Whitemarsh Township

Anti-Data Center Policies

Whitemarsh Township allows data centers in six districts only with conditional-use approval, but 500-foot setbacks from protected places and strict energy, water, noise, emergency-planning, and closure rules limit where and how they can operate.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Whitemarsh Township
Limits data centers to conditional use in six zoning districts and requires safeguards for their location, energy and water use, noise, emergency response, and eventual decommissioning.Whitemarsh Township data center zoning ordinance

What this means

The measure allows data centers by conditional use in six districts, so it is not a ban, but strict siting rules—including 500-foot separation from sensitive places—limit where they can go (permitted only by conditional use; 500-foot setback). Detailed energy, water, noise, emergency-planning, and decommissioning requirements add substantial study, compliance, and operating burdens, making this a significant barrier to development (energy usage plan; noise limits).

People behind it

  • Held the public hearing, considered the ordinance, and approved it.

  • Collaborated on developing the draft regulations and recommended the ordinance.

  • Collaborated with the county and Planning Commission to develop the draft regulations.

Show 1 more peopleShow fewer people
  • Collaborated with Township staff and the Planning Commission on the suitability analysis and draft regulations.

Restrictions & requirementsHide restrictions & requirements18
  • Data centers require conditional-use approval and are allowed only in the AR, CLI, CLI-X, EX, HVY, and LIM zoning districts. permitted only by conditional use

  • Sites must meet the underlying district’s lot-area rules; a data center over 100,000 square feet must have at least 5 acres. Buildings and freestanding accessory uses are limited to 60 feet, including rooftop equipment, and the underlying district’s building-coverage and impervious-cover limits still apply. over 100,000 square feet

  • Principal buildings, accessory uses, and truck-idling areas generally must be 250 feet from property lines. Principal buildings and accessory uses must be at least 500 feet from residential districts, residentially zoned or used properties, and other sensitive receptors. minimum setback from sensitive receptors

  • A data center must access an arterial or collector road and provide secondary access suitable for emergency response. Parking is set at one space per employee plus five visitor spaces for a data center, and one space per employee for an accessory use. secondary access suitable for emergency response

  • Building design is subject to facade, material, color, entrance, and rooftop-equipment screening rules. Enclosing fences may be up to 10 feet tall, but fences over 6 feet must be set back at least half the applicable setback and screened from nearby residences, sensitive receptors, and public roads. fence up to 10 feet in height

  • A landscape buffer at least 50 feet wide is required next to residential districts, sensitive receptors, and public roads, with specified minimum quantities and sizes of trees and shrubs. Plantings must be replaced during an 18-month guarantee period if they die or become unhealthy or unsightly; the Township may credit adequate existing vegetation or topography toward the buffer. at least 50 feet in width

  • Projects must meet the current LEED v5 data-center rating system or an equivalent approved by the Township Engineer, and operators must annually report specified energy, water, renewable-energy, and carbon-use metrics. A professional engineer must prepare and certify an energy-use plan for conditional-use review; the Township may require supplemental or amended plans before zoning approval. LEED v5

  • The energy-use plan must address demand, supply, storage, critical functions, emergency curtailment, backup power, clean-energy measures, and—if connecting to the grid—utility interconnection documentation, including available capacity and anticipated energization timing. energy usage plan

  • Grid-connected projects must procure renewable generation from the PJM region: at least 10% of power for demand up to 50 MW, and at least 25% for demand over 50 MW. Procurement must use a power-purchase agreement or similar mechanism; renewable-energy credits alone do not qualify. minimum of 10% of its power

  • On-site generation serving normal operations is treated as an accessory use and remains subject to applicable Township, utility, state, and federal regulations. Applicants must document expected generation and excess power, which must be stored or supplied to the PJM grid; on-site power lines of 34.5 kV or below must be buried. supply power directly to a data center during normal operations

  • Battery storage must be prioritized before diesel backup. Diesel generators must meet EPA Tier 4 standards and undergo annual testing with reports to the Township. Fossil-fuel backup may operate during an emergency outage only to support critical functions, or for maintenance/readiness testing capped at 100 hours annually; testing is limited to 9 a.m.–3 p.m. Monday through Friday, with at least 72 hours’ advance notice. Backup generation cannot be used for peak shaving or to supply the grid. capped at 100 hours per year

