Willistown Township
Anti-Data Center Policies
Willistown Township’s enacted measure allows data centers only through conditional-use approval in qualifying office or industrial areas, with siting limits and requirements for studies, noise, water, backup generators, and shutdown. The description calls it proposed despite labeling it enacted.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Willistown TownshipCreates data-center zoning rules requiring conditional-use approval, minimum setbacks, and plans addressing energy use, water, noise, emergency response, electronic waste, and decommissioning.Willistown Township Zoning Ordinance Amendment (Proposed Ordinance 2026)
What this means
The measure would allow data centers through conditional-use approval, but only in qualifying office or industrial areas and with substantial siting limits, including distance requirements from sensitive receptors. Applicants would also face costly studies and plans, plus operating rules for noise, water use, backup generators, and eventual shutdown, creating significant barriers despite the new approval pathway.
People behind it
- Willistown Township Board of Supervisors
Identified in the ordinance as the body that enacted and ordained the measure.
Restrictions & requirementsHide restrictions & requirements17
Data centers are allowed only through conditional-use approval by the Board of Supervisors, following a public hearing; approval is not automatic. Conditional use approval process
The overlay is limited to qualifying parcels entirely in the Office or Restricted Industrial districts, held in single and separate ownership, with at least 3 acres and specified minimum widths of 350 feet at the building line and 300 feet at the street line. Qualifying conditions
Conditional-use applications require a development plan and studies addressing traffic, community impacts, and environmental impacts. The community study includes assessments of services, fire protection, waste, water, sewer, and stormwater; the traffic study must be prepared by a consultant hired by the applicant. Required application studies
The application must include detailed water and sewer assessments, and principal uses must use public water systems; the applicant must provide certified documentation that the public authority can supply the required water. Public water and capacity documentation
Data centers must take access from an arterial or collector road and provide secondary access suitable for emergency response. The application must also identify anticipated daily use by vehicles weighing over 20,000 pounds and the roads planned as access roads. Data center access requirements
Data center buildings, accessory uses, and truck-idling areas must be at least 250 feet from property lines, except utility lines, fiber-optic lines, and security stations. They generally must be at least 1,000 feet from residences, residential districts, and other sensitive receptors; that distance may be reduced to 500–999 feet only if the applicant demonstrates specified enhanced noise, screening, aesthetic, and thermal protections. Data center separation distances
The overlay limits building coverage to 25%, total impervious coverage to 50%, and building height to 35 feet. It also sets general building setbacks, including 75 feet from an arterial or collector street where that rule applies, and 100 feet from a residential district or use; a 35-foot boundary buffer must remain free of buildings, structures, and parking. Area, height, and buffer limits
Data centers must operate indoors in completely enclosed buildings. Outdoor storage is allowed only if located and screened to mitigate visual impacts, and outdoor storage of solid waste is prohibited. Indoor operations and outdoor storage
An engineer-certified Energy Usage Plan is required with the conditional-use application. It must address annual electricity demand, supply sources, storage, backup power, efficiency, and efforts to maximize renewable or clean energy. The plan must consider covering 50–80% of unused roof space with solar, exploring battery storage for 50–100% of onsite backup needs, supporting new renewable generation in the PECO region, and regularly reporting efficiency and emissions data. Grid-connected projects must document interconnection application and fee, receipt and signing of the transmission security agreement, and the utility’s proposed energization date. Energy Usage Plan requirements
An onsite electric substation must be in a side or rear yard, not the front yard, and screened from public view; if visible from an arterial roadway, screening must combine year-round opaque landscaping and screening walls. Substation siting and screening
Diesel backup generators must meet EPA Tier 4 standards and undergo annual testing, with reports submitted to the Township. Fossil-fuel emergency generation is limited to outages and maintenance or readiness testing capped at 100 hours per year; routine testing is restricted to 9 a.m.–3 p.m. Monday through Friday. Generators may not be used for peak shaving or supplying power to the grid. Backup generator limits
Data centers must use closed-loop water circulation for equipment cooling unless the applicant demonstrates to the Township engineer’s satisfaction that an alternative uses less water and energy. The application must disclose potential cooling-tower additives and assess impacts, and estimate supplemental water use and show it will not adversely affect surrounding properties or the community. Cooling and water-use requirements
An engineer-certified Thermal Impact Mitigation Plan is required with the application. It must identify waste-heat sources, assess off-site impacts in representative seasons, describe mitigation, evaluate waste-heat reuse, and provide monitoring if required by approval conditions. Thermal Impact Mitigation Plan
Applicants must submit an acoustical-engineer-prepared pre-construction noise study with baseline measurements and octave-band analysis. A post-construction study is due 1–12 months after the first certificate of occupancy; if it shows noncompliance with the baseline study, corrective measures are required. Noise must be measured at all property lines, with full-spectrum modeling for low-frequency noise; where baseline noise already exceeds the ordinance’s listed maximum, the data center may not exceed that baseline. Noise studies and compliance
An Emergency Evacuation or Response Plan is required with the application, including review and approval letters from the local fire department and emergency-management entity, fire and evacuation procedures, annual professional fire-safety inspections, emergency contact signage, radio-coverage coordination and any needed enhancements, and evidence of compliance with NFPA Standard 855 or similar standards for energy-storage systems. Emergency-plan requirements
