Smith County
For Smith County, see Tennessee’s statewide laws and regulations below. No additional county-specific measures are listed in our research.
Slightly Pro-Data Center Policies
Tennessee rules can limit how much utilities and municipalities absorb data-center-specific infrastructure costs, while allowing certain cost allocations and independent power. Qualifying large projects that meet investment and job requirements can receive equipment tax breaks and a reduced electricity tax.
Incentives
Tax benefits3
The attached amendment introduces a 1.5% electricity tax rate for qualified data centers and adds their computer equipment to industrial machinery. The broader measure also provides enhanced industrial-machinery investment tax credits and additional job tax credits for qualifying businesses.
Provides qualified data centers a 1.5% tax rate on electricity and a tax exemption for cooling equipment and backup power infrastructure. Their computers, related equipment, repair and installation services, and service contracts qualify as industrial machinery, for which no tax is due.
Establishes qualified-data-center tax benefits by adding qualifying computing equipment to industrial machinery and providing a 1.5% electricity tax rate. The broader act also expands industrial-machinery credits for qualifying capital investments and introduces additional job credits for qualifying businesses in distressed counties. Electricity tax relief is counted only as a tax benefit, not duplicated as a utility-rate incentive.
current law · StatewidePublic Chapter 961, enacted through HB 1847, prohibits municipalities and electric utilities from paying or absorbing covered electrical-infrastructure costs for newly constructed or expanded data centers projected to reach at least 50 MW peak demand during their first three years, subject to statutory exclusions.Tennessee Public Chapter 961 / HB 1847 (2026)
What this means
The enacted electrical-infrastructure cost rule can increase project costs by limiting municipal and utility absorption of data-center-specific infrastructure costs. It allows specified system-improvement allocations, standard reimbursements, and independent-power arrangements; it does not impose a data-center construction ban.
People behind it
- Butler
Primary sponsor of HB 1847
- Barrett
Co-prime sponsor of HB 1847
- Reneau
Co-prime sponsor of HB 1847
Show 12 more peopleShow fewer people
- Howell
Co-prime sponsor of HB 1847
- Hawk
Co-prime sponsor of HB 1847
- Taylor
Primary sponsor of SB 2128
- Walley
Co-prime sponsor of SB 2128
- Yager
Co-prime sponsor of SB 2128
- Bailey
Co-prime sponsor of SB 2128
- Bowling
Co-prime sponsor of SB 2128
- Crowe
Co-prime sponsor of SB 2128
- Gardenhire
Co-prime sponsor of SB 2128
- Lowe
Co-prime sponsor of SB 2128
- Powers
Co-prime sponsor of SB 2128
- Stevens
Co-prime sponsor of SB 2128
Restrictions & requirementsHide restrictions & requirements3
Municipalities and electric utilities may not pay or absorb covered electrical transmission and distribution infrastructure costs incurred to serve a covered new or expanded data center, subject to the law's limited exceptions.
The covered data-center definition requires projected peak demand of at least 50 MW during the first three years and excludes specified state-owned facilities and provider facilities primarily supporting network operations or broadband access servers.
The final law applies to conduct and contracts or agreements entered into, amended, or renewed on or after May 7, 2026. Earlier drafts' January 2027 and July 2026 application dates were superseded by adopted amendment HA1209.
Benefits & exceptionsHide benefits & exceptions3
An electric utility may allocate qualifying portions of electrical-infrastructure costs to general utility-system improvements when the statutory conditions are satisfied.
A utility may reimburse a data-center owner or operator under standard policies applicable to comparable customers, without preferential treatment or causing existing customers a rate increase.
A covered data center may purchase energy, capacity, and related services from an eligible Tennessee independent power producer through the authorized interconnection arrangements, subject to federal law and applicable utility approval.