  • If public water is available, private groundwater wells or direct surface-water withdrawals cannot be the primary cooling-water source. Cooling must use a closed-loop system unless the Township Engineer accepts an alternative shown to use less water and energy. Public suppliers must certify capacity; nonpublic sources require a professional water feasibility study, and proposed groundwater wells trigger notice to nearby private-well users within 1,000 feet. closed-loop water circulation system

  • Applicants must submit a drought-response plan and analyze wastewater needs. Public wastewater systems must document capacity; private disposal requires a feasibility study. Untreated wastewater may not be discharged to stormwater systems or surface waters, and required state and regional permits must be obtained before permits are issued. No permits shall be issued until

  • A professional engineer must prepare and certify a thermal-impact mitigation plan for conditional-use review. It must evaluate off-site heat effects and mitigation, including feasible waste-heat reuse; the Township may require changes or supplemental plans before zoning approval. thermal impact mitigation plan

  • Applicants must provide pre-construction and post-construction noise studies, including low-frequency analysis and measurements at property lines. Limits are 40 dB(A)/50 dB(C) overnight and 45 dB(A)/60 dB(C) during the day; where baseline noise is already higher, the project generally cannot increase it above baseline. Sound levels at the property line shall not exceed

  • A qualified professional must prepare an emergency-response plan for conditional-use review. It must be acceptable to specified Township and emergency-service officials, address hazards and response procedures, and provide annual first-responder training and facility walkthroughs at the applicant’s expense, plus annual fire-safety inspections and maintenance reports. Battery energy-storage systems must demonstrate compliance with NFPA 855 or similar standards and have dedicated fire suppression. annual training specific to the installed system

  • Conditional-use applications must include an electronic-waste plan covering safe removal, recycling, and disposal of servers, batteries, hazardous materials, and related products; the Township may require supplemental or amended reports before zoning approval. electronic waste plan

  • Applicants must submit a decommissioning plan. After operations cease or the operator gives notice of abandonment, decommissioning must begin within one year; the Township may grant a one-year extension if the owner is actively marketing the site for a compatible replacement use. Work must then be completed within 18 months, unless the Township extends the deadline for good cause, and the property owner bears the costs. Decommissioning shall begin within 1 year

Benefits & exceptionsHide benefits & exceptions6
  • Data centers may seek conditional-use approval in six districts: AR, CLI, CLI-X, EX, HVY, and LIM. This authorizes the use in those zones, subject to conditional-use review and the ordinance’s standards. Permitted only by conditional use

  • The ordinance treats normal-operation energy generation as a data-center accessory use and identifies related infrastructure—including substations, utility lines, cooling facilities, and backup generators—as accessory uses when located on the same tract or a unified development of adjacent parcels. Energy generation systems

  • The 250-foot property-line setback does not apply to utility lines or fiber-optic lines, allowing those connections closer to property boundaries. Exceptions of utility lines

  • A data center may use an alternative to the required closed-loop cooling system if the Township Engineer is satisfied that it uses less water and energy. Alternative cooling system

  • Existing topography or vegetation may count for some or all of the required landscape buffer if the Board of Supervisors, on the Shade Tree Commission’s recommendation, finds it adequate to meet the screening intent. Existing topography and/or vegetation

  • Fossil-fuel backup generation is allowed during an emergency outage to support critical functions, and for routine maintenance or readiness testing capped at 100 hours per year. Testing is limited to 9 a.m.–3 p.m. Monday through Friday, with at least 72 hours’ notice to the Township; peak shaving and supplying power to the grid are prohibited. Backup energy generation

Sources

current law · Whitemarsh Township
The Board of Supervisors approved the amendment as Ordinance 1059 by a 5 to 0 vote on September 10, 2026, according to the meeting minutes, and the text it considered is posted in that meeting's agenda packet.Whitemarsh Township, Montgomery County — data-center ordinance (No. 1059)

What this means

The measure imposes setbacks from homes or other protected places, cooling and water-use rules and noise limits and sound testing. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.

