Wright Township

Anti-Data Center Policies

Wright Township allows data centers only with conditional approval in the I-1 district, subject to size, setback, noise, planning, and infrastructure requirements that make projects harder and costlier, but do not ban them.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Wright Township
Restricts data centers to Wright Township’s industrial district, requires township approval, and sets limits on size, location, utilities, noise, traffic, and screening.Wright Township Ordinance No. 2025-10 (data-center zoning amendment)

What this means

The proposal would allow data centers only as conditional uses in the I-1 industrial district, with limits on site size, height, floor area, and distance from homes. It also requires studies and approvals for utilities, water, wastewater, traffic, noise, and community benefits, making projects and expansions significantly harder, though not banned.

People behind it

  • The ordinance identifies the Board as its enacting body; supervisors adopted it unanimously.

Restrictions & requirementsHide restrictions & requirements21
  • Data centers, accessory uses, and disaster-recovery facilities are allowed only as conditional uses in the I-1 General Industrial District, with approval under the township’s conditional-use process. Conditional uses in the I-1 district

  • A site must contain at least 50 contiguous acres; total floor area is capped at 500,000 square feet, and buildings—including rooftop equipment—may not exceed 45 feet. Minimum tract size

  • Structures, loading docks, and truck areas must be at least 300 feet from residential zoning districts and existing occupied residences. 300-foot setback

  • An expansion exceeding 10% of the originally approved footprint or utility load requires amended conditional-use approval. Expansion threshold

  • Applicants must obtain utility-capacity letters and show infrastructure can accommodate the project without adverse effects; reviews must consider cumulative impacts from existing or proposed data-center projects. Utility capacity and cumulative impacts

  • Power plans require provider feasibility letters, underground lines, documentation of regional impacts, and a demonstration that the project will not adversely affect the local grid. Power requirements

  • A water-supply feasibility study is required, with Township Engineer and Pennsylvania DEP approval, and must show no adverse effect on local water supply or quality. Water-supply study and approvals

  • Applicants must demonstrate adequate wastewater disposal for domestic and cooling or industrial needs, including public-sewer capacity verification, with review or approval by the SEO, Township Engineer, and Pennsylvania DEP. Wastewater requirements

  • Noise limits are 67 dBA during the day and 57 dBA at night; noise and vibration may not cross property lines. Daytime and nighttime noise limits

  • Portable generators must meet Tier IV diesel standards and have a muffler or enclosure; generator noise is limited to 67 dBA at the property line. Portable-generator standards

  • Generator testing is restricted to 7 a.m.–5 p.m. May through September and 11 a.m.–5 p.m. October through April; overnight testing is prohibited. Emergency exceptions require EMA approval and must be temporary. Testing hours and emergency exception

  • Portable turbines are limited to two per parcel, must be at least 75 feet from property lines, and may operate for no more than 10 days per year without a temporary permit; they must meet noise requirements and have secure functional braking. Portable-turbine limits

  • Vibration and air-quality compliance is required; studies may be required, with peer review at the Township’s discretion, and emissions must meet state and local standards. Vibration and air-quality requirements

  • Projects must provide year-round visual opacity of 75% within three years and plant one evergreen and one deciduous tree every 20 feet of frontage. Buffer areas cannot be used for parking or storage; public-road fencing cannot be chain link or barbed wire, and rooftop equipment and refuse areas must be screened or enclosed. Buffer and screening standards

  • Primary façades must have at least 30% fenestration and articulation every 150 feet; a green wall may replace up to 50% of the required fenestration. Facade design standards

  • Applicants must submit a traffic-impact study showing impacts are within tolerances, emergency access is ensured, and local roads are not adversely affected. Traffic-impact study

  • Non-essential activities, including deliveries and maintenance, are limited to 7 a.m.–7 p.m., Monday through Saturday. Ancillary-activity hours

  • Applicants must submit a binding Community Incentive Package; its terms may be recorded in a Developer’s Agreement, and contributions should be proportional to project impacts and tied to public welfare, education, health, or infrastructure improvements. Community Incentive Package

  • A fire-safety plan meeting NFPA standards is required; battery storage must comply with NFPA 855, hydrants must have Storz fittings, and every structure must have a Knox Box. Emergency-response requirements

  • Owners must pay for required generator and turbine noise monitoring, and the Township may require continuous remote monitoring. Qualified professionals must conduct sound studies before and after occupancy using ANSI-standard meters at the property line. Monitoring and sound-study costs

  • Violations may result in daily fines, corrective orders, and potential permit revocation; the Township may recover legal fees. Fines and permit consequences

Benefits & exceptionsHide benefits & exceptions3
  • Data centers, accessory uses, and disaster recovery facilities may seek conditional-use approval in the I-1 Industrial District; approval is required, and the zoning hearing board decides the application. The ordinance lists them as conditional uses.

  • The ordinance sets project-specific dimensional rules instead of applying the general I-1 standards: a minimum 50-acre tract, a maximum 500,000 square feet of floor area, a maximum height of 45 feet, and a 300-foot separation from residential districts or occupied homes. These limits still constrain development. The article summarizes the size, height, and setback limits.