Sources
current law · StatewideEstablishes sales and use tax treatment for qualified data centers, defined generally as facilities making more than $100 million in required capital investment within up to three years and creating at least 15 net new full-time employee jobs paying at least 150% of Tennessee’s average occupational wage; an enacted 2024 amendment also covers certain affiliate transfers.Tennessee Code Annotated §§ 67-6-102 and 67-6-206 — Qualified Data Center Sales and Use Tax Treatment
What this means
The measure substantially lowers operating and equipment costs by exempting qualifying data centers’ cooling and backup-power equipment from sales tax, while electricity remains taxed at 1.5% (cooling and backup-power exemption). Eligibility still requires a large investment and job creation, and applicants for job tax credits must certify recent compliance with specified laws, so the benefits are meaningful but conditional (qualification requirements).
People behind it
- Norris
Primary sponsor of SB2537.
- Dickerson
Co-prime sponsor of SB2537.
- Stevens
Co-prime sponsor of SB2537.
Show 13 more peopleShow fewer people
- McCormick
Primary sponsor of HB1535.
- Brooks K
Co-prime sponsor of HB1535.
- Hazlewood
Co-prime sponsor of HB1535.
- Daniel
Co-prime sponsor of HB1535.
- Zachary
Co-prime sponsor of HB1535.
- White
Primary sponsor of HB2182.
- Gant
Co-prime sponsor of HB2182.
- Lamberth
Co-prime sponsor of HB2182.
- Gillespie
Co-prime sponsor of HB2182.
- Thompson
Co-prime sponsor of HB2182.
- Taylor
Primary sponsor of SB2583.
- Yager
Co-prime sponsor of SB2583.
- Secretary of State
Assigned the public chapter numbers to the enacted measures.
Restrictions & requirementsHide restrictions & requirements4
To qualify as a qualified data center for the statutory tax benefits, a facility must make a capital investment exceeding $100 million within an investment period of no more than three years and create at least 15 net new full-time jobs paying at least 150% of Tennessee’s average occupational wage. The jobs must be permanent positions lasting at least 12 consecutive months, involve at least 37.5 hours per week, and include minimum health-care benefits. The investment period may be extended to a maximum of four years only for good cause determined by the commissioner of economic and community development. The qualified data center definition requires these investment and job thresholds.
A data center transferred to an affiliate can qualify under the qualified-data-center definition only if it previously satisfied the over-$100-million capital-investment requirement and previously created at least 15 qualifying full-time jobs, and the transfer occurs as part of a reorganization under Internal Revenue Code § 368(a). The affiliate-transfer provision requires prior satisfaction of the investment and job requirements.
Electricity sold to or used by a qualified data center is subject to a 1.5% sales and use tax, creating an ongoing operating cost. The statute imposes a 1.5% tax on electricity used by qualified data centers.
A qualified data center seeking job tax credits must certify in its business plan that, during the previous 12 months, it was not found to have violated the federal WARN Act, the Fair Labor Standards Act, or federal immigration laws. Failure to provide the certification disqualifies the data center from the job tax credits. The statute requires the 12-month compliance certification and denies credits without it.
Benefits & exceptionsHide benefits & exceptions7
Qualified data centers can qualify for sales and use tax exemptions by investing more than $100 million in Tennessee during an investment period of up to three years and creating at least 15 net new full-time jobs paying at least 150% of the state average occupational wage. The investment period may be extended by up to one additional year for good cause.
Electricity sold to or used by a qualified data center is taxed at the reduced rate of 1.5% rather than the standard sales and use tax rate.
Cooling equipment used by a qualified data center is exempt from sales and use tax. The equipment must be used primarily for and be necessary to the data center's operations.
Backup power infrastructure used by a qualified data center is exempt from sales and use tax. Covered infrastructure includes backup power generation, battery systems, and related infrastructure used primarily for and necessary to operations.
Computer systems, computer software, network equipment, peripheral devices, repair parts, repair or installation services, and warranty or service contracts used in operating a qualified data center are treated as exempt industrial machinery.
A data center that previously met the capital-investment and job requirements remains a qualified data center when transferred to an affiliate as part of a corporate reorganization under Internal Revenue Code § 368(a).
A qualified data center may claim job tax credits if its business plan certifies that, during the previous 12 months, it was not found to have violated the WARN Act, the Fair Labor Standards Act, or federal immigration laws. Failure to provide the certification disqualifies the data center from those job tax credits.
