Wysox Township

Neutral Data Center Policies

Wysox Township’s enacted overlay allows data centers on listed lots by right after Master Plan approval, but studies, a $50,000 escrow, removal security, noise rules and setbacks add costs and requirements.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Wysox Township
Creates a data center overlay district in parts of Wysox Township and sets rules for where data centers can be built, how projects are reviewed, and what safeguards they must meet.Ordinance 2026-001 — Data Center Overlay District

What this means

The overlay creates a path for data centers and, after Master Plan approval, says development of listed lots is permitted by right. But studies, a $50,000 escrow, and financial security for decommissioning add real costs and hurdles, so the overall effect is a modest encouragement rather than a major benefit or barrier. Escrow requirement

People behind it

  • Enacted and adopted Ordinance No. 2026-001 on April 14, 2026 (“DULY ENACTED AND ORDAINED”).

Restrictions & requirementsHide restrictions & requirements19
  • Data centers may be developed under this overlay only on the mapped portions of the M Manufacturing and CG Commercial districts; Conservation District land is excluded. overlays portions of both

  • Electrical generation must meet EPA emissions standards; non-modular nuclear generation facilities are excluded. meeting Environmental Protection Agency emissions standards

  • Data centers and related uses must be set back at least 200 feet from residential lot lines at the front, rear, and each side. two-hundred (200) feet

  • Lot coverage is capped at 90%, with adequate land required for current and future stormwater improvements. Buildings may be up to 90 feet in the M district or 40 feet in the CG district, except stacks, towers, and other unoccupied facilities. not more than ninety percent (90%)

  • Unattached buildings on the same lot must generally be at least 30 feet apart. Internal unit or lot-line setbacks in a non-residential planned community or condominium are 30 feet or the applicable building-code distance, whichever is greater; attached buildings may have zero-foot internal setbacks. thirty (30) feet

  • A Master Plan is required for a data center or campus and must include feasibility studies, a conceptual layout, impact analysis, proposed management documents, anticipated fiscal benefits and costs, and a development schedule. It is subject to the Bradford County subdivision and land development rules. A Master Plan shall be submitted

  • Master Plan approval depends on the Board of Supervisors evaluating the adequacy of proposed measures to mitigate short- and long-term community and fiscal impacts. The Board may accept impact fees for water, sewer, firefighting capacity, and other impacts it considers appropriate. Approval of the Master Plan application will be contingent

  • Before a building permit, the applicant must submit a site plan for each data center or campus phase, show consistency with the approved Master Plan, and provide copies of applicable third-party permits, such as highway occupancy or NPDES permits. prior to issuance of a building permit

  • After Master Plan approval, major modifications are subject to county subdivision and land development procedures. A modification is major if it produces greater stormwater discharge or runoff than the rate approved in the Master Plan’s Stormwater Management Plan; the major-modification procedure is the same as for a new Master Plan. greater than the rates identified

  • To retain the ordinance’s stated protection for phased development from later zoning or subdivision changes and further approvals, development must commence within five years after Master Plan approval. commences within five (5) years

  • Noise may not exceed 70 dBA on receiving properties outside the overlay district. There is no limit along lot lines shared with other data centers or campuses; lawful utility operation, required periodic generator testing, and emergency generator use during utility outages are exempt. A qualified professional’s sound and vibration analysis is required for properties within 300 feet of project-area property lines. 70 dBA as measured on receiving properties

  • Parking must follow the zoning ordinance, be provided only for portions of the data center actually used as office space, and be supported by a staffing plan in the Master Plan. Campus parking generally cannot be within 50 feet of a property line abutting a residential-use district, except for security purposes; a signal is required at parking-area access if warranted. Each data center must provide one loading or unloading space at least 12 by 50 feet. Parking availability permitted only

  • Applications must include natural screening plans to buffer facility views from neighboring residences and soften noise impacts as much as practicable. screening plans that serve to buffer the views

  • Data centers must meet facade-design rules: a differentiated main entrance and, on primary facades facing a Township road or State highway at a 60–90 degree angle, a facade-surface change about every 150 feet or windows, doors, or similar features on at least 30% of the facade. These rules do not apply to accessory uses. minimum of thirty percent (30%)

  • Applicants must file a Local Emergency Response Plan with specified emergency organizations and coordinate fire protection with the local fire department, meet its reasonable training, equipment, and information requests, and prepare a master firefighting plan addressing on-site generation and battery storage. Knox Boxes, a detailed security plan, emergency-access signage, and continuous maintenance of required on-site emergency equipment are also required. A Local Emergency Response Plan (LERP)

  • The Master Plan application must include a water and sewer feasibility analysis. Projects must use municipal water and sewer systems or on-site water treatment facilities and provide adequate wastewater drainage; if municipal-system improvements are necessary, the applicant must finance and construct them to Municipal Authority specifications. Applicants must also document sufficient electricity capacity without negative community-wide energy or security impacts. water and sewer feasibility analysis

  • Applications must include a decommissioning plan for otherwise unusable energy or other infrastructure and financial security satisfactory to the Township, where applicable, equal to 125% of applicable removal costs. The guarantee must provide for updates every five years under a developer’s agreement and use financial instruments approved by the Board. 125% of applicable costs