The application must include an Electronic Waste Plan for safe removal, recycling, or disposal of servers, hazardous materials, batteries, and related products whenever equipment is updated or decommissioned. It must also include a qualified-professional-prepared decommissioning plan. Waste and decommissioning plans
If operations cease for more than one year, the owner must notify the Township within 30 days. Decommissioning must begin within one year of cessation, though the Township may grant up to a one-year extension if the owner is actively marketing the site for a compatible replacement use; completion is required within 18 months after work begins unless the Township grants an extension for good cause. Decommissioning requires equipment removal, lawful hazardous-material disposal, soil stabilization and revegetation, and safe disconnection and capping of utilities. Cessation and decommissioning deadlines
Benefits & exceptionsHide benefits & exceptions4
Data centers are expressly eligible for conditional-use approval in the C-1 overlay, which serves as an alternative to the underlying zoning rules. The tract must be entirely in an O or I district, under single ownership, at least three acres, and meet the width requirements; approval requires a public hearing and the specified application materials. Data Centers
The definition of data-center accessory uses expressly includes supporting infrastructure such as backup generators, electrical substations, utility and fiber-optic lines, cooling and wastewater facilities, and fire-suppression equipment. Ancillary uses or structures
The usual 1,000-foot separation from residences, residential districts, and other sensitive receptors may be reduced to 500–999 feet if the applicant demonstrates stronger environmental performance, including noise no greater than ambient levels, visual screening or aesthetic improvements, and no thermal air changes affecting the nearest receptors. This distance may be reduced
A data center may use a cooling system other than closed-loop circulation if the applicant demonstrates to the Township engineer that the alternative uses less water and energy than a closed-loop system. An alternative cooling system may be permitted
Sources
pending · Willistown TownshipThe township posted the full text on October 12, 2026 and included the unsigned ordinance in the packet for the Board of Supervisors' October 26, 2026 public hearing, and the outcome of that meeting has not been posted.Willistown Township, Chester County — proposed data-center ordinance (None Adopted)
What this means
The proposal would impose setbacks from homes or other protected places, minimum site-size requirements and limited eligible locations. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.
Restrictions & requirementsHide restrictions & requirements29
35 ft building height limit; rooftop equipment not addressed, § 139-195.B
Conservation Plan and Environmental Impact Study required; no data center riparian buffer, § 139-193.B(2) and E
Octave band limits at the receiving property line with a 10 dBA night reduction at residential uses; no overall dBA day and night limits, § 139-196.I
Where baseline exceeds the table limits, levels may not exceed the pre-construction baseline; impulsive sound capped at 20 dBA over ambient, § 139-196.I and § 139-196.W(8)(a)
60 dBC from 7:00 a.m. to 7:00 p.m. and 50 dBC at night, § 139-196.I
Pre-construction study with the application and post-construction study 1 to 12 months after occupancy; none at building permit, § 139-196.W(8)
Generator testing 9:00 a.m. to 3:00 p.m. Monday through Friday, capped at 100 hours per year, § 139-196.W(5)(c)
Public water required with certified documentation of supply capacity; no hydrogeologic study or pump tests, § 139-193.D(6)
Closed-loop cooling required unless an alternative uses less water and energy; cooling tower additives must be assessed, § 139-196.W(6)(a)-(b).
Projected water use and supplemental water estimates disclosed; no cap, reporting, or drought plan, § 139-193.D(6) and § 139-196.W(6)(c)
Water discharge and sanitary sewer assessments, including discharge temperature, § 139-193.D(6)-(7)
Diesel generators must meet EPA Tier 4 with annual testing reports to the Township, § 139-196.W(5)(a)-(b)
Thermal Impact Mitigation Plan including evaluation of waste heat reuse, § 139-196.W(7).
Electronic Waste Plan for servers, batteries, and hazardous materials, with refrigerants addressed at decommissioning, § 139-196.W(10) and (11)(c).
Utility interconnection application and transmission security agreement documentation required; no electrical inspection, § 139-196.W(3)(f)
Energy Usage Plan certified by an engineer; rooftop solar only to be considered, § 139-196.W(3)
On-site power generation and back-up power addressed in the Energy Usage Plan and noise study; not a separate use for data centers, § 139-196.W(3)(d) and (8)(a)
Substations in the side or rear yard and screened; burial of on-site lines not addressed, § 139-196.W(4)
35-ft boundary buffer within a 100-ft buffer yard next to residential uses, § 139-195.C(2) and D
Principal buildings must include architectural elements, articulation, or fenestration, § 139-193.D(1)
Substations screened; no all-sides, height, or acoustic screening standard, § 139-196.W(4)
Emergency plan approved by the fire department, with radio coverage and 24-hour contact signage; no annual updates, § 139-196.W(9)
Hazardous materials addressed in the Electronic Waste and Decommissioning Plans; no storage setbacks or containment, § 139-196.W(10)-(11)
Annual fire safety inspections, § 139-196.W(9)(d)
Section 139-193.C requires a Traffic Impact Study under Section 123-30.B assessing the impact on the road network and possible improvements, but it does not cover construction traffic or set a study area.
Decommissioning Plan, 30-day cessation notice, removal within 18 months of commencement; no financial security, § 139-196.W(11)
One post-construction noise study after occupancy, § 139-196.W(8)(b)
Applicant must bring the data center into compliance if the post-construction study fails; no specific penalties, § 139-196.W(8)(b)
Energy and thermal plans subject to Township review; cost not assigned to the applicant, § 139-196.W(3)(g) and (7)(f)
Benefits & exceptionsHide benefits & exceptions1
Proposed approval pathway: Proposed: conditional use in the C-I Overlay District (O and I districts)
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data