Slightly Pro-Data Center Policies

Tennessee rules can limit how much utilities and municipalities absorb data-center-specific infrastructure costs, while allowing certain cost allocations and independent power. Qualifying large projects that meet investment and job requirements can receive equipment tax breaks and a reduced electricity tax.

Rating and summary from Tennessee statewide as there are no scored current or future laws outside temporary restrictions for Lawrence County.

Specific to Lawrence County only.

pending · County measure
Proposes a temporary moratorium within Lawrence County on the establishment, construction, development, expansion, or operation of data centers, cryptocurrency-mining facilities, and certain high-density computing operations.Tennessee Lawrence County Resolution No. 20260728-03 (2026)

What this means

If enacted, this measure would temporarily stop the establishment, construction, development, expansion, and operation of data centers in Lawrence County, creating a major barrier to projects. The provided source does not state how long the moratorium would last or describe exceptions. It proposes a temporary moratorium.

Timing

The agenda includes a resolution declaring a temporary moratorium on data centers, cryptocurrency mining facilities, and certain high-density computing operations, but the provided sources do not state its expiration date or ending condition.

People behind it

  • Listed as sponsors of the honorariums honoring Lawrence County student and youth teams, and of the resolution establishing the dead stock removal relief fund.

  • Listed as a sponsor or co-sponsor of multiple honorariums and the dead stock removal relief fund resolution; explicitly identified as the sponsor of the Boone Gobble and Lawrenceburg Public School Junior Beta Club honorariums.

  • Sponsor of the resolutions approving the May 26, 2026 regular-session minutes and June 30, 2026 special-session minutes.

Show 6 more peopleShow fewer people
  • Co-sponsor of the resolution declaring a temporary moratorium on certain data centers, cryptocurrency mining facilities, and high-density computing operations.

  • Co-sponsor of the resolution declaring a temporary moratorium on certain data centers, cryptocurrency mining facilities, and high-density computing operations.

  • Sponsor of resolutions concerning the certified tax rate, nonprofit and charitable contributions, hotel-motel tax distribution, opioid settlement funds, the fiscal-year tax levy, county appropriations, a Veterans Service Office position, and a fiscal-year budget amendment.

  • Sponsor of the resolution authorizing an agreement for construction of a communications tower at the Jason Dickey Fire Training Center.

  • Sponsor of resolutions accepting roads into the county road system and naming the Crawfish Creek Bridge the Joe Newton Memorial Bridge.

  • Sponsor of the resolution approving the Lawrence County EMS 24/72 work schedule policy.

Restrictions & requirementsHide restrictions & requirements1
  • Declares a temporary moratorium on establishing, constructing, developing, expanding, or operating data centers, cryptocurrency-mining facilities, and certain high-density computing operations within Lawrence County. temporary moratorium on the establishment, construction, development, expansion, or operation

Sources

pending · County measure
Would temporarily pause data centers and certain high-density computing operations in Lawrence County, but the proposed moratorium was tabled and is not in effect.Lawrence County, Tennessee Resolution 20260728-03 (2026)

What this means

If enacted, the measure would temporarily block establishing, building, expanding, and operating data centers in Lawrence County, a broad restriction likely to make projects much harder. The source does not state how long the pause would last; it says only that the proposed moratorium was tabled for later consideration.

Timing

The proposed moratorium was tabled for later consideration. No expiration date or ending condition is stated.

People behind it

  • Listed in connection with the proposed temporary moratorium on data centers and certain high-density computing operations, which was tabled for later consideration.

Restrictions & requirementsHide restrictions & requirements1
  • A proposed temporary moratorium would restrict establishing, constructing, developing, expanding, or operating data centers in Lawrence County. It also covers cryptocurrency mining facilities and certain high-density computing operations. The proposal was tabled for later consideration, not adopted, and the document gives no duration. The proposed temporary moratorium