Sources
current law · StatewideCreates enacted tax incentives for qualified data centers that invest more than $250 million during an investment period of no more than three years and create at least 25 net new full-time jobs paying at least 150% of Tennessee’s average occupational wage.Tennessee SB 2223 (2007) / HB 2281 (2007) — Qualified Data Center Tax Incentives
What this means
The measure offers meaningful tax benefits to qualifying data centers, including a sales-tax exemption for industrial machinery and a reduced 1.5% tax on electricity. Those benefits require an investment over $250 million and at least 25 new, well-paid jobs, so they support major projects but are not available to every data center (investment and job requirements, reduced electricity tax).
People behind it
- Kyle
Senate Bill 2223 sponsor
- Marrero
Senate Bill 2223 co-sponsor
- Odom
House Bill 2281 sponsor; House companion measure proposer
Show 1 more peopleShow fewer people
- Tennessee General Assembly
Legislative body that enacted the measure
Restrictions & requirementsHide restrictions & requirements3
Electricity sold to or used by a qualified data center is subject to a 1.5% special user privilege tax, creating an ongoing operating cost. A qualified data center must meet the statutory qualification requirements, including more than $250 million in capital investment and at least 25 qualifying jobs.
To qualify as a qualified data center for the data-center tax treatment, a facility must make a required capital investment exceeding $250 million within an investment period of no more than three years and create at least 25 net new full-time jobs paying at least 150% of Tennessee’s average occupational wage. The jobs must be permanent positions lasting at least 12 consecutive months and requiring at least 37.5 hours per week with minimum health-care coverage.
A person seeking the data-center exemption for qualifying purchases must apply to the Commissioner of Revenue and receive a certificate of qualification for each location. The certificate, or an approved exemption certificate containing its authorization number, must be provided to vendors and suppliers, and the Commissioner may revoke it if the eligibility conditions are no longer met.
Benefits & exceptionsHide benefits & exceptions4
Qualified data centers receive industrial-machinery treatment for computers, computer networks, software, computer systems, peripheral devices, repair parts, and necessary installation labor used in operating the facility, making this equipment eligible for the applicable industrial-machinery tax exemption. A qualified data center must invest more than $250 million within a three-year investment period and create at least 25 permanent full-time jobs paying at least 150% of Tennessee's average occupational wage. industrial machinery used in the operation of a qualified data center
Electricity sold to or used by a qualified data center is subject to a 1.5% tax rather than the ordinary applicable sales-tax treatment. The data center must satisfy the qualified-data-center investment and employment requirements, and the facility must obtain the required exemption or qualification certificate for applicable purchases. a tax of one and one-half percent (1.5%) on the purchase price of electricity sold to or used by a qualified data center
A qualified data center may claim an exemption for electricity, gas, fuel, and other qualifying energy substances under the manufacturing and data-center utility provisions when the required qualification certificate is obtained and provided to vendors. The exemption is subject to the statutory qualification and certification requirements, and the separate 1.5% qualified-data-center electricity tax applies under the special user privilege tax provisions. apply for and receive a certificate of qualification for the exemption
Computer software fabricated by a data center or other person for its own use and consumption is exempt from Tennessee use tax. exempt from the use tax
Sources
failed · StatewideWould establish a permitting and oversight system for privately owned data centers exceeding 20 megawatts, with operation prohibited without a board-issued permit beginning January 1, 2027.Tennessee HB 2392 (2026)
What this means
For data centers over 20 MW, the bill would require an operating permit, detailed water and wastewater reviews, public hearings, and ongoing reporting. These steps could add real cost and delay, though they are water-focused safeguards rather than a ban. The permit and review requirements would apply starting January 1, 2027, if enacted.