  • Expansion is allowed through an amended conditional-use approval when it exceeds 10% of the originally approved footprint or utility load; the ordinance does not require that amendment for an expansion at or below that threshold. The ordinance’s expansion threshold.

Sources

current law · Wright Township
Requires data centers and related facilities proposed in Wright Township’s I-1 district to meet detailed zoning, setback, noise, water, power, environmental, screening, traffic, and emergency-planning requirements.Wright Township Zoning Ordinance § 145-802(JJ), as amended by Ordinance No. 2026-01

What this means

The measure would make data centers substantially harder to build and expand, requiring at least 50 contiguous acres and 300-foot separation from homes, plus extensive utility, water, noise, and emergency planning. A minimum $3 million water-infrastructure bond, strict operating limits, and further approval requirements add major costs and hurdles, though the measure does not ban data centers outright.

Restrictions & requirementsHide restrictions & requirements30
  • The rules apply to proposed data centers, accessory uses, disaster recovery facilities, and substations in the I-1 District, limiting the locations covered by this provision to that district. Applicability

  • A data center tract must contain at least 50 contiguous acres; adjacent parcels under common ownership may count toward the minimum. Minimum tract size

  • Each building is limited to 500,000 square feet of floor area; multiple buildings may be permitted. Maximum floor area

  • Buildings are limited to 45 feet in height, including rooftop equipment. Maximum height

  • Structures, loading docks, and truck areas must be at least 300 feet from residential zoning districts and existing occupied residential properties. Setbacks

  • An expansion exceeding 10% of the originally approved footprint or utility load requires amended conditional-use approval. Expansion approval

  • Applicants must provide utility-capacity letters, and approval is conditioned on infrastructure being adequate without adverse impact; cumulative effects of existing and proposed data center projects must be considered. Utility capacity and impacts

  • Power plans require provider feasibility letters, documentation of regional impacts, and a demonstration of no adverse effect on local grids; new or upgraded lines must be underground where feasible, with Township approval and justification required if overhead installation is proposed. Power feasibility

  • Applicants must demonstrate adequate water supply and obtain required Township Engineer and Pennsylvania DEP review or approval. For nonpublic water sources, a feasibility study must assess effects on nearby wells and water resources; the Township may extend the study area beyond the stated minimums. Water feasibility

  • If water use could adversely affect a nearby well, the applicant must improve that well at its own expense before operations. Quarterly water-use reporting is required at the applicant’s expense, and a bond of at least $3 million is required, with a higher amount possible. Well improvements and bonding

  • Wastewater disposal must be adequate for domestic and cooling or industrial needs, with required review or approval and public-sewer capacity verification. Wastewater requirements

  • Portable generators must be Tier IV diesel and have a muffler or enclosure; testing is limited, and the subsection states a 65 dBA noise limit for both day and night. Portable generator requirements

  • Portable turbines are limited to two per parcel, must be at least 75 feet from property lines, and may operate up to 10 days per year without a temporary permit; they must meet noise requirements and have functional braking. Portable turbine limits

  • Noise at any property line may not exceed 65 dBA from 7 a.m. to 7 p.m. or 55 dBA from 7 p.m. to 7 a.m.; the 24-hour time-weighted average may not exceed 60 dBA. A Township-approved acoustical engineer, paid by the applicant, must conduct the study and measurements, including an as-built study; ongoing monitoring may be required. Noise limits and studies

  • Standby-generator testing must occur only from 7 a.m. to 7 p.m., excluding federal holidays, with no overnight testing; the applicant must submit an impact statement and testing schedule for Township review and approval. Violations may lead to daily fines or permit revocation. Generator testing

  • Applicants must submit professional studies addressing vibration, air quality, and water use; the Township may require peer review. Environmental studies

  • Fuel storage must comply with applicable emissions, hazardous-material, and environmental rules, and the Township must receive proof of required agency compliance, permits, and renewals. Emissions and permits

  • New and replacement outdoor lights must be full cut-off, directed downward and shielded; illumination at an adjacent residential property line is limited to 0.5 foot-candles. A lighting plan, including fixture specifications and a photometric plan, is required for relevant applications. Outdoor lighting standards

  • A continuous 50-foot vegetation buffer is required along lot lines, with 75% visual opacity year-round within three years; planting and maintenance requirements apply, and buffer areas cannot be used for parking or storage. Vegetation buffers

  • Solid fencing is required, and chain-link or barbed-wire fencing is barred along public roads. Rooftop equipment must be screened or hidden, refuse areas enclosed, and fences and equipment maintained. Fencing and screening

  • Facade design must include articulation at least every 150 feet and at least 30% fenestration coverage on primary facades; a green wall may substitute for up to 50% of fenestration. Facade design

  • Applicants must submit a traffic-impact study showing that impacts are within tolerances, emergency access is ensured, and local roads are not adversely affected. Traffic impact

  • Nonessential activities, including deliveries and maintenance, are limited to 7 a.m. to 7 p.m., Monday through Saturday. Ancillary activity hours

