City of Knoxville
This restriction takes precedence while in effect. The rating below excludes temporary restrictions.
Slightly Pro-Data Center Policies
Knoxville enacted a one-year pause on permits, construction, and development for data centers needing at least 10 megawatts; the description calls it proposed, and it does not expressly bar existing centers from operating.
Rating from Tennessee statewide as there are no scored current or future laws outside temporary restrictions for City of Knoxville.
current law · City of KnoxvilleProhibits permitting, construction, or development of data centers requiring 10 megawatts or more of power in Knoxville for one year.City of Knoxville Data-Center Moratorium (2026)
What this means
The proposed one-year moratorium would temporarily stop permitting, construction, and development of data centers needing 10 megawatts or more in Knoxville, making new projects and expansions substantially harder. It does not expressly prohibit existing data centers from operating.
Timing
- Ends
- one year after adoption
The measure establishes a one-year moratorium on permitting, construction, or development of large data centers requiring 10 megawatts or more of power.
People behind it
- Administration
Requested the emergency ordinance.
- Charles Thomas
Moved to approve the ordinance.
- Denzel Grant
Seconded the motion to approve the ordinance.
Restrictions & requirementsHide restrictions & requirements1
Imposes a one-year moratorium on permitting, construction, or development of large data centers in Knoxville that require 10 megawatts or more of power.