, in an amount set by the City Manager based on estimated decommissioning and restoration costs plus a 25% contingency.
A data center must be at least 500 feet from a residentially zoned property line.
A data-center building or structure used as the primary use may not exceed the maximum height allowed in its zoning district.
Buildings visible from public rights of way must incorporate at least three listed architectural features, such as decorative cornices, accents, awnings, or parapets.
Outdoor data-center equipment, including generators, fuel tanks, and cooling equipment, must be screened so it is not visible, in accordance with the referenced screening standards.
A data center must use closed-loop cooling or similar technology that eliminates continuous draws from a public water supply. Applicants must provide a water-capacity availability letter detailing startup and average water use and typical wastewater, if any.
Electricity capacity must be available for permit approval, and the application must include an electricity-capacity availability letter.
The application must include a grid-coordination plan showing coordination with the local utility and regional grid operator, including interconnection status, load profile, ramp rates, redundancy, and curtailment capabilities.
Applicants must use best available noise-control technologies, and cooling operations must be sequenced to minimize nighttime noise. The City may also impose stricter noise limits and other mitigation conditions reasonably related to impacts on residential users.
Generators must be placed the maximum practical distance from residential property lines and equipped with hospital-grade-or-better silencers and enclosures.
At least one trained security person must be on site at all times, 24 hours a day, seven days a week.
Operators must submit an annual registration form to verify compliance with the data-center regulations.
A decommissioning plan must address triggers including 120 consecutive days of ceased operations. After decommissioning, specified equipment and materials must be removed within 120 days unless the City approves retention; the site must be remediated and restored, and an engineer’s completion certification and final report must be submitted within 30 days of completion.
Applicants for data-center site-plan review must pay the applicable site-plan review fee, in addition to other required fees.
Violations may be punished by a fine of up to $500, with each day a violation continues treated as a separate offense.
Benefits & exceptionsHide benefits & exceptions1
Data centers may be located in the LI district with City Council approval of a specific use permit; once approved, they may be erected, operated, expanded, or modified, subject to the ordinance’s requirements. [LI district](https://mccmeetingspublic.blob.core.usgovcloudapi.net/angletontx-meet-9dc89b1371754105a826205128faf8e6/ITEM-Attachment-001-c094839a0b534ceeb90264e1b60786f2.pdf#:~:text=Data%20centers%20(See%20also%20section)