Borough of Yardley

For Borough of Yardley, see Bucks County’s laws and regulations below. No additional city or town-specific measures are listed in our research.

Anti-Data Center Policies

Bucks County’s Newtown-area ordinance allows data centers through an approval process but limits where and how they can operate, with setbacks, minimum site sizes, and noise controls.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · County measure
Wrightstown enacted it as local Ordinance 359 on August 17, 2026; the shared measure took effect after Upper Makefield completed the jointure approvals on August 18, 2026.Newtown Area Joint Municipal Zoning Ordinance 2026-03 — data-center G-17 use

What this means

The measure imposes setbacks from homes or other protected places, minimum site-size requirements and noise limits and sound testing. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.

Restrictions & requirementsHide restrictions & requirements20
  • Conditional use; no approval expiration, § 803.G-17

  • Section 803.G-17.3.c bars any data center building, structure, or Data Center Equipment, including generators, cooling systems, substations, and rooftop or ground-mounted equipment, within 1,000 ft of any residential lot or district, measured from the closest point of the building or equipment (JMZO Ordinance 2026-03 text).

  • Single limits of 50 dBA next to homes and 62 dBA otherwise, § 803.G-17.8.a and b

  • Baseline study but no background cap

  • Pre-construction study; post-construction study only if conditioned, § 803.G-17.8.c and d

  • Water resources impact study under Wrightstown § 26-251, § 803.G-17.4.d

  • Cooling method not addressed

  • On-lot sewage disposal must be demonstrated, § 803.G-17.4.a

  • Decommissioning plan covers removal and disposal of batteries, refrigerants, and e-waste, § 803.G-17.12.c and d

  • Will-serve letter or engineer's capacity assessment with application; no inspection, § 803.G-17.4.b

  • Assessment of potential electrical consumption required, § 803.G-17.4.b

  • Lines from substations buried where practical; substations not screened, § 803.G-17.5

  • Section 803.G-17.4 requires, with the conditional use application, a will-serve letter or professional assessment of electrical capacity and, where it identifies insufficient capacity, the system improvements the applicant must provide at its own expense.

  • Buffer yards per § 1003 with six-foot berms, § 803.G-17.11

  • Safety plan approved by Fire Marshal, recertified annually, § 803.G-17.6

  • Annual Fire Marshal site inspection, § 803.G-17.6.a

  • Security based on estimate, abandonment notice, removal within 12 months of plan approval, § 803.G-17.12

  • One post-construction noise study may be required, § 803.G-17.8.d

  • Zoning Officer enforcement and draw on security, § 803.G-17.8.e and 12.f

  • Developer, operator, and end user not required

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Conditional use in the QA-A district