  • Applicants must reimburse expert-review expenses, pay normal application fees, and maintain a Township escrow of at least $50,000 for review and inspection fees. The Township may adjust the amount based on project complexity; failure to keep the escrow fully funded can result in application denial or revocation. no less than $50,000

  • A data center proposed outside a Master Plan must submit a Land Development Plan under the county subdivision and land development rules and comply with the ordinance’s supplemental data center campus regulations. other than as part of a Master Plan

Benefits & exceptionsHide benefits & exceptions10
  • Data centers and data center campuses are expressly permitted in the overlay, along with accessory offices, utilities and utility facilities, and EPA-compliant electrical generation (excluding non-modular nuclear facilities). Permitted uses

  • Once a Master Plan is approved, development of each lot, parcel or building identified in it is permitted by right. Permitted by right

  • A campus may be built in phases without further approvals, and is protected from later municipal zoning or subdivision ordinance changes, if development begins within five years of Master Plan approval and remains consistent with the approved plan. Phased development

  • The Master Plan may set ranges or limits and show conceptual layouts without fixing the exact location, orientation or size of buildings, drives, access points or facilities, allowing flexibility as individual lots or units are developed. Major changes remain subject to the ordinance’s major-modification process. Flexibility in design

  • The Board may waive or modify requirements for a Master Plan or individual data-center land development plan if a provision is unreasonable, causes undue hardship, or an alternative standard provides equal or better outcomes. Waivers or modifications

  • The ordinance sets no minimum lot area or width; permits up to 90% lot coverage if adequate land remains for stormwater management; and allows coverage to be calculated across commonly owned lots under a Master Plan or planned-community/condominium ownership. Lot coverage and aggregation

  • Multiple principal buildings may be built on one lot, subject to the ordinance’s standards and a 30-foot separation unless a lesser distance is allowed by building code or the buildings are attached. The tract may also be divided into a non-residential planned community or condominium for separate ownership or lease, with specified reduced internal setbacks. Multiple buildings and separate ownership

  • Parking is determined under the existing zoning requirements, but for data centers parking may be provided only for portions actually used as offices, with a staffing plan used to establish needed spaces. Data-center parking requirements

  • The 70 dBA sound limit does not apply along lot lines shared with other data centers or campuses, and sound from utility generation and transmission, required periodic generator testing, and emergency generator use is exempt. Sound exemptions

  • Projects may use municipal water and sewer systems or on-site water treatment; if municipal-system additions or improvements are necessary, the applicant must finance and construct them to Municipal Authority specifications. Water and sewer services

Sources

current law · Wysox Township
The current rules are in Ordinance 2026-001, which the Supervisors enacted on April 14, 2026.Wysox Township, Bradford County — data-center ordinance (No. 2026-001)

What this means

The measure imposes money set aside for eventual removal, noise limits and sound testing and setbacks from homes or other protected places. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.

Restrictions & requirementsHide restrictions & requirements24
  • Section 408.A adds the DCO Data Center Overlay District and maps it in the amended Zoning Map within the ordinance, and Section 408.C lists data centers as permitted uses in the overlay, but the ordinance does not expressly state that data centers are excluded from all other districts.

  • Master plan approval by the Supervisors, then development by right; no conditional use, § 408.F

  • Data center campus defined and developed under one master plan, § 408.B and .F

  • Phasing under the master plan; only major modifications need new approval, § 408.F.5 and .6

  • Single 70 dBA limit outside the overlay, § 408.F.9

  • Sound and vibration analysis with the master plan only, § 408.F.9

  • Generator testing exempt from sound limits, § 408.F.9

  • Vibration analysis required; no vibration standard, § 408.F.9

  • Water and sewer feasibility analysis, § 408.F.14

  • General wastewater provisions; no cooling discharge plan, § 408.F.14

  • Stormwater management plan tied to the master plan, § 408.F.6

  • Power generation must meet EPA emission standards; no testing or reports, § 408.C.4

  • Electricity supplier capacity commitments; no electrical inspection, § 408.F.14.

  • On-site power generation addressed as a permitted use, § 408.C.4

  • Firefighting plan must address battery storage; no NFPA 855, § 408.F.13

  • Applicant pays only for water and sewer system improvements

  • Natural screening next to residences; no width stated, § 408.F.11

  • Lighting covered only in a security plan

  • Section 408.F.12 requires a differentiated main entrance feature and, on primary facades facing a Township road or State highway, either a change in building material, pattern, texture, color, or accent material every 150 horizontal feet or at least 30 percent fenestration or faux windows.

  • Local emergency response plan filed with responders; no annual update or radio rule, § 408.F.13

  • Applicant must meet fire department requests for training and equipment, § 408.F.13.

  • Plan and 125% security for unusable energy infrastructure only; no removal deadline, § 408.F.15

  • Monitoring regimen recommended only

  • Section 408.F.17 requires every applicant to reimburse the Township for all expert review expenses and to fund an escrow of at least $50,000, replenished regularly, and Section 408.G requires a land development plan under the County SALDO.

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data