Worcester Township

Anti-Data Center Policies

Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.

Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for Worcester Township.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

pending · Worcester Township
Proposes to allow data centers only by conditional use in Worcester’s Industrial Research District, with size and power caps and requirements for setbacks, noise, cooling, monitoring, emergency response, and decommissioning.Draft Worcester Township Data Center Ordinance No. 2026-___ (proposed amendment to Chapter 150, Zoning)

What this means

The proposal would create a route to build data centers as conditional uses in the IR district, but only up to 25,000 square feet and five megawatts. It also requires a 50-acre site, substantial technical studies, and strict setbacks and operating standards, creating significant practical barriers to building and expanding facilities.

People behind it

  • Township Manager who prepared and administered the staff review materials for the data center and signage amendments; the memoranda identify him as the sender and request Planning Commission recommendations on the revisions. The Board is requesting a recommendation

  • Identified as the body seeking a recommendation on the data center ordinance revisions and as the body that would enact the proposed ordinances. The Board is requesting a recommendation

Restrictions & requirementsHide restrictions & requirements16
  • A data center would be allowed only as a conditional use in the IR Industrial Research District, requiring Board of Supervisors approval; land-development approval is also required when the project qualifies as land development. conditional use in the IR Industrial Research District

  • The site must comprise at least 50 contiguous acres under unified control, consolidated into one lot; later division that causes noncompliance is prohibited. at least 50 contiguous acres

  • The draft limits each lot to one data center and one principal building or approved Data Center Premises, with a maximum of 25,000 square feet and five megawatts of demand; data center campuses and cryptocurrency or similar digital-asset mining are prohibited. 25,000 square feet

  • Accessory energy generation would be allowed only with an approved data center on the same consolidated lot, capped at five megawatts; simultaneous output counts toward the facility-demand limit. Standalone generation, export, merchant service, grid supply, and demand response are prohibited. only as an accessory subordinate use

  • Principal buildings and listed equipment generally must be 250 feet from property lines. They must also achieve the greatest practicable separation from residences and sensitive receptors: at least 500 feet, with a 1,000-foot distance applying unless the applicant meets enhanced requirements for a shorter distance. Energy-generation facilities have a 300-foot property-line setback and may not be within 500 feet of a sensitive receptor. at least 250 feet from every property line

  • A separation distance below 1,000 feet would require sealed site, acoustical, and thermal analyses, screening and monitoring, and Township review; the distance cannot be less than 500 feet. less than 1,000 feet

  • Cooling must be non-evaporative. Routine cooling or process water may not use groundwater, direct surface-water withdrawals, routine water imports or exports, once-through or open-loop cooling, or evaporative cooling systems; public water and public sewer are required, subject to stated exceptions for lawful zoning relief. Only air-cooled, closed-loop, or other non-evaporative cooling is permitted

  • Applicants must submit utility-load documentation and an engineer-certified energy plan. A utility determination that the requested service cannot be provided, or requires an improvement that violates the ordinance, requires denial; final utility authorization is required before the use-and-occupancy permit. Final utility authorization is required

  • The draft imposes objective operating limits, including noise and vibration standards and a prohibition on off-site thermal impacts at or above a one-degree-Fahrenheit increase; noncompliant nonemergency equipment must be reduced or suspended until compliance is demonstrated. shall not exceed 40 dBA and 50 dBC

  • Emergency generators may operate only during outages, legally required emergencies, or readiness testing. Fossil-fuel generator testing is limited to 100 hours per calendar year and 9 a.m.–3 p.m., Monday through Friday, excluding federal holidays. limited to 100 hours per calendar year

  • Applications require extensive technical submissions, including full-build-out studies and plans for energy, water, wastewater, traffic, thermal impacts, noise, emergency response, and decommissioning. The applicant must reimburse reasonable and necessary independent-review costs and provide or replenish escrow when authorized by law and the fee schedule. reimburse reasonable and necessary costs

  • Before normal operation, the project must demonstrate compliance and obtain zoning use-and-occupancy authorization. A temporary commissioning authorization may last no more than 60 days and is limited to startup and testing, not occupancy or commercial operation. no more than 60 days

  • The operator must install revenue-grade meters, record specified loads at intervals of no more than 15 minutes, retain records for five years, and submit an annual engineer-certified demand and efficiency report. intervals not exceeding 15 minutes

  • The draft requires a recorded decommissioning agreement and financial security set at 120% of an engineer-prepared cost estimate. The plan and security must be updated at least every three years and in specified circumstances, including when security will expire within 90 days. 120%

  • Construction is restricted to 7 a.m.–7 p.m., Monday through Saturday, excluding federal holidays; construction traffic generally may not use residential streets. Construction is limited to 7:00 a.m. through 7:00 p.m.