Restrictions & requirementsHide restrictions & requirements29
  • Conditional use decided by the Board of Supervisors, § 329; no one-year expiration of approval

  • Building coverage limited to the underlying district maximum, § 330.B(5); no footprint or megawatt cap

  • Tree Protection Standards of Chapter 55 stated as applying, § 330.D(1)(f); no riparian buffer

  • Section 330.J(2)(a) sets 45 dBA from 7:00 a.m. to 7:00 p.m. and 40 dBA from 7:00 p.m. to 7:00 a.m. at the property line, and Section 330.J(1)(c) requires measurement at all property lines with full spectrum modeling, but no metric, meter class, or measurement standard is stated.

  • Where baseline ambient exceeds the limits, levels may not exceed the baseline, § 330.J(1)(d) and J(2)(b); no general cap above background

  • 50 dBC at night and 60 dBC by day, § 330.J(2)(a)

  • Pre-construction study and post-construction study 1 to 12 months after the first certificate of occupancy, § 330.J(1)(a) and (b); none at building permit

  • Baseline vibration levels and mitigation in the noise study, § 330.J(1)(a); no standard that vibration not be perceptible

  • Closed-loop cooling required, with an alternative allowed if it uses less water and energy, § 330.H(2); evaporative cooling not expressly restricted

  • Section 330.H(6) requires a drought response plan showing compliance with state, water supplier, and local drought declarations, but Section 330.E(2) requires only annual reporting of the Water Usage Effectiveness ratio under ISO/IEC 30134, not metered water volumes reported to the Township.

  • Section 330.H(7) requires an analysis of sewage and HVAC wastewater disposal with either certification from the public authority that it can convey and treat the flow or a wastewater feasibility study for a private system, and Section 330.H(5) bars any permit until all required PADEP, SRBC, and DRBC permits are obtained.

  • Diesel generators must meet EPA Tier 4, with annual testing reports to the Township, § 330.G(2) and (3)

  • Thermal impact mitigation plan including evaluation of waste heat reuse, § 330.I.

  • Electronic waste plan for removal and recycling of servers, batteries, and hazardous materials, § 330.L, with refrigerants addressed at decommissioning, § 330.M(4)(b).

  • Utility documentation of available capacity before zoning approval, § 330.E(3)(f); no third-party electrical inspection.

  • Energy usage plan required, § 330.E(3); rooftop solar only to the greatest extent feasible, with renewable procurement of 10 or 25 percent off site, § 330.E(4)

  • Energy generation for normal operations is an accessory use subject to siting rules, § 330.F(1) to (3); no separate approval

  • Substations to the side or rear and screened, and on-site lines of 34.5 kV and below buried, § 330.F(4) to (6)

  • 50 ft landscape buffer next to residential districts and sensitive receptors, § 330.D(1)(b)

  • Facade offsets every 150 ft, material and color limits, and entrance standards, § 330.C(1) to (5)

  • Roof-mounted equipment screened from ground level, § 330.C(7); no all-sides acoustic screening of ground equipment

  • Elevations and renderings of facades visible from off site required, § 330.C(6); no visual impact study

  • Emergency plan reviewed by the fire department and others, 24-hour contacts, and in-building radio coverage, § 330.K(1) to (3); no annual plan updates

  • Emergency plan must cover hazardous materials, § 330.K(1)(c); no storage setbacks or spill containment

  • Annual fire safety inspections by the Fire Marshal, § 330.K(1)(e); no third-party electrical inspection

  • Decommissioning plan, notice of closure, and completion within 18 months after it begins, § 330.M; no financial security

  • Annual reporting of PUE, WUE, REF, and CUE, and annual energy and emissions reports, § 330.E(2) and E(3)(e)[5]

  • Noise increase above baseline deemed a violation, § 330.J(1)(d); no specific penalties

  • Township review of plans and studies and a Township landscape architect, § 330.D(1)(g) and E(3)(g); cost not assigned

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Conditional use in six districts

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data