  • The applicant must submit a binding Community Incentive Package with its application; the Township may require its terms to be recorded in a Developer’s Agreement. Community Incentive Package

  • An Emergency Response Plan is required for Township review and approval. Before a certificate of occupancy, the applicant must fund specialized emergency-responder training and necessary equipment; fire-safety plans, NFPA-compliant battery storage, Storz hydrant fittings, and Knox boxes are also required. Emergency response requirements

  • Before approval, the applicant must provide written confirmation from the primary electric utility of sufficient capacity, including peak demand, redundancy, and grid or property impacts; independent engineering review may be required at the applicant’s expense, and inadequate confirmation may result in denial or suspension. Utility supply confirmation

  • Onsite generation may be used only for emergency backup, not normal operations, and must meet applicable environmental, noise, and emissions standards; routine testing is limited to daytime hours unless the Township approves otherwise. Onsite power generation

  • Electrical upgrades must minimize visual impacts and must be underground where feasible; if undergrounding is impractical, overhead lines require justification and Township approval. The applicant must demonstrate that upgrades will not adversely affect electrical-system reliability or safety, and an independent engineering review may be required at the applicant’s expense. Transmission and distribution infrastructure

  • New or expanded substations must be sited and designed to minimize effects on neighboring properties, including through screening, setbacks, and noise mitigation, and must comply with applicable safety and environmental regulations. Substation requirements

  • The Township may require periodic reporting or monitoring to verify compliance with requirements for data-center power use and backup generation. Power-use monitoring

Benefits & exceptionsHide benefits & exceptions5
  • Adjacent parcels under common ownership may be combined to meet the 50-acre minimum tract size. Adjacent parcels under common ownership may be counted.

  • A data center may use multiple buildings, provided each building stays within the 500,000-square-foot maximum. Multiple buildings may be permitted.

  • Expansions of 10% or less of the originally approved footprint or utility load do not trigger the subsection’s requirement for amended conditional-use approval. Expansion of over 10%.

  • Up to two portable turbines per parcel may operate for up to 10 days per year without a temporary permit, subject to the stated setback, noise, and safety requirements. 10 days/year without temporary permit.

  • On-site generators are allowed for emergency backup and routine testing; testing is generally limited to daytime hours and subject to Township approval and applicable standards. Emergency backup only.

Sources

current law · Wright Township
The rules are in Ordinance No. 2026-01, which the Board of Supervisors adopted on January 12, 2026, adding § 145-802JJ to the zoning chapter.Wright Township, Luzerne County — data-center ordinance (No. 2026-01)

What this means

The measure imposes noise limits and sound testing, setbacks from homes or other protected places and minimum site-size requirements. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.

Restrictions & requirementsHide restrictions & requirements21
  • Conditional use; no expiration of approval in § 145-802JJ, § 145-508C(8)

  • 65 dBA day and 55 dBA night at the property line, § 145-802JJ(6)

  • Noise study with application and as-built study after construction; none at building permit, § 145-802JJ(6)

  • Testing 7 AM to 7 PM only; not limited to weekdays, § 145-802JJ(6) and (16)

  • Vibration study, and vibration may not cross property lines, § 145-802JJ(7) and (9).

  • Hydrogeologic feasibility study; no bar on wells for cooling, § 145-802JJ(7)

  • Quarterly water use reporting; no drought plan, § 145-802JJ(7)

  • Section 145-802JJ(3)(d) requires adequate disposal of domestic and cooling or industrial wastewater with approval by the SEO, the Township Engineer, or PA DEP, but it does not state when approval must be obtained and allows approval by the Township Engineer alone.

  • Tier IV diesel for portable generators and emissions rules; no annual testing, § 145-802JJ(4) and (7)

  • Utility capacity letter with optional independent review; no electrical inspection, § 145-802JJ(3) and (16).

  • On-site generation limited to emergency backup, § 145-802JJ(16)

  • Substations screened; lines underground only where feasible, § 145-802JJ(16)

  • NFPA 855 required, § 145-802JJ(15)

  • 50-ft vegetated buffer along all property lines, § 145-802JJ(10)

  • Rooftop equipment fully screened and solid fencing; no height or acoustic screening, § 145-802JJ(10)

  • Emergency plan reviewed by township with 24-hour contacts; no annual update or radio, § 145-802JJ(15)

  • Hazards identified in emergency plan; no storage setbacks, § 145-802JJ(15)

  • Section 145-802JJ(12) requires a study showing that traffic impacts are within tolerances and that emergency access is ensured.

  • Mandatory quarterly water use reports; noise and power monitoring at township option, § 145-802JJ(6), (7), and (16)

  • Fines and corrective orders for noise and testing violations; no amounts or revocation, § 145-802JJ(6)

  • Sections 145-802JJ(6)(a)[3], (7)(a)[5], and (16)(a)[2] require a Township-approved acoustical engineer, the hydrogeologic study, and an independent review of the utility confirmation at the applicant's expense, but the text does not place this review in land development review.

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Conditional use in the I-1 Industrial District

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data