  • The draft creates a rebuttable abandonment presumption after 12 consecutive months without lawful operations, or with demand below 10% of approved demand and no active customer contract, computational operation, or regular staffing; abandonment triggers decommissioning requirements. 12 consecutive months with no lawful operations

Benefits & exceptionsHide benefits & exceptions8
  • The draft permits data centers by conditional use in the IR Industrial Research District, creating a defined approval route for them. Permitted only by conditional use in the IR Industrial Research District.

  • A data center may occupy a separately enclosed and secured premises inside a lawful multi-tenant building. For a qualifying existing building that is not enlarged, certain setbacks and separation distances may be measured from the premises’ perimeter rather than the whole building; the premises must remain physically separate, and its support areas count toward the size limit. A Data Center may occupy a Data Center Premises within a lawful multi-tenant principal building.

  • Conditional-use review may proceed concurrently with preliminary land-development review. If a proposal does not qualify as land development, it can proceed through conditional use with an existing-conditions and development-envelope plan instead; other permits and approvals still apply. When a proposal does not constitute land development.

  • The draft allows separation distances below 1,000 feet, down to an absolute minimum of 500 feet, if the applicant meets the enhanced technical and mitigation criteria. The conditional-use decision must set the greatest distance that permits a compliant full-buildout plan. 500 feet as the absolute minimum.

  • An energy-generation facility may be approved as an accessory use on the same consolidated lot, subject to a five-megawatt generation cap and the overall facility-demand limit. Qualifying rooftop or building-integrated solar and certain other renewable generation are excluded from the energy-generation-facility definition; emergency generators and batteries also have specified permitted roles and limits. An Energy Generation Facility may be approved only with, or by amendment to, a Data Center conditional use.

  • The draft permits emergency generators for bona fide outages, legally required emergency operation, and limited readiness testing; fossil-fuel testing is capped at 100 hours annually and restricted to specified weekday daytime hours. Batteries may support backup, ride-through, power quality, and on-site load management, subject to operating limits. Fossil-fuel generator testing is limited to 100 hours per calendar year.

  • A specific data-center standard would control over a conflicting general zoning standard on the same requirement, subject, or impact; independent requirements remain applicable. The draft also states that §150-215(F) does not apply to data centers or accessory energy-generation facilities. A specific standard in this Article controls over a conflicting general standard.

  • The draft allows principal data-center buildings up to 45 feet and accessory structures, rooftop equipment, screening, and energy-generation equipment up to 60 feet, subject to the stated legal exception. Accessory structures, rooftop equipment, screening, and Energy Generation Facility equipment shall not exceed 60 feet.

Sources

pending · Worcester Township
The Planning Commission recommended the ordinance on August 27, 2026, and the Board of Supervisors reauthorized its advertisement on September 16, 2026, but no hearing or adoption has been recorded.Worcester Township, Montgomery County — proposed data-center ordinance (None Adopted)

What this means

The proposal would impose setbacks from homes or other protected places, cooling and water-use rules and noise limits and sound testing. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.

