Williams Township
Anti-Data Center Policies
Williams Township’s enacted ordinance requires data centers to follow cooling and water-use rules, set aside money for eventual removal, and meet noise limits with sound testing. Projects can still be approved, but these requirements add costs.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Williams TownshipThe rules are in Ordinance No. 2026-3, which the Board of Supervisors enacted on October 14, 2026, according to the signed copy posted on eCode360, and which exempts generator testing and emergency use from the noise limits and does not set a cooling method, a buffer yard, or decommissioning security.Williams Township, Northampton County — data-center ordinance (No. 2026-3)
What this means
The measure imposes cooling and water-use rules, money set aside for eventual removal and noise limits and sound testing. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.
Restrictions & requirementsHide restrictions & requirements23
Impervious coverage capped at the lesser of the district limit and 60%; no campus footprint or megawatt cap, § 27-1402(67)(c)
200-ft building setback from all property lines only; no separate sensitive-use distance, § 27-1402(67)(c)
35 ft including rooftop units, elevator towers, and parapets, below the 60-ft GI district limit in § 27-1107.J, § 27-1402(67)(i)
Phased development allowed with a site plan for each data center; no demand by phase or expansion triggers, § 27-1402(67)(n)-(o)
General limits of 57 dBA day and 53 dBA night at residential lot lines, measured per ANSI S1.13-2020; higher than 50 and 45 dBA, § 27-1402(67)(d) and § 27-1511
Only a 5 dBA reduction for pure tones; no dBC or octave-band limits, § 27-1511.B
Predictive sound assessment by an acoustic engineer with the land development application; no post-opening study, § 27-1402(67)(d)
Sound from required generator testing and emergency use is exempt from the noise limits; no testing hours or cap, § 27-1402(67)(d)
Numeric ground displacement limits by frequency measured with a three-component system; no vibration study or stated measurement point, § 27-1402(67)(k)[2]
Public utilities required with a will-serve letter or capacity assessment; on-site wells allowed if public service is infeasible without a stated pump test, § 27-1402(67)(f)
DRBC approval for withdrawals of 100,000 gallons per day or more; no projected use disclosure, reporting, or drought plan, § 27-1402(67)(f)[3]
Public sewer service with a will-serve letter or capacity assessment; no cooling wastewater route, § 27-1402(67)(f)
Air Pollution Control Act, opacity limits, and federal NESHAP compliance; no Tier 4 requirement, § 27-1402(67)(k)[1]
Operations producing intense heat must be enclosed or fenced so heat is imperceptible beyond the lot lines; no thermal plan, § 27-1402(67)(k)[3]
Utility will-serve letter or professional capacity assessment for electric service; timing before a zoning permit not stated, § 27-1402(67)(f)[1]
On-site energy generation requires Fire Chief approval of a safety plan; not treated as a separate use, § 27-1402(67)(m)
Capacity assessment must identify utility constraints and the applicant pays for needed system improvements; no provider, cost estimate, or tariff disclosure, § 27-1402(67)(f)[2]
§ 27-1514 applies: shielded fixtures with 0.3 to 0.5 footcandle spillover limits at residential lot lines, § 27-1402(67)(j)
Only substations and service lines visible from homes must be concealed; other equipment screening not required, § 27-1402(67)(k)[4]
Safety plan for on-site energy generation and substations approved by the Fire Chief and recertified every year; no general emergency plan or 24-hour contacts, § 27-1402(67)(m)
Annual site inspection by the Fire Marshal for the on-site energy generation safety plan; no report or correction deadline, § 27-1402(67)(m)
Second emergency access with Fire Chief approval; no arterial or collector access requirement, § 27-1402(67)(h)
Construction hours of 7:00 a.m. to 7:00 p.m. Monday through Saturday; no haul routes or road bonding, § 27-1402(67)(l)
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Conditional use in the GI General Industrial District
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data