People behind it
- Taylor
Sponsor of Senate Bill 2653
- Reneau
Sponsor of House Bill 2392
- Crowe
Co-prime sponsor of the measure
Show 3 more peopleShow fewer people
- Water and Wastewater Operator Board of Certification
Administers the data-center permit program, reviews applications, oversees compliance, conducts hearings and evaluations, receives reports, and promulgates rules
- Commissioner of Environment and Conservation
May seek injunctive relief on behalf of the Board to enforce the measure
- Department of Environment and Conservation
Publishes and maintains the required public reports on data-center water use
Restrictions & requirementsHide restrictions & requirements14
Beginning January 1, 2027, a person may not operate a data center with a power capacity greater than 20 megawatts without first obtaining a permit from the Water and Wastewater Operator Board of Certification.
Permit applicants must submit extensive information, including the facility location, responsible operators, power capacity, water providers and sources, projected daily, peak, and annual water use, effects on residential and public water supplies, drought and contingency plans, cumulative water-system impacts, conservation and reuse measures, and proof that the facility will not adversely affect residential or public water use. These requirements apply even when water is supplied through a municipal or private utility.
Applicants must notify the board within 30 days of changes to submitted information before permit approval, and owners or operators must continue reporting such changes within 30 days while the permit remains valid.
The board must evaluate a proposed data center's wastewater, blowdown, and other discharges, including their chemical and thermal impacts, compatibility with municipal treatment systems, and effects on downstream water consumers.
The board may deny a permit or impose conditions when discharges are reasonably likely to degrade water quality, interfere with treatment processes, or impose additional treatment or infrastructure burdens without mitigation.
When deciding whether to approve a permit, the board must presume that residential and public access to water takes precedence over industrial and speculative water uses.
The board must hold public hearings and receive testimony from affected members of the public and local governments before approving an application.
For data centers proposing to use Tennessee Valley Authority-managed waters, the board must coordinate with TVA and other relevant agencies to evaluate water availability, residential access, cumulative impacts, and discharge quality.
The board must conduct biennial evaluations of closed-loop or recirculating water systems, including cooling-water reuse, and must require those systems when technologically and economically feasible. Feasibility is presumed unless the applicant demonstrates infeasibility.
Data centers may not shift water-treatment, infrastructure-expansion, or remediation costs onto public utilities or Tennessee ratepayers.
Water utilities serving an operating data center must report the amount of water supplied during each billing period within 30 days after the billing cycle ends, and the Department of Environment and Conservation must publish monthly reports identifying each data center's most recently reported water use.
Owners or operators must notify the board within 30 days after a data center ceases operations; the permit remains valid until the board's executive director receives that notice.
Violations may result in an administrative civil penalty of up to $1,000 per day, capped at $25,000 total, including operating without a permit or failing to timely update required information. The commissioner may also seek injunctive relief to stop continuing violations.
The board must promulgate rules implementing the data-center permitting and oversight requirements under the Uniform Administrative Procedures Act.
Benefits & exceptionsHide benefits & exceptions3
A permit to operate remains valid until the board's executive director receives notice that the data center has ceased operations; the measure does not specify a routine expiration date. A permit issued under § 68-221-1403 is valid until notice of cessation
A party involved in a board hearing concerning permit revocation or a board order or civil-penalty assessment may appeal the board's final order to the Davidson County Chancery Court. A party to a hearing ... may appeal the final order
Civil penalties for violations are capped at $1,000 per day and $25,000 total, limiting the maximum administrative penalty exposure for a data center. not more than one thousand dollars ($1,000) per day up to a maximum of twenty-five thousand dollars ($25,000) in total
Sources
failed · StatewideWould amend Tennessee Code Annotated § 67-6-206(d) to allow qualified data centers applying for job tax credits to submit the required certification electronically when appropriate under the proposed measure.Tennessee SB 2584 (2026)
What this means
The measure would let qualified data centers submit a required certification electronically, making the job-tax-credit application slightly easier. It does not remove the certification requirement or provide a new incentive, so the practical benefit is small (certify electronically).
People behind it
- McCalmon
House sponsor of HB 2047
- Jackson
Senate sponsor of SB 2584
Benefits & exceptionsHide benefits & exceptions1
Allows a qualified data center applying for job tax credits to submit the required certification electronically, as appropriate, rather than only through a non-electronic method.
Sources
failed · StatewideWould require local governments to impose additional review requirements on new high-energy-use facilities (HEUFs)—including data centers requiring at least 100 megawatts of electric power—before approving rezoning requests, special exceptions, or special-use permits.Tennessee SB 962 (2026)
What this means
If enacted, the measure would require qualifying new data centers (100 MW or more) to provide sound assessments and their utilities to report on needed power infrastructure before certain local approvals, adding some cost and possible delay (site assessment requirements). It does not ban data centers, and smaller expansions of already approved facilities are exempt, so the added burden is meaningful but limited (expansion exception).
People behind it
- Brooks
House sponsor of HB 946.
- Lamar
Senate sponsor of SB 962.
Restrictions & requirementsHide restrictions & requirements6
New data center projects requiring 100 megawatts or more of retail electric power are classified as high energy use facilities and face the measure’s additional requirements.
Before approving a rezoning request, special exception, or special use permit for a new high energy use facility, the locality must require the applicant to submit a site assessment analyzing the facility’s sound profile in residential areas and schools within 500 feet of the property.
A locality may require the applicant’s site assessment to examine impacts on water, agricultural resources, parks, registered historic sites, and forestland on the facility site or immediately contiguous land.
A locality may request that required permitting procedures and site assessments be conducted with guidance and oversight from the Tennessee Department of Environment and Conservation.
Before approving the rezoning, special exception, or special use permit for a new high energy use facility, the locality must require the serving electric utility to submit an assessment describing required new generating units, new or existing substations that will serve the facility, and the anticipated transmission voltage.
The locality must use the submitted assessments to evaluate consistency with its comprehensive plan and compliance with noise, zoning, and other applicable laws and regulations, which can affect approval of the project.
Benefits & exceptionsHide benefits & exceptions1
Existing or already approved data center facilities may expand or be modified without the measure’s required site assessments when the expansion does not exceed an additional 100 megawatts of electrical power.
Sources
failed · StatewideEnacts broad Tennessee tax amendments through Public Chapter 602, including changes to business tax credits, sales and use taxes, franchise and excise taxes, tire fees, tax administration, and exemptions.Tennessee HB 2281 (2007)
What this means
The measure offers meaningful tax benefits: qualifying data centers receive an exemption for certain computer equipment and a reduced electricity tax (qualified data center provisions). But eligibility requires more than $250 million in investment and at least 25 new full-time jobs paying above a wage threshold (investment and job requirements). It does not add general restrictions on building or operating data centers.
Timing
- Ends
- 2008-01-01 and 2009-07-01
The measure delays implementation of some streamlined sales tax provisions until 2008-01-01 and other provisions, including multijurisdictional sourcing and the single-article local tax changes, until 2009-07-01. These provisions then take effect; all other provisions remain in effect according to their stated effective dates.
People behind it
- Odom
House sponsor of HB 2281
- Kyle
Senate sponsor of SB 2223 and proposer of Senate Amendment 4
- Marrero B
Co-prime sponsor of SB 2223
Show 5 more peopleShow fewer people
- Fitzhugh
Sponsor of House Amendment 1 to HB 2281
- McNally
Proposer of Senate Amendment 5 to SB 2223
- Tennessee General Assembly
Legislative body that enacted the measure
- Commissioner of Revenue
Administering official assigned authority to administer and enforce multiple tax provisions
- Commissioner of Economic and Community Development
Administering official assigned authority over investment extensions, cultural-attraction determinations, and economic-distress designations
Restrictions & requirementsHide restrictions & requirements3
To qualify as a “qualified data center” for the measure’s tax treatment, a facility must make more than $250 million in capital investment within an investment period of no more than three years and create at least 25 permanent full-time jobs paying at least 150% of Tennessee’s average occupational wage. Full-time jobs must last at least 12 consecutive months, require at least 37.5 hours per week, and include minimum health-care coverage. qualified data center requirements
Electricity sold to or used by a qualified data center is subject to a 1.5% tax, creating an operating cost. electricity tax for qualified data centers
A person seeking the data-center-related manufacturing exemption must apply for and receive a certificate of qualification for each qualifying location and provide the certificate, or an approved Streamlined Sales Tax exemption certificate, to vendors and suppliers. certificate requirement
Benefits & exceptionsHide benefits & exceptions3
Qualified data centers may receive the existing industrial-machinery tax treatment for computers, computer networks, software, computer systems, peripheral equipment, repair parts, and related installation labor used in operating the facility. To qualify, the data center must invest more than $250 million during an investment period of no more than three years and create at least 25 permanent full-time jobs paying at least 150% of Tennessee’s average occupational wage. The measure’s qualified-data-center industrial-machinery provision sets these qualification requirements
Electricity sold to or used by a qualified data center is taxed at a reduced rate of 1.5%, rather than the standard rate applicable to electricity. The same qualified-data-center investment and job requirements apply. The measure imposes the 1.5% electricity rate
A data-center project meeting the applicable capital-investment requirements can receive an enhanced franchise-and-excise tax credit for qualifying industrial machinery purchased in Tennessee: 5% for investments exceeding $250 million, 7% for investments exceeding $500 million, or 10% for investments exceeding $1 billion. The credit remains subject to the other statutory credit rules. The measure establishes the investment-based machinery credit rates
Sources
failed · StatewideWould create a Tennessee data-center registration and reporting program for privately operated facilities with power capacity exceeding 20 megawatts, prohibiting operation from January 1, 2027, unless registered with the Department of Revenue.Tennessee SB2112 (2026)
What this means
The measure would require data centers over 20 MW to register and disclose information, and utilities to report their fuel, electricity, and water use (registration and reporting requirements). These are extra administrative and disclosure burdens, but they do not prevent construction or impose major operating limits, so the overall effect is minor.
People behind it
- Senator Campbell
Sponsor of Senate Bill 2112
- Representative Pearson
Sponsor of House Bill 2456, the companion measure to SB 2112
- Department of Revenue
Administers the data-center registration, reporting, publication, penalty, and rulemaking provisions
Show 1 more peopleShow fewer people
- Commissioner of Revenue
Receives registrations and reports and may seek injunctive relief under the measure
Restrictions & requirementsHide restrictions & requirements6
Beginning January 1, 2027, a person may not operate a data center in Tennessee unless it is registered with the Department of Revenue. The requirement applies to privately owned and operated facilities with power capacity exceeding 20 megawatts.
Registration requires submitting the facility’s physical address, responsible operator’s contact information, approximate power capacity, electric and water utilities serving the facility, backup-fuel suppliers, and any additional information required by department rule.
An owner or operator must notify the commissioner within 30 days after any information in the registration changes.
An owner or operator must notify the commissioner within 30 days after the data center ceases operations.
The department may impose a civil penalty of up to $1,000 per day, capped at $25,000, if the owner or operator, without good cause, fails to timely register or update, correct, or modify the registration.
The commissioner may seek injunctive relief in Davidson County Chancery Court to stop an owner or operator from continuing to violate the registration requirements.
Sources
failed · StatewideWould permit qualified data centers seeking job tax credits to submit the required certification electronically when appropriate, confirming that during the preceding 12 months they were not found in violation of the federal WARN Act, Fair Labor Standards Act, or immigration laws.Tennessee HB2047 (2026)
What this means
The bill would let qualified data centers submit an existing certification electronically, making the tax-credit process slightly easier. It does not add a new tax incentive or change the certification requirements (electronic submission).
People behind it
- McCalmon
Sponsor of House Bill 2047
- Jackson
Sponsor of Senate Bill 2584
Restrictions & requirementsHide restrictions & requirements1
A qualified data center applying for job tax credits must certify that, during the previous 12 months, it has not been found in violation of the WARN Act, the Fair Labor Standards Act of 1938, or federal immigration laws; the certification may be submitted electronically.
Benefits & exceptionsHide benefits & exceptions1
Allows a qualified data center’s required certification to be submitted electronically, simplifying the process for applying for job tax credits. The electronic submission is permitted when appropriate.
Sources
failed · StatewideWould require privately owned or operated data centers with power capacity exceeding 20 megawatts to obtain a permit beginning January 1, 2027, under the proposed Tennessee Data Center Impact Review Act.Tennessee SB 2653 (2026)
What this means
The proposal would require data centers over 20 MW to obtain a water-impact permit before operating, with detailed water-use disclosures and review of wastewater and effects on local supplies (permit and review requirements). The potential for added conditions or denial creates a significant development and operating hurdle, though the bill is limited to larger centers and does not ban them.
People behind it
- Reneau
Sponsor of House Bill 2392 proposing the Tennessee Data Center Impact Review Act
- Taylor
Sponsor of Senate Bill 2653 proposing the Tennessee Data Center Impact Review Act
- Crowe
Co-prime sponsor of Senate Bill 2653
Show 3 more peopleShow fewer people
- Water and Wastewater Operator Board of Certification
Administers the measure by reviewing and issuing data center permits, conducting oversight, receiving reports and complaints, enforcing violations, and promulgating rules
- Commissioner of Environment and Conservation
May seek injunctive relief on behalf of the board to prevent continuing violations
- Department of Environment and Conservation
Publishes required public notices and monthly data center water-use reports
Restrictions & requirementsHide restrictions & requirements11
Beginning January 1, 2027, a person may not operate a data center in Tennessee without first obtaining a permit from the Water and Wastewater Operator Board of Certification. The requirement applies to facilities with more than 20 megawatts of power capacity. Beginning January 1, 2027, a person shall not operate a data center
Permit applicants must submit extensive information, including the facility's location, power capacity, water providers and sources, projected water use, effects on residential and public supplies, drought and contingency plans, cumulative water-system impacts, conservation measures, and proof that the facility will not adversely affect residential or public water use. an applicant shall submit the following
The permit-application requirements apply even when a data center obtains water through a municipal or private water utility, rather than directly from a natural water source. including, but not limited to, data centers that source their water through municipal or private utilities
Applicants must report changes to submitted information within 30 days before permit approval, and owners or operators must report changes within 30 days throughout the permit's validity. within thirty (30) days of the change
The board must evaluate wastewater, blowdown, and other discharges, including their chemical and thermal effects, compatibility with municipal treatment systems, and effects on downstream water consumers. It may deny a permit or impose conditions when discharges are reasonably likely to degrade water quality, interfere with treatment, or impose unmitigated treatment or infrastructure burdens. The board may deny an application
When deciding whether to approve a permit, the board must presume that residential and public water access takes precedence over industrial and speculative water uses. residential water access and the public need for water access take precedence
The board must hold public hearings and provide notice on the department website and in newspapers in the county where the proposed data center would be located. Hold public hearings to receive testimony
The board must conduct biennial evaluations of closed-loop or recirculating water systems and require those systems when technologically and economically feasible. Feasibility is presumed unless the applicant demonstrates that the systems are infeasible. require the implantation of the systems
Data centers may not shift water-treatment, infrastructure-expansion, or remediation costs to public utilities or Tennessee ratepayers, potentially requiring the facility to bear those costs itself. shall not externalize water treatment, infrastructure expansion, or remediation costs
Water utilities serving a data center must report the facility's water use to the board within 30 days after each billing cycle, and the department must publish monthly reports identifying each data center's most recently reported water use. The reports must be provided to the board within thirty (30) days
Violations may result in an administrative civil penalty of up to $1,000 per day, capped at $25,000 total, including operating without a permit or failing to update required information. The commissioner may also seek an injunction against continuing violations. not more than one thousand dollars ($1,000) per day
Benefits & exceptionsHide benefits & exceptions2
Facilities with a power capacity of 20 megawatts or less are outside the measure’s definition of a data center and therefore are not subject to its new data-center permit requirement.
Once issued, a permit remains valid until the board’s executive director receives notice that the data center has ceased operations; the measure does not impose a periodic permit-renewal requirement.