Restrictions & requirementsHide restrictions & requirements36
  • Conditional use by the Board of Supervisors, §150-255(A); approval expires without a building permit within one year or a diligent land development effort within six months, §150-215.1 as cited in §150-271(A)

  • 500 ft minimum Separation Distance from residential uses and districts, 1,000 ft unless sealed noise and thermal modeling supports less, measured from buildings and all outdoor equipment, §150-257(B)-(C)

  • All other Chapter requirements stated to remain in effect and environmental constraints shown on the envelope plan; no riparian buffer, §§150-255(B) and 150-257(C)(1)

  • Conditional use amendment for a change over 10% in demand, energy source, substation, or phasing, §150-259(D); no generator, cooling, or battery triggers or like-for-like exemption

  • 45 dBA and 60 dBC by day, 40 dBA and 50 dBC at night as 15-minute Leq, Class 1 meters, §150-263(B)-(C)

  • 60 dBC by day and 50 dBC at night with one-third-octave low-frequency evaluation, §150-263(B)-(C)

  • Sealed predictive study and postconstruction study within 12 months, Class 1 meters, testing under Peak Operating Conditions, §§150-263(A)-(B) and 150-268(C)

  • Generator testing 9:00 a.m. to 3:00 p.m. weekdays, 100 hours per year, §150-258(B)

  • Peak particle velocity and VdB limits with three-axis vibration studies, §150-263(B) and (E)

  • Public water required and groundwater barred for cooling; any nonpublic source needs zoning relief and a safe-yield and nearby well study, §150-260(A)-(B)

  • Only air-cooled, closed-loop, or other non-evaporative cooling permitted, §§150-255(C) and 150-260(A)

  • Public supplier certifies capacity for full build-out; no water metering, reporting, or drought plan, §150-260(B)

  • Public sewer with authority capacity certification and untreated discharge barred, §150-261; no cooling or process discharge route or approvals before a zoning permit

  • Fire suppression and hazardous material containment must prevent off-site or groundwater discharge, §150-269(E); no added runoff treatment for fuel or transformer areas

  • Generators must meet federal and state emission rules with sealed air-emission analyses, §150-258(C); no Tier 4 requirement

  • Thermal study models property line effects with a 1.0°F limit and the plan quantifies heat recovered and recovery measures, §150-265

  • Plan for storage, removal, and disposal of computer equipment, batteries, and refrigerants, §150-269A; no disposal contract

  • Utility documentation of the filed service application with the application and final utility authorization before a zoning use and occupancy permit, §150-259(B)

  • Certified Energy Usage Plan with annual use, Maximum Facility Demand, PUE, and phasing, §150-259(A); no solar requirement or renewable incentive

  • Energy Generation Facility requires its own conditional use approval, setbacks, and buffer, §150-273; standards are tied to the data center rules rather than other generation uses

  • Applicant substations placed behind or beside the building and screened, utilities underground, §150-264

  • Battery storage must meet NFPA 855 as incorporated in the adopted code, §150-269(D)

  • Utility documentation must show required improvements, §150-259(B); no cost, tariff, or service agreement disclosure

  • 50 ft year-round buffer on every property line with dead plants replaced, §150-264A(A); below 100 ft

  • Outdoor equipment screened to equipment height or 12 ft, whichever is less, and generators in acoustic enclosures, §§150-258(D) and 150-264A(C)

  • Off-site-visible elevations and renderings required, §150-257A(A); no visual impact study

  • Emergency Response Plan reviewed by the Fire Marshal and fire department with posted 24-hour contacts, §150-269(A)-(C); no annual update or walk-through

  • Site-specific responder training before occupancy and annually at operator expense, §150-269(B); no specialized equipment requirement

  • Hazardous material quantities in the response plan and containment against off-site discharge, §§150-269(A), (E) and 150-269A; no storage setbacks or filed spill plan

  • Annual review by a Qualified Professional of fire code and plan compliance, §150-269(B); no report to the fire official or correction deadline

  • Traffic study in every case covering construction and full build-out, §150-262B(A); route reach not stated

  • Construction 7:00 a.m. to 7:00 p.m. Monday to Saturday and truck routes in a Construction Management Plan, §150-262; road security only for a residential route

  • Recorded agreement with 120% security, removal begun within one year and finished in 18 months, §150-270(B)-(E); no 6-month equipment removal

  • Estimate and security updated every three years with an index floor, §150-270(D); no update after the first year

  • Annual certified power demand and PUE reports and quarterly sound and thermal monitoring reports, §§150-257(C)(5), 150-259(C), and 150-263(F)

  • Applicant reimburses Township consultants reviewing its studies, with escrow, §150-267(A)

Benefits & exceptionsHide benefits & exceptions1
  • Proposed approval pathway: Proposed: conditional use in the IR Industrial